Attachment 11 - Answers to Questions dated 17 Aug 22.pdf

PDF 169 KB Posted

Attached to
Replace HVAC Controls Facilities 1068 & 60680 Federal contract opportunity
Solicitation number
FA252122B0012
Issued by
Department of the Air Force Space Command

About this file

This document provides answers to contractor questions regarding Solicitation Number FA252122B0012 from the Department of the Air Force Space Command. The solicitation seeks a firm-fixed price construction contract to replace HVAC controls at Facilities 1068 and 60680 located at Cape Canaveral Space Force Station in Florida. The project scope involves replacing existing controls with new SmartStruxure Automation Servers to connect the facilities to an upgraded EMCS server. The period of performance is 364 days. The acquisition is set aside for Service-Disabled Veteran Owned Small Businesses. Existing relays, switches, dampers and actuators can be reused if functional, otherwise replacements are required. New sensors for temperature, humidity and pressure are also required. Pneumatic actuators at Facility 60680 must be upgraded to electric. The government prefers air flow calibration by a testing and balancing contractor but default parameters are acceptable if none is used. Manual overrides are required for all plant level DDC controllers.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS & ANSWERS 17 Aug 22

Solicitation: FA252122B0012 Project Number: DBEH 22-1582

Project Description: Replace HVAC Controls Facilities 1068 & 60680, Cape Canaveral Space Force Station, FL 32925

1. You are requesting a bid guarantee in the amount of 100% of the bid price. Normally, Bid

Bonds are for 20% of the bid amount not to exceed $3,000,000.00. Performance and Payment bonds are for 100% of the contract price. Will you clarify how much the bid guarantee is supposed to be?

Answer: Solicitation Amendment 0003 corrected the bid guarantee to 20% of the bid price or $500,000, whichever is less.

2. The current lead time for DDC Controllers is 26-30 weeks or more. Can the performance period be extended to at least 52 weeks?

Answer: Solicitation Amendment 0004 included an updated Statement of Work with a period of performance of 364 days.

3. Please confirm that no new DDC control points are required. The upgrade scope is like-for-like with no new control points.

Answer: No new DDC control points are required, except for hangar AE. The government requests the chiller plant controller to have additional spare points for future automatic valves on the cooling towers.

4. Please confirm that existing control relays and status switches can be reused.

Answer: All existing relays and status switches can be reused if functional.

5. Please confirm that duct and space temperature and humidity sensors shall be provided new.

Answer: All sensors will be new.

6. Please confirm that duct and space pressure sensors shall be provided new.

Answer: All sensors will be new

7. Please confirm that existing dampers can be reused.

Answer: Existing dampers can be reused. However, if any non-functional dampers are to be found, the government requests notification in order to have repaired in house.

8. Please confirm that existing electric actuators for dampers and valves can be reused.

Answer: Existing actuators for dampers can be used as long as functional. Replace any defective actuator.

9. Building 60680 has pneumatic actuators for dampers and control valves. Shall the pneumatic actuators be upgraded to electric actuators?

Answer: Yes, convert to electric actuators.

10. Can the existing BAS enclosures and transformers be reused if found to be in good condition?

Answer: BAS enclosures and transformers can be reused.

11. Building 60680 has a DCX-250 Display that is no longer supported and has no replacement part. Confirm that access to the facility will be from the new BAS workstation only.

Answer: The DCX-250 will not be used. There is a LAN drop that was installed for connection to the EMCS server.

12. Several buildings require the removal and replacement of the VAV Terminal Box DDC controllers. The calibration of the VAV air flow sensor resides within the existing DDC controller and will be lost when the controller is replaced. Please verify if the new VAV Controller should be calibrated by a Test & Balance contractor or if the initial default parameters of the new VAV controller will suffice.

Answer: The government’s preference is to have a T&B contractor provide the air flow settings. However, if no T&B contractor is used, then the default parameters will suffice.

13. Please verify that local override should be provided for all Plant Level DDC Controllers for AHU’s, Chillers, and Boilers.

Answer: All outputs on the DDC controllers will have manual override switches.

14. Please confirm that existing power meters are not to be integrated into the BAS System.

Answer: The existing power meters are not part of this project and will not be integrated into the BAS system

Project Description: Replace HVAC Controls Facilities 1068 & 60680, Cape Canaveral Space Force Station, FL 32925