FA255024Q0024_Delta 8 B300 SST COOP Conduit Install_QnA.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Delta 8 B300 Conduit Install
- Solicitation number
- FA255024Q0024
About this file
This document is a Question and Answer (Q&A) sheet related to the Solicitation Number FA255024Q0024 for the Delta 8 B300 Conduit Install project. The project requires the installation of (2) 2" rigid conduits with sealed fittings, approximately 250 feet of 2" x 4" wire basket tray, a ground system, and (3) wall-mounted cabinets with fiber optic LIUs. It also includes the procurement of necessary equipment and cleanup/trash removal. The Q&A addresses various requirements and specifications, such as the preferred conduit and grounding system, raceway sizes, wall penetrations, staging areas, and cabinet details. No wage determination or weekly certified payroll reports are required for this project. The Q&A sheet indicates that all answers will be posted to the solicitation on SAM.gov on July 24, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW SST COOP PDS 29 July 2024.pdf | ||
| PWS SST COOP PDS 26 July 2024.pdf | ||
| FA255024Q0024_Delta 8 B300 SST COOP Conduit Install_QnA Revised.xlsx | XLSX spreadsheet | |
| Room 246 option A.pdf | ||
| Room 242.pdf | ||
| Room 243 V2.0.pdf | ||
| Building 300 8 CTS training coop-JT.pdf | ||
| SOW SST COOP PDS_27JUN2024.pdf | ||
| Delta 8 B300 Conduit Install_Solicitaion Combo.pdf | ||
| Attachment 1_Provisions and Clauses.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FA255020Q0024 Delta 8 B300 SST COOP Conduit Install | ||
| QUESTIONS | Date Received | ANSWERS |
| 1. Are pathways to be used free, straight, and clear for the to-be-installed PDS and cable trays? | 18-Jul | Assume no, You were given the opprotunity to inspect above the ceilings during the site walk. |
| 2. Is there a requirement to weld, compression seal, or chemically seal the PDS? | 18-Jul | Chemically seal is prefered |
| 3. Is there an existing building ground to be tied to? | 18-Jul | Yes in the electrical room |
| 4. Are wall penetrations already installed? If not, we need wall type details, such as standard drywall, Kane screened, SCIF rated .... | 18-Jul | Standard drywall metal studs |
| 5. Will answers to all questions be posted to bidders? | 18-Jul | Yes, answers will be posted to the solicitation on SAM.gov on Wednesday, 24 July, 2024 |
| 6. Are there is requirement to cable each workstation pictured in the provided documentation. | 18-Jul | No that is being taken care of separately |
| 7. Requirements/Purpose: “Installation of (2) 2” rigid conduit with sealed fittings”. Is Rigid Conduit with epoxy sealed fittings acceptable for this requirement? | 18-Jul | Yes |
| 8. It the 2” rigid conduit above or below the drop ceiling in the hallway? | 18-Jul | Above |
| 9. Requirements/Purpose: “Installation of ground system to include convenance, ground bar, and grounding of pathways” Can the government please explain the ground system – wire size, location, connect to building steel, water pipe, etc. | 18-Jul | The expectation is the installer will determine the design of the ground system to meet the appropriate need and building code standards. This cable tray will be housing CAT5 and CAT6 Plenum rated cable based on the room layouts referenced in the SOW. My understanding is the ground system will be connected to building steel inside the electrical room located on the south east side of the building. |
| 10. Can the government please provide information on the (3) wall-mounted cabinets? Make, model, etc. | 18-Jul | Yes locking and yes swinggate. Please see attached spec sheet for dimentions. |
| 11. Can the government provide raceway size from cabinets to cable trays? | 18-Jul | 4inch width is acceptable |
| 12. Paragraph 4.3 - is this the only requirement on this project? Are all other paragraphs part of a different solicitation? | 18-Jul | Paragraph 4.3 is not the only requirement. You will abide by the entire SOW. |
| 13. Is there a current Wage Determination for use with this project? | 18-Jul | No, there is not. |
| 14. Are weekly certified payroll reports required? | 18-Jul | No, they are not required |
| 15. What is the preferred path of travel for fiber to individual rooms? | 18-Jul | Throught the PDS into apporpriate raceway and cable manegment |
| 16. Can we receive pictures above the tiles to discern if the space is congested in each room? | 18-Jul | Assume congestion, no pictures are authorized. You were given the opprotunity to inspect above the ceilings during the site walk. |
| 17. Is it preferred to have the cable tray above or below the tiles to facilitate the drops? | 18-Jul | Above the ceiling as it will conflict with modular wall. |
| 18. Is the preference to hammer drill a cable tray or is it preferred to have it anchored? Any noise constraints? | 18-Jul | No noise constraint. No preference |
| 19. Will a staging area be assigned for the materials? | 18-Jul | Room 242, 243, 246, and 248 can all be used for staging |
| 20. Specifications on the cabinets -will it require locking mech and or swing gate? | 18-Jul | Yes locking and yes swinggate. Please see attached spec sheet for dimentions. |