This document contains questions and answers regarding Solicitation Number FA252124R0008 for the Simplified Acquisition Base Engineering Requirements (SABER) program. The SABER program is utilized by the 45th Civil Engineering Squadron to expedite design efforts and accomplish minor construction, maintenance, and repair projects supporting the mission of Space Launch Delta 45 at Patrick Space Force Base, Cape Canaveral Space Force Station, and other Geographically Separated Units. Offerors must submit a bid guarantee or bid bond with their proposal, and provide evidence of bonding capability. Past performance will be evaluated in accordance with the solicitation. Pricing should be provided using coefficient or adjustment factors applied to the estimated workload values for the base period and option years as shown in the Standard Form 1442. Field overhead and insurance costs should be included in the pricing calculation. Self-performed trade work will not be evaluated against a unit price book.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 7

FA252124R0008 Simplified Acquisition of Base Engineering

Requirements (SABER)

QUESTION AND ANSWER TEMPLATE

RFP Section __I_______ Paragraph _52.228-1 Bid Guarantee

SOW Paragraph __N/A______

Other (Specify) ___________________________

Question 1:

Section I – Contract Clauses states the Offeror shall” furnish a bid guarantee in the amount of 20 percent of the bid price or $3 million, whichever is less”, however Section L only references the requirement of a bonding capability letter, not a bid bond. Is the offeror required to submit a bid bond or just a capability letter from its broker? If a bid bond is also required, please advise which volume it should be placed in.

Response: A bid guarantee is required per FAR 52.228-1. A letter from a surety attesting to bond capability is also required.

RFP Section _L_________ Paragraph _1.2.4.6_

SOW Paragraph __ N/A _________

Other (Specify) Past Performance Questionnaire

Question: 2

If a CPARS currently exists for a project identified on Attachment 8 Fact Sheet, will USAF allow it to be provided in lieu of a Past Performance Questionnaire? Many clients will not complete a PPQ if a CPARS already exists.

Response: The government will evaluate Past Performance in accordance with Section L and Section M.

RFP Section ___B_______ Paragraph ________

SOW Paragraph __N/A_________

Other (Specify) Supplies or Services & Prices or Costs Matrix

Question 3:

Should we assume that the “Estimated Quantity” and “Unit Price” column titles in Section’s B

Matrix of the Standard Form 1442, be understood as: “Estimated Workload Value” and

“Coefficient/ Adjustment Factor” respectively? If not, please clarify what is the quantified amount in front of each contract line-item number, as well as the unit price information that should be accounted for to complete the above-mentioned matrix.

Response: Yes.

RFP Section ___I_______ Paragraph ________

SOW Paragraph __N/A_________

Other (Specify) Contract Clauses – FAR Clauses Incorporated by Full Text

Question 4:

Are field overhead expenses (management and supervision), liability insurance and workers compensation premiums, included within the base and year options estimated workload values, or should we account for these expenses to be included in the calculation of our proposed coefficient/adjustment factor in addition to home office overhead, profit, performance and payment bond fees?

Response: The coefficient/adjustment factors are dependent on the estimating software you intend to propose on this SABER contract. See Section L, para 1.2.3.2.

RFP Section ___F_______ Paragraph ________

SOW Paragraph __N/A_________

Other (Specify) Deliveries or Performance

Question 5:

If the answer to Question 4 is that field overhead expenses must be included within the calculation of our proposed coefficient/ adjustment factor, then should we assume that the base and year options for all contract line-item numbers will be performed concurrent within the 120 calendar-days performance period allotted after the completion of lead item events, or should we account for a continuous and uninterrupted full-time representation to perform the different construction line-item numbers during the base and year options?

Response: Refer to page 1 Box 11 of the SF 1442 & Section F of the SF 1442.

RFP Section ___G_______ Paragraph ________

SOW Paragraph __N/A_________

Other (Specify) Contract Administration Data

Question 6:

Will self-performed trade work costs be evaluated by comparison to a unit price book, or in accordance with subcontracting costs procedures? If self-performed trade work will be evaluated against a unit price book, then please provide the database name that will be used for evaluation purposes.

Response: No, the government will use the same estimating software as the offeror who proposed the best value to the government.