About this file

This is an Area of Interest (AOI) solicitation issued under the Air Force Research Laboratory (AFRL) Rapid Infrastructure for Science and Experimentation (RISE) program for a facility alteration and space optimization project. The project, titled "Facility Alteration & Space Optimization – Bombers Directorate Hallway Project" (AOI FA2396-27-9CTBD), seeks to transform the 2nd Floor hallway of Building 556 at Wright-Patterson Air Force Base, Ohio into a modern environment reinforcing the USAF Bombers community mission through environmental wall graphics, heraldry shields, UV-resistant structural scale models of bombers (B-52, B-1, B-2, B-21), historical elements, painting, architectural finishes, and decals. The project must be completed within 90 calendar days of award across three stages: Design Plan (30 days), Sourcing & Fabrication (60 days), and Physical Implementation & Closeout (90 days), with on-site installation not exceeding 30 calendar days and restroom disruption limited to 30 contiguous minutes maximum. The submission deadline is 04 December 2026 at 17:00 EST, with submissions sent to AFRL.2808a.inbox@us.af.mil.

The solicitation is structured as an Accelerated Two-Step Down-Select process resulting in a Firm-Fixed-Price (FFP) Milestone Payment contract. Step 1 requires a streamlined commercial proposal (maximum 5 pages) addressing technical and graphic concept, mandatory qualifications demonstrating prior Wright-Patterson AFB experience, execution and disruption mitigation methodology, and firm-fixed-price milestone allocation. Step 2 involves direct award negotiation and design finalization with the highest-ranked offeror. Special articles and cost drivers include Davis-Bacon wage rates (Department of Labor General Decision OH20260081), waived bonding and liquidated damages, standard commercial general liability insurance ($1M occurrence/$2M aggregate), 100% U.S. citizenship requirement with Tier 1 background checks, Buy American preference, and CMMC Level 1 cybersecurity standards. Site utilities are provided at no cost by the Government. Evaluation criteria prioritize mandatory qualifications and Wright-Patterson AFB experience, schedule execution risk, site logistics and disruption mitigation in an occupied military headquarters, safety and structural attachment methodology, and access, security, and public release compliance. The Agreements Officer is Megan Rosenbeck, AFRL/RMZ. A pre-proposal site walkthrough is available with 3 business days' notice to AFRL.2808a.inbox@us.af.mil.

View the file

Other files

File Type Posted
Bombers Heritage Hall PWS - 13 Nov 26.docx DOCX document
Bombers Heritage Hall diagram.pptx PPTX presentation
2808a_OT_Articles_Bombers_Hallway_Project_FINAL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AFRL RISE 2808a Construction OT

Closed Signal — Area of Interest (AOI)

NOTICE: This is an Area of Interest (AOI) issued under the Air Force Research Laboratory (AFRL) Rapid Infrastructure for Science and Experimentation (“RISE”) parent notice: FA8652279-RISE. Companies are encouraged to review the parent notice prior to submitting against this AOI.

Item Details

AREA OF INTEREST (AOI) # FA2396-27-9CTBD

PROJECT TITLE Facility Alteration & Space Optimization – Bombers Directorate Hallway Project

STATUTORY AUTHORITY 10 U.S.C. § 2808a (Facility Construction or Repair)

PUBLICATION DATE 20 November 2026

SUBMISSION DEADLINE 04 December 2026, 17:00 EST

ISSUING OFFICE Air Force Research Laboratory (AFRL/RMZ), Wright-Patterson

AFB, OH

AGREEMENTS OFFICER Megan Rosenbeck, AFRL/RMZ

SUBMISSION LOCATION AFRL.2808a.inbox@us.af.mil (Subject Line: “AOI FA2396-27-9- CTBD – Bombers Directorate Hallway Project – [Company Name]”)

PROJECT CLASSIFICATION Alteration & Minor Facility Repair

1.0 PROJECT OBJECTIVE

To optimize the work environment and facility functionality for personnel in the 2nd Floor hallway of Building 556, Acquisition Management Complex, Wright-Patterson Air Force Base, Ohio. This project transforms an existing standard entrance hallway into a modern, motivating environment that reinforces the strategic deterrence mission and heritage of the USAF Bombers community through bomber-specific environmental wall graphics, heraldry shields, structural scale models, historical elements, painting, architectural finishes, decals, and visual enhancement using existing space and structures.

Target Timeline: The entire project must be completed within ninety (90) calendar days of award: Stage 1 Design Plan (30 days), Stage 2 Sourcing & Fabrication (60 days), and Stage 3 Physical Implementation & Closeout (90 days). On-site physical installation shall not exceed thirty (30) calendar days from physical site commencement and shall not restrict access to 2nd Floor restroom facilities for more than thirty

(30) contiguous minutes.

2.0 PROJECT SCOPE & SITE CONDITIONS

• Project Classification: Alteration & Minor Facility Repair [MR2.1].

• Physical Location: 2nd Floor hallway, Building 556, Area B, Acquisition Management Complex, Wright- Patterson AFB, Ohio.

• Estimated Footprint: Existing 2nd Floor hallway corridor and entranceway; installation boundaries conform strictly to the Government-approved Heritage Hall Plan.

• Existing Utilities at Site: Standard facility lighting and normal electrical building utilities are present. No utility tie-ins, heavy electrical rewiring, or plumbing modifications are required.

• Key Site Constraints: Work takes place in an occupied military headquarters facility. Egress and head clearance must be verified for all ceiling-suspended models (B-52, B-1, B-2, and B-21). Suspended models and mounting hardware must be constructed of ultraviolet (UV)-resistant, thermally stable materials to withstand direct sunlight from exterior windows. Decals and graphics must utilize commercial architectural-grade adhesives and edge-sealing techniques to prevent peeling or bubbling.

3.0 SPECIAL ARTICLES & COST DRIVERS

The following tailored terms and conditions apply to this project under 10 U.S.C. § 2808a and reflect thresholds appropriate for a $100,000.00 project:

Cost Driver / Special Article Project-Specific Requirement & Governing Article

Statutory Wage Rates (Davis-Bacon Act)

Applicable (Article 15). Required for construction/alteration over $2,000. Department of Labor General Decision Wage Determination Number: OH20260081 applies. Weekly certified payrolls (WH-347) and SF 1413 flow-downs required.

Financial Security / Bonding Waived by Agreements Officer. Below the statutory $150,000 Miller Act threshold; 100% performance and payment bonds are fully waived to maximize commercial competition and eliminate unnecessary cost markups.

Overtime Standards

(CWHSSA)

Tailored / Waived. Project is below the $150,000 CWHSSA statutory threshold. Standard Fair Labor Standards Act (FLSA) rules apply; CWHSSA liquidated damages reporting is excluded.

Liquidated Damages Deleted / Not Applicable. Milestone delivery and schedule performance are enforced via fixed-price payable milestone gates (Article 6) and termination remedies (Article 4).

Specialized Insurance Standard Commercial Coverage (Article 16). Contractor must maintain Commercial General Liability ($1M occurrence / $2M aggregate) and statutory Workers' Compensation. Builder's Risk and E&O are waived.

Site Utility Consumption Costs

Provided at No Cost by the Government. Existing facility electricity and lighting for installation tools and equipment will be furnished by Building 556 at no charge.

Personnel Security & Facility Badging

Borne by Performer / Coordinated with Base (Article 10 & PWS 4.5, 6.1). 100% U.S. Citizenship required. Personnel must obtain Tier 1 background checks (SF85) for unescorted entry or coordinate escort rosters with AOR 48 hours in advance.

Domestic Content (Buy American)

Applicable (Article 9). WTO GPA / Trade Agreement waivers do not apply below $7,032,000. Standard Buy American preference applies; COTS item exception applies to standard off-the-shelf paints, fasteners, and materials.

Cybersecurity Standards (CMMC Level 1)

Applicable (Article 12). Mandates basic safeguarding of Federal Contract Information (FCI) across 15 security controls and annual self-attestation. Full NIST SP 800-171/FedRAMP is waived.

4.0 ASSESSMENT CRITERIA

Submissions will be evaluated against the following tailored criteria selected by the Agreements Officer:

Active Selected Criteria Specific AOI Focus for this Project

[X] Mandatory Qualifications & Past Experience

Documented prior experience successfully designing and executing interior visual enhancements, environmental graphics, and facility space optimization at Wright-Patterson AFB, OH (PWS Section 1.1).

[X] Schedule & Phased Milestone Execution Risk

Demonstrated capability to meet the strict 90-calendar-day timeline across three gates: Design Plan (30 days), Sourcing/Fabrication (60 days), and Installation/Walkthrough (90 days), with physical site work finished in under 30 days.

[X] Site Logistics & Disruption Mitigation

Detailed plan for execution in an occupied military headquarters facility, strictly guaranteeing zero restroom disruptions exceeding 30 contiguous minutes, daily debris/dust cleanup, and adherence to 0800–1700 duty hours.

[X] Safety, Structural Attachment & Material Durability

Sound engineering methodology for ceiling suspension of 4 scale models (B-52, B-1, B-2, B-21) with rated hardware, head/egress clearance, and UV/thermal resistance against direct window sunlight. Compliance with OSHA (29 CFR 1910) and NFPA 101.

[X] Access, Security & Public Release Compliance

Full compliance with U.S. Citizenship mandates, Tier 1/escort security procedures (AFMAN 16-1405), OPSEC/iWATCH training, and strict adherence to AFLCMC/PA and AO pre-release approval requirements.

5.0 STREAMLINED SUBMISSION & DOWN-SELECT PROCESS

To reduce administrative burden on commercial firms for projects of this size, the Government is utilizing an Accelerated Two-Step Down-Select process. The resultant award will be negotiated under a Firm-Fixed-Price (FFP) Milestone Payment structure pursuant to 10 U.S.C. § 2808a.

STEP 1: STREAMLINED COMMERCIAL PROPOSAL (Maximum 5 Pages)

• Format: Maximum five (5) pages (Title Page excluded). PDF format preferred.

• Required Submission Content:

1. Technical & Graphic Concept: Proposed design approach for graphics, heraldry shields, UV-resistant suspended aircraft models (B-52, B-1, B-2, B-21), and wall finishes.

2. Mandatory Qualifications: Documented prior experience designing and executing visual enhancement/space optimization projects at Wright-Patterson AFB, OH (PWS 1.1).

3. Execution & Disruption Mitigation Plan: Methodology to complete work within 90 days (site work ≤ 30 days) and guarantee restroom disruption ≤ 30 contiguous minutes.

4. Firm-Fixed-Price Milestone Schedule: Proposed price allocated across the 3 mandatory milestone gates.

• Evaluation: The Government will evaluate proposals against the Section 4.0 criteria. The highest-ranked commercial offeror demonstrating the best technical capability and fair/reasonable pricing will be selected.

STEP 2: DIRECT AWARD & DESIGN FINALIZATION

The selected offeror will be invited directly to negotiate and execute the final OT Project Order. (The Government reserves the right to request a brief 30-minute virtual technical clarification meeting if necessary prior to award).

6.0 SITE VISIT / PRE-PROPOSAL CONFERENCE

A site walkthrough of the 2nd Floor hallway in Building 556 will be conducted for interested offerors to examine corridor lighting, curved ceiling structure, and site dimensions prior to submission. RSVPs and security clearance rosters must be submitted to AFRL.2808a.inbox@us.af.mil at least three (3) business days prior to the visit. All attendees must possess valid U.S. government photo ID and verify U.S.

citizenship.

7.0 NON-GOVERNMENT ADVISORS & CONFIDENTIALITY

Non-government advisors may be utilized to assist in technical reviews under strict non-disclosure agreements. Proprietary data and trade secrets will be protected pursuant to Article 1. All statutory requirements under 10 U.S.C. § 2808a have been met.

8.0 FOLLOW-ON TRANSACTIONS (N/A)

Pursuant to 10 U.S.C. § 2808a, this effort represents a discrete, localized interior facility enhancement project. No follow-on prototype or production transaction is authorized or contemplated.

AGREEMENTS OFFICER APPROVAL:

Megan Rosenbeck Agreements Officer, AFRL/RMZ Wright-Patterson AFB, OH

File details come from the government source that posted it. Updated .