AFRL RISE 2808a AOI: Facility Alteration & Space Optimization – Bombers Directorate Hallway Project (Bldg 556)
Solicitation number
FA2396-27-9CTBD
Issued by

About this file

This document is an Other Transaction Agreement (OTA) for facility alteration services executed by the Air Force Research Laboratory (AFRL) under the authority of 10 U.S.C. § 2808a.

The agreement (FA2396-27-9-CTBD) establishes a Firm-Fixed-Price Milestone Agreement for the Facility Alteration & Space Optimization – Bombers Directorate Hallway Project at Wright-Patterson Air Force Base, Ohio. The scope includes planning, design, engineering, UV-resistant model fabrication, heraldry shield fabrication, painting, architectural finishes, and physical installation in the 2nd Floor hallway of Building 556. The performance period is ninety (90) calendar days from the effective date, with no physical site work beginning until the Participant receives a written Notice to Proceed from the Agreements Officer. Payment is Firm-Fixed-Price on a milestone basis through Wide Area Workflow (WAWF) within thirty (30) days of Agreements Officer Representative acceptance. Four key deliverables are required: (1) Kickoff Meeting (within 10 calendar days); (2) Site-Specific Heritage Hall Plan (within 30 calendar days); (3) Material Sourcing & Staging Verification (within 60 calendar days); and (4) Physical Installation & Joint Walkthrough Closeout Report (within 90 calendar days).

The agreement incorporates significant compliance requirements including Buy American domestic content preferences for non-Commercial Off-The-Shelf (COTS) materials, Davis-Bacon prevailing wage requirements with weekly certified payrolls (WH-347), CMMC Level 1 cyber security controls, Tier 1 background checks (SF85) for unescorted personnel, OPSEC and Level I Antiterrorism/iWATCH training, prohibitions on specified foreign equipment and software (ByteDance/TikTok, Kaspersky Lab, Huawei, ZTE, Hytera, Dahua, Hikvision, and certain unmanned aircraft systems), Commercial General Liability and Workers' Compensation insurance, and compliance with OSHA General Industry Standards and NFPA 101 Life Safety Code. The Agreements Officer is Megan Rosenbeck (AFRL/RMZ), and the AOR will be designated in writing upon award. The Government's total financial obligation is limited to the obligated funding amount stated on the award document.

View the file

Other files

File Type Posted
Bombers Heritage Hall PWS - 13 Nov 26.docx DOCX document
Bombers Heritage Hall diagram.pptx PPTX presentation
AOI Final OT Bombers.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE RESEARCH LABORATORY (AFRL)

OTHER TRANSACTION AGREEMENT ARTICLES

Authority: 10 U.S.C. § 2808a (Facility Construction or Repair)

Item Terms

Agreement Number FA2396-27-9-CTBD

Project Title Facility Alteration & Space Optimization – Bombers Directorate Hallway Project

Agreement Type Firm-Fixed-Price Milestone Agreement

Place of Performance Building 556, Area B, 2nd Floor Hallway, Wright-Patterson AFB, OH

Period of Performance Ninety (90) Calendar Days from Effective Date

Effective Date Upon Final Signature

PREAMBLE

This Agreement between the Government and the Participant is entered into pursuant to 10 U.S.C. § 2808a, which permits the Department of Defense (DoD) to execute transactions other than contracts and grants for facility repair and construction projects, including all associated planning, design, and engineering efforts. This Agreement is not a procurement contract, grant, or cooperative agreement.

The Federal Acquisition Regulation (FAR) and Defense Federal Acquisition Regulation Supplement (DFARS) do not apply except to the extent specific provisions are expressly incorporated by reference as terms of this Agreement.

ARTICLE 1: DEFINITIONS

• Adequate Security: Protective measures commensurate with consequences and probability of loss, misuse, or unauthorized modification of information.

• Agreement: This Other Transaction Agreement, including Attachments and written bilateral modifications.

• Agreements Officer (AO): The warranted Air Force official with authority to enter into, administer, modify, and terminate this Agreement.

• Agreements Officer’s Representative (AOR): The designated technical representative monitoring project progress and deliverable acceptance (without authority to direct out-of-scope work).

• Controlled Unclassified Information (CUI): Information requiring safeguarding controls pursuant to law and DoDI 5200.48.

• Federal Contract Information (FCI): Non-public information provided by or generated for the Government under this Agreement.

• Milestone: A defined technical deliverable accomplishment entitling the Participant to payment.

• Participant: The awarded commercial entity executing the project.

ARTICLE 2: SCOPE OF THE AGREEMENT

The Participant shall perform the project to achieve the objectives described in Attachment A, Performance Work Statement (Bombers Directorate Hallway Project, dated 13 November 2026). This includes planning, design, engineering, UV-resistant model fabrication, heraldry shield fabrication, painting, architectural finishes, and physical installation in the 2nd Floor hallway of Building 556, Wright- Patterson AFB, OH. All personnel must comply with installation access control procedures, U.S.

citizenship requirements, and force protection condition (FPCON) directives.

ARTICLE 3: TERM OF AGREEMENT AND NOTICE TO PROCEED

The term of this Agreement is ninety (90) calendar days from the Effective Date. The AO will issue a written Notice to Proceed (NTP) authorizing commencement of performance. No physical site work shall begin until the Participant receives a written NTP executed by the AO.

ARTICLE 4: TERMINATION

The Parties may terminate this Agreement by mutual written agreement, or the AO may terminate for convenience or for cause (upon thirty (30) days written notice to cure). In the event of termination for convenience, the Government shall pay for accepted Milestones and verified work in place. In the event of termination for cause, payment is strictly limited to accepted Milestones. The Government retains the right to terminate immediately for national security or unacceptable foreign ownership, control, or influence (FOCI).

ARTICLE 5: AGREEMENT ADMINISTRATION & CHANGES

• Agreements Officer (AO): Megan Rosenbeck, AFRL/RMZ (megan.rosenbeck@us.af.mil).

• Agreements Officer Representative (AOR): Designated in writing upon award.

Substantive changes to the PWS, schedule, funding allocation, or milestones are effective only by written bilateral modification signed by the AO and Participant.

ARTICLE 6: OBLIGATION AND PAYMENT

The Government's total financial obligation under this Agreement shall be limited to the obligated funding amount stated on the Agreement award document. The Participant is not authorized to perform work that exceeds the available obligated funding. Payment is made on a Firm-Fixed-Price payable milestone basis through Wide Area Workflow (WAWF) within thirty (30) days of AOR acceptance.

ARTICLE 7: DELIVERABLES

The Participant shall deliver all items specified in Attachment A, PWS Section 7.0: (1) Kickoff Meeting (within 10 calendar days); (2) Site-Specific Heritage Hall Plan (within 30 calendar days); (3) Material Sourcing & Staging Verification (within 60 calendar days); and (4) Physical Installation & Joint Walkthrough Closeout Report (within 90 calendar days).

ARTICLE 8: DISPUTE RESOLUTION

The Parties agree to resolve claims in good faith. Claims must be submitted to the AO in writing within three (3) years of accrual. The AO will issue a final decision within 180 calendar days. Either Party may seek mediation or file an action in the U.S. Court of Federal Claims under the Tucker Act (28 U.S.C. § 1491(a)(1)).

ARTICLE 9: BUY AMERICAN & DOMESTIC CONTENT

(a) Statutory Preference: This Article implements 41 U.S.C. Chapter 83 (Buy American) by providing a preference for domestic construction and alteration materials. International Trade Agreement waivers do not apply to this facility alteration effort.

(b) Commercial Off-The-Shelf (COTS) Waiver: In accordance with 41 U.S.C. § 1907, the domestic content component test is waived for commercial off-the-shelf items (including standard architectural fasteners, commercial paints, vinyl films, adhesives, and mounting hardware).

(c) Domestic Requirement: All non-COTS materials shall be manufactured in the United States unless determined impracticable or unreasonable by the AO pursuant to Article 9.3.

ARTICLE 10: SECURITY AND INFORMATION CONTROL

Participant personnel shall comply with installation security policies (PWS Section 4.5 and 6.0).

Unescorted personnel must complete Tier 1 background checks (SF85) or remain escorted by Government personnel. Personnel assigned to Wright-Patterson AFB must complete OPSEC and Level I Antiterrorism / iWATCH training within required timeframes.

ARTICLE 11: SECURITY PROHIBITIONS AND EXCLUSIONS

The Participant shall not provide or utilize any equipment, software, or service prohibited by federal statute, including: ByteDance/TikTok (Consolidated Appropriations Act 2023), Kaspersky Lab hardware/software (NDAA FY18 Sec 1634), covered telecommunications/surveillance from Huawei, ZTE, Hytera, Dahua, or Hikvision (NDAA FY19 Sec 889), and covered foreign unmanned aircraft systems (American Security Drone Act of 2023). Mandatory 72-hour reporting applies via DIBNet.

ARTICLE 12: CYBER SECURITY REQUIREMENTS (CMMC LEVEL 1)

The Participant shall implement the fifteen (15) basic safeguarding controls for Federal Contract Information (FCI) pursuant to 32 CFR Part 170 (CMMC Level 1). The Participant shall submit a written self-assessment and attestation to the AO prior to award.

ARTICLE 13: GOVERNING LAW AND JURISDICTION

This Agreement shall be governed by and construed in accordance with the federal law of the United States.

ARTICLE 14: STATUTORY AUTHORITY AND APPLICABLE LAW

The Participant shall comply with applicable federal, state, and local laws, OSHA General Industry Standards (29 CFR 1910), NFPA 101 Life Safety Code, and Wright-Patterson AFB Base Civil Engineering regulations.

ARTICLE 15: COMPLIANCE WITH LABOR LAWS

(a) Construction Wage Rate Requirements (Davis-Bacon Act): Because the project involves manual painting, decorating, and surface alteration, all laborers and mechanics shall be paid not less than the prevailing wage rates contained in Department of Labor Wage Determination OH20260081. The Participant shall submit weekly certified payrolls (WH-347) and flow down mandatory clauses via SF 1413.

(b) Overtime Standards: Laborers and mechanics shall be compensated for overtime pursuant to the Fair Labor Standards Act (FLSA).

ARTICLE 16: INSURANCE AND LIABILITY

The Participant shall maintain Commercial General Liability and statutory Workers' Compensation insurance. Builder's Risk and Professional Liability (E&O) are waived. The Participant's total liability (absent gross negligence or willful misconduct) shall not exceed the total obligated Agreement amount.

ARTICLE 17: PUBLICITY AND PUBLIC RELEASE

The Participant shall not release any marketing materials, photos, case studies, or press announcements regarding this project without prior written review and approval from AFLCMC Public Affairs and the Agreements Officer.

ARTICLE 18: FOLLOW-ON TRANSACTIONS (N/A)

Reserved. This effort is a discrete interior facility alteration project. No follow-on prototype or production transaction is authorized or contemplated.

ARTICLE 19: GOVERNMENT OVERSIGHT AND ACCESS

The Government retains access to the site and project records at reasonable times to inspect installation workmanship and conduct final walkthrough acceptance.

ARTICLE 20: ASSIGNMENT AND SUBCONTRACTING

The Participant shall not assign this Agreement without prior written consent of the AO. Appropriate flow-downs (labor rates, security prohibitions, and CMMC Level 1) must be included in subcontracts.

ARTICLE 21: ATTACHMENTS

• Attachment A: Performance Work Statement (PWS), dated 13 November 2026

• Attachment B: Milestone Payment Schedule

• Attachment C: Reports and Deliverables Schedule

• Attachment D: Domestic Content Criteria & Foreign-Origin Reporting

• Attachment E: Department of Labor Wage Determination OH20260081

• Attachment F: Insurance Requirements (as detailed in article 16)

SIGNATURE PAGE

FOR THE PARTICIPANT: FOR THE GOVERNMENT:

By: ______________________________ Name:

Title:

Date:

Entity Name:

UEI:

By: ______________________________ Name: Megan Rosenbeck Title: Agreements Officer, AFRL/RMZ Date:

Wright-Patterson AFB, OH

File details come from the government source that posted it. Updated .