THE PURPOSE OF THIS AMENDMENT IS TO ADD THE NEW DAVIS BACON WAGE RATES THAT BECAME EFFECTIVE 16 SEPTEMBER 2011.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA2521-11-R-0023-0005.pdf | ||
| 11-R-0023-04.pdf | ||
| PAVING IDIQ SOLICITATION Q A VOLUME 2.docx | DOCX document | |
| FA2521-11-R-0023 Amendment 2.pdf | ||
| 01 SOLICITATION Q A PAVING IDIQ.docx | DOCX document | |
| FA2521-11-R-0023-0001.pdf | ||
| PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| Attachment 1 Paving IDIQ Pricing schedule.docx | DOCX document | |
| Paving IDIQ Solicitation.pdf | ||
| Attachment 2 Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
THE PURPOSE OF THIS AMENDMENT IS TO ADD THE NEW DAVIS BACON WAGE DETERMINATION, EFFECTIVE 16 SEPTEMBER 2011. ALL OFFERORS ARE REQUIRED TO ADHERE TO THE NEW WAGE DETERMINATION AS IT WILL APPLY TO ANY RESULTANT CONTRACT.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Sep-2011
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA2521-11-R-0023
X 9B. DATED (SEE ITEM 11)
19-Aug-2011
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Sep-2011
CODE
45 CONS/LGCAC
14640 HANGAR ROAD
CCAFS 1704 ROOM 2102B MS2037
PATRICK AFB FL 32925-2206
FA2521 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA2521-11-R-0023
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION H - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
DAVIS BACON WAGE DETERMINATION
General Decision Number: FL100017 09/16/2011 FL17
Superseded General Decision Number: FL20080017
State: Florida
Construction Types: Building, Heavy and Highway
County: Brevard County in Florida.
**CAPE CANAVERAL AIR STATION, PATRICK AIR FORCE BASE KENNEDY
SPACE CENTER AND MALABAR RADAR SITE IN BREVARD COUNTY BUILDING
CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and partments up to and including 4 stories) HEAVY AND HIGHWAY CONSTRUCTION
PROJECTS
Modification Number Publication Date 0 03/12/2010 1 04/23/2010 2 09/03/2010 3 09/10/2010 4 10/29/2010 5 11/12/2010 6 12/17/2010 7 12/31/2010 8 01/21/2011 9 04/01/2011 10 07/22/2011 11 09/16/2011
ASBE0067-001 01/01/2011
Rates Fringes
Asbestos Workers/Insulator (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems).........................$ 24.62 10.49
ASBE0067-002 07/01/2009
Rates Fringes
HAZARDOUS MATERIAL HANDLER
(Includes preparation, wetting, stripping, removal, scrapping, vacuuming,bagging, and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not).........$ 24.87 10.10
BOIL0199-001 01/01/2009
Rates Fringes
BOILERMAKER......................$ 27.63 13.96
All other work..............$ 25.13 13.96
BRFL0001-001 05/01/2010
Rates Fringes
BRICKLAYER (BRICKLAYERS,
BLOCKLAYERS, PLASTERERS,
TERRAZZO WORKERS, TILE
SETTERS AND CEMENT MASONS)
COMMERCIAL..................$ 18.50 6.00
INDUSTRIAL..................$ 23.15 7.85
INDUSTRIAL work includes: Bulk plants, power houses, chemical plants, missile sites including all work at Cape Canaveral Air Force Station and Kennedy Space Flight Center.
CARP1000-001 07/01/2008
Rates Fringes
MILLWRIGHT.......................$ 26.93 10.49
* CARP1765-001 05/01/2008
Rates Fringes
Carpenters:
*INDUSTRIAL:
CARPENTERS.................$ 23.96 7.21
PILEDRIVERMEN..............$ 21.75 8.65
COMMERCIAL:
CARPENTERS.................$ 22.46 7.21
PILEDRIVERMEN..............$ 21.75 8.65
ELEC0222-001 09/01/2009
Line Construction:
CABLE SPLICER...............$ 33.86 4.75+23%
GROUNDMAN...................$ 18.38 4.75+23%
LINEMAN; HEAVY EQUIPMENT
OPERATOR....................$ 32.25 4.75+23%
ELEC0756-001 09/01/2010
Rates Fringes
Electricians:
Cable Splicer...............$ 27.75 6.45+4.4% Wireman.....................$ 27.75 6.45+4.4%
ELEV0139-001 01/01/2011
Rates Fringes
ELEVATOR MECHANIC................$ 36.33 21.785
FOOTNOTE:
A. Employer contributions 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; Employer contributions 6% of regular hourly rate to vacation pay credit for employee who has worked in business less than 5 years.
Paid Holidays: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; The Day After Thanksgiving and Christmas Day.
ENGI0673-001 05/01/2010
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 23.25 8.80
GROUP 2.....................$ 22.45 8.80
GROUP 3.....................$ 20.91 8.80
GROUP 4.....................$ 19.27 8.80
POWER EQUIPMENT OPERATORS
CLASSIFICATIONS GROUP 1: Tower Crane, Locomotive Crane, Crawler Crane, Truck Crane, Hydro Crane, Piledriver (incluidng auger and boring machine)
GROUP 2: Mechanic/Welder and operators of: Gantry Crane, Bridge Crane, Clam Shell, Dragline, Backhoe, Gradeall, Grader, Sideboom Cat, Hulti-Drum Hoist, Highlift (10' or higher), Locomotive Engineer, Tugboat Captain (150 hp or more), Concrete Pump with boom
GROUP 3: Bulddozers, Forklifts, Straddle Buggy, Single Drum Hoist, Winch Truck, Trenching Machine, Concrete Paver, Scraper, Loader, Asphalt Paving Machine, Lubricating Engineer, Fireman, Concrete Breaking Machine, Concrete Mixer
GROUP 4: Tractors, Wellpoint System Operator and Installer, Air Compressor, Pulver Mixer, Motor boat, Power Boat, Power Sweeper, Welding Machine, Oiler, Mechanic's Helper, Pump, Conveyor, Roller, Watertruck, Asphalt distributor, Concrete Pump (trailer type), Utility Operator
IRON0808-001 07/01/2009
Rates Fringes
IRONWORKER.......................$ 24.28 9.95
LABO0517-001 05/01/2008
Rates Fringes
Laborers:
Asbestos Abatement, Hazardous and Toxic Waste Removal Laborers; (On all mechaincal systems: Lead Base Paint Removal;pipes, boilers, ducts, flues, breechings, ect.; that are going to be scrapped, the removal of all insulating materials whether they contain asbestos or not shall be the exclusive work of the laborers;.......$ 17.50 5.47 Carpenter Tender, Cement Mason Tender, Block/ Bricklayer Tender Plasterer Tender............$ 17.50 5.47 Demolition Laborers.........$ 17.50 5.47 General Laborer.............$ 17.35 5.47 Pipelayer Laborer, Laborer engaged in the pouring of concrete, mortar mixers, masonry forklift operator, and operation of power tools.......................$ 16.32 5.47
PAIN0078-001 08/01/2010
Rates Fringes
GLAZIER..........................$ 22.00 8.10
PAIN0078-002 01/01/2010
PAINTER..........................$ 23.25 9.95
PLUM0295-001 01/01/2011
Rates Fringes
Plumber/Pipefitter/Steamfitter INDUSTRIAL: Bulk Plants, Power-houses, Chemical Plants, Missile Sites, (Including all Work at Cape Canaveral Air Force Station and Kennedy Space Flight Center but excluding work performed at Patrick Air Force Base and Malabar Radar Site), Oil Refineries, etc., and such other wirk which is related to and considered a part of the above type projects....................$ 32.13 14.87 Schools, Hospitals, Shopping Centers, and work not listed as Industrial....$ 32.13 14.87
ROOF0103-001 02/01/2003
Rates Fringes
ROOFER, Including Built Up, Composition and Single Ply Roofs............................$ 14.50 5.10
* SFFL0821-002 07/01/2011
Rates Fringes
SPRINKLER FITTER
Commercial..................$ 25.20 15.90 Industrial..................$ 27.40 15.90
Industrial: Jobs covering sugar mills, power plants, trash burning plants, military installations and Cape Kennedy. All other work shall be commercial rate.
SHEE0015-001 07/01/2009
Rates Fringes
SHEET METAL WORKER...............$ 25.41 12.78
TEAM0385-001 05/01/1990
TRUCK DRIVER.....................$ 13.00 .80
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
(End of Summary of Changes)
File details come from the government source that posted it. Updated .