Site Visit Results Q A
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wall_Illustration.docx | DOCX document | |
| Updated_Site_Visit_Q A.docx | DOCX document | |
| Shoothouse_directional_layout.pdf | ||
| Updated_Site_Visit_Q A.docx | DOCX document | |
| Revised_Bid_Schedule.pdf | ||
| SOW_SFS_Shoothouse_03_Sep_14.pdf | ||
| SFS_Shoot_House_Bid_Schedule.pdf | ||
| SOW_SFS_Shoothouse_07_Aug_14.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA2550-14-R-2007 SFS Shoot House Site Visit Q&A 27 August 2014
Q1: What type of materials are the walls required to made from?
A1: A specific material isn’t suggested as long as it meets the requirements identified within the SOW, UFC documents. However, no combustable materials are required per fire code. Modification to SOW will reflect.
Q2: Is a replacable exterior facia required for the walls/doors?
A2: If the walls/doors are made of a material that is capable of withstanding the requirements identified within the SOW without showing any signs of wear then the answer is “no”, if the material is expected to show wear then a replaceable exterior facia is required.
Q3: What is the height of the exterior walls?
A3: The wall will be eight (8) feet tall. The grid system will be located above the eight foot walls.
Q4: How is the catwalk to be supported?
A4: The catwalk can be supported via collums located at the intersecting points of the catwalks.
Catwalk may also be supported by rafter/truss componets located on top of requested room that are being utilized to suspend the grid system inside.
Q5: Can portable heaters be utilized within the building?
A5: Yes, they must be UL listed, and are equipped with a "tip switch" that automatically shuts down the heater if it is turned over. Contractor must ensure that fuel supplies for gas fired heaters comply with NFPA 1: 16.2.1.4 (Fuel supplies for liquefied petroleum gas-fired heaters shall comply with NFPA 54).
Q6: What is the work schedule for installation?
A6: The contractor can determine their own work schedule as long as final installation meets the time requirements.
Q7: Can progress payments be utilized?
A7: Progress payments will not be utilized, however a modification to the solicitation has been made that will separate the purchase/delivery of the commerical items requested apart from the labor costs involved in installation. This will allow contrators to request payment on line items upon completion.
Q8: Will other agencies be using this facility?
A8: If memorandum of agreements with other agencies are completed then “yes” other agencies may use the facility. At this time no such agreements exist and the requesting agency will retain sole usage.
Q9: Can the grid system walls be secured to the floors if a spring loaded dust shield is installed in the floor to prevent clogging and tripping hazards?
A9: Yes, if this type of configuration is used then the walls can be secured utilizing a pin/hole locking method.
Q10: Can building “As Builts” be provided prior to the start of work?
A10: As builts can be provided upon request if available.
Q11: What is the requested width of the catwalk?
A11: 36 inches or three (3) feet.
FA2550-14-R-2007 SFS Shoot House Site Visit Q&A 27 August 2014
Q12: Are Navy Stairs acceptable as a form of stariway?
A12: Yes.
Q13: Should be camera system contain a recording device?
A13: Yes, the camera system must be capable of recording.
Q14: Are sway cables authrozied to be attached from the exterior walls and exisiting building structures?
A14: No, the overhead rafter/tuss system built into the requested room will provide sway prevention.
Q15: How thick it the concrete slab?
A15: Four (4) inches thick.
Q16: Is it acceptable for the overhead grid system to be made of aluminum? Steel is mentioned in SOW A16: Yes, aluminium is acceptable, a modification to the SOW will reflect change.
Q17: Modular windows. Please confirm (5) modular panels with windows, NOT (40)?
A17: Follow the bid schedule, a modification to the SOW will reflect change. Five (5) is the correct number.
Q18: Are designs required in the technical evaluation section of quotes?
A18: Designs will be used to ensure all referenced specifations are met.
Q19: Width of unit when counting the 4x4 squares shows 44’. Please confirm 40’ is accurate?
A19: 40’ is accurate.
Q20: Only 10 cameras shown on plan, confirm 10 or 11 cameras needed?
A20: 11 cameras are needed.