Attachment 7 - Questions and Answers.pdf
PDF 103 KB Posted
- Attached to
- CMSFS Fiberoptic Cable Installation - Amendment 1 Federal contract opportunity
- Solicitation number
- FA251725Q0049
About this file
This document is a Questions and Answers file for Solicitation FA251725Q0049, addressing key details about a fiber optic cable installation project at Cheyenne Mountain Space Force Station. The Q&A clarifies critical requirements, including that SECRET-cleared personnel are mandatory for CLIN 0002, escorted access is not permissible, and proposals must be submitted for all Contract Line Item Numbers (CLINs). The government confirmed this is a new project, with a similar previous contract awarded to Aquintas, LLC, and provided maps/drawings in Attachment 1 under Appendix D.
The solicitation requires contractors to engineer, furnish, install, and test (EFI&T) fiber optic cable, with all equipment and materials being new and not refurbished. Proposal submissions are due on 17 June 2025 at 1000 MDT, with questions accepted until 10 June 2025 at 1000 MT. All quotations should be emailed to TSgt Holly Hepler at holly.hepler@spaceforce.mil, and telephone inquiries will not be answered. The project is being managed by the Department of the Air Force Space Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Cheyenne Mountain Fiber Install PWS.pdf | ||
| Attachment 5 - DD254 Draft OSP.pdf | ||
| Combined Synopsis and Solicitation.pdf | ||
| Attachment 2 - CLIN Price Sheet.xlsx | XLSX spreadsheet | |
| Attachment 3 - Additional Applicable Clauses and Provisions.pdf | ||
| Attachment 4 - Wage Determination 23 Dec 2024.pdf | ||
| Attachment 6 - QA from Previous Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
Solicitation FA251725Q0049
1. As noted in the PWS Section 2.1.3.1, CLIN 0002 requires SECRET-cleared personnel due to secure area access. Would escorted access by government-cleared personnel be acceptable to fulfill the requirements of CLIN 0002?
a. No. The Government does not have the manning on site to escort for the duration of the project.
2. If escorted access is not permissible, please confirm whether proposals may be submitted for CLIN 0001 only.
a. No. Proposals must be submitted for all CLINs.
3. What is the magnitude of construction range for this project?
a. This is not a construction project; it is a service. Thus, a magnitude of construction projects will not be disclosed.
4. Is this a brand-new contract OR is (was) there an incumbent performing these services?
a. This is a new project. However, a similar project was awarded under contract number FA251724P0042 to Aquintas, LLC.
5. The announcement indicated that maps are available. Can you share those maps with us?
a. Maps/drawings are available on Attachment 1, Cheyenne Mountain Fiber Install PWS under Appendix D: Drawings (pages 21 and 22).
6. Will an extension to the proposal submission deadline be considered to allow industry sufficient time to submit a compliant proposal?
a. At this time, no. Offers remain due on 17 June 2025 at 1000 MDT.