This is a Performance Work Statement (PWS) for the Bombers Heritage Hall facility alteration project at Wright-Patterson Air Force Base, Building 556. The project aims to transform the 2nd Floor hallway entrance into a modern environment that reinforces the strategic deterrence mission and heritage of the USAF Bombers community through bomber-specific environmental wall graphics, heraldry shields, structural scale models, historical elements, painting, architectural finishes, decals, and visual enhancement utilizing existing space and structures.
The project must be completed within ninety (90) calendar days of award, structured in three stages: Stage 1 Design Plan (30 days), Stage 2 Sourcing & Fabrication (60 days), and Stage 3 Physical Implementation & Closeout (90 days). On-site physical installation shall not exceed thirty (30) calendar days from physical site commencement and shall not restrict access to 2nd Floor restroom facilities for more than thirty (30) contiguous minutes. This solicitation is issued under the Air Force Research Laboratory (AFRL) Rapid Infrastructure for Science and Experimentation (RISE) parent notice FA8652279-RISE pursuant to 10 U.S.C. 2808a, with the solicitation number FA2396-27-9CTBD. The contracting agency is the Department of the Air Force Materiel Command Research Laboratory.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bombers Heritage Hall diagram.pptx | PPTX presentation | |
| 2808a_OT_Articles_Bombers_Hallway_Project_FINAL.pdf | ||
| AOI Final OT Bombers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .