This is a Question-and-Answer Sheet for solicitation FA220426R0001, addressing contractor inquiries regarding the transportation of an AN/TPY-4 (V)1 radar system from White Sands Missile Range, New Mexico to Santa Rosa Island Site A-17, Florida—a one-time shipment covering approximately 1,340 miles with pickup on 24 April 2026 and delivery by 10:00 AM CDT on 27 April 2026.
Key clarifications include: the government will provide cranes for loading and unloading only; contractors must source all other material handling equipment and are responsible for obtaining oversize/overweight permits; the system weighs 24,000 lbs and requires a minimum $25,000,000 all-risk cargo insurance policy (the declared value is Controlled Unclassified Information); the radar is unclassified and unsanitized for shipment, requiring no armed security escorts; transportation configuration is at vendor discretion (box trucks, step deck trailers, or RGN trailers are acceptable alternatives) provided all cargo requirements are met; heavy-duty, weather-resistant industrial-grade tarps (vinyl-coated polyester or equivalent) are required for concealment and weather protection; vehicles must have active real-time GPS tracking and be parked only in secured locations overnight; and the system contains lithium batteries classified as hazardous materials under DOT regulations. Additional requirements include qualified, security-cleared drivers for military installation access; compliance with White Sands Missile Range access procedures (Forms 301, 300, photo brief, and hazard analysis); ancillary equipment including mobilizers may be transported on open deck trailers; and no specific overnight parking locations require government pre-approval. The applicable NAICS code is 484230, and this is a new requirement with no incumbent contractor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q-A
| FA220426R0001 3DELRR TPY-4 Transportation Question-and-Answer Sheet | |
| Question | Answer |
| Clarification regarding the anticipated shipment volumes on a weekly, monthly, and annual basis | As defined in the SOW (Section1.1) This is a one time shipment. |
| Information you may provide concerning your expected pricing framework. | Please see the attached Model Contract - FA220426QB001, Page 3. |
| Would a 53’ enclosed dry van with a liftgate, or equivalent configuration capable of meeting all cargo handling and operational requirements, be considered acceptable as an alternative to the specified box trucks? | It is at the descretion of vendor to transport radar and components to meet requirements given specifications |
| The specifications show the Main Radar Unit weighs 24,000 lbs. Will the government provide the necessary crane or heavy rigging equipment and personnel to safely load the system onto the trailer at White Sands and unload it at Site A-17 in Florida, or is the contractor required to source and provide the heavy lifting equipment? | Government will provide - Crane |
| The Statement of Work requires vehicles to be parked in secure locations and never left unattended in unsecured areas. Does the government have a list of approved military installations along the route for overnight parking, or does a standard fenced and well-lit commercial truck stop meet this security requirement? | Radar is santized for shipment -- radar system is uncalssifed and PG is locked with padlock |
| The SOW states the system must be concealed from public view during transit. Can the government confirm if standard heavy-duty commercial freight tarps are acceptable for this concealment, or are specific military-grade covers required? | As defined in the SOW (Section 4.4), the standard we require is "heavy-duty, weather-resistant, industrial-grade tarps (e.g., vinyl-coated polyester or similar)." This means a standard, high-quality commercial tarp used for protecting industrial equipment during long-haul transportation. A thin, low-quality "blue poly" would not meet this standard. |
| Could you please confirm if a declared cargo value is available for this shipment, or advise on the required cargo insurance coverage level? | For security and acquisition-sensitive reasons, the specific programmatic cost and exact declared value of the AN/TPY-4 system is Controlled Unclassified Information (CUI) and will not be publicly released.To ensure the government's interests are protected, |
The selected contractor shall be required to have and maintain a minimum of $25,000,000 (twenty-five million USD) in all-risk cargo insurance coverage specific to this shipment.
| Can you elaborate on what is to go on the two enclosed box trucks that are required by the SOW (para 4.3)? The SOW says "Power & Ancillary Equipment," however the Cargo & Equipment Specifications document only mentions the TG, PG, and both mobilizers. | Ancillary Equipment includes moblizers |
| Can the mobilizers be transported on an open deck trailer? | yes-- they can transported on an open trailer --- refer to diagram in requirement document |
| Can the mobilizers be lifted by crane? | yes-- crane can be used |
| Does the government have criteria for what is required of a "secure" location for planned overnight stops (SOW, para 4.6)? If the vehicles remain accompanied during the overnight, does that qualify as secured? | No-- there is no requirement please refer to question 8 |
| Are there any hazardous materials on the TPY-4 (as defined by DOT)? | Lithium batteries contained in TG |
| For insurance purposes, what is the overall declared value of the TPY-4? | see question 10 for answer regarding value and insurance |
| Can you advise on the loaded weight of the cargo that is intended to go on an RGN or Step Deck for this move. | per requirement document (pg.4 and 6) -- step deck trailer maximum payload is at least 48,000 lbs -vendor caluculation |
| Are you able to provide the cargo insurance requirements per piece? Specifically for the transceiver and processor groups? | per refer to question 10 ---TG and PG are not seperated out and is treated as a complete radar system for tranport |
| Can a commercial invoice or an estimated value of the government-furnished cargo be provided for insurance and liability purposes? | For security and acquisition-sensitive reasons, the specific programmatic cost and exact declared value of the AN/TPY-4 system is Controlled Unclassified Information (CUI) and will not be publicly released.To ensure the government's interests are protected, |
The selected contractor shall be required to have and maintain a minimum of $25,000,000 (twenty-five million USD) in all-risk cargo insurance coverage specific to this shipment.
| Are there any specific insurance requirements or minimum coverage limits required for this transport? | refer to question 10 --- $25M |
| Will security escorts be required at any point during transit? If so, should security be armed or unarmed? | No -- radar system is sanitized and unclassifed during transport |
| Are there any special handling requirements, permits, or clearances needed for transporting the radar system and associated components? | Vendor is responsible for : Provide qualified and security-cleared drivers as required for access to military installations. Cost or provision of special state/federal permits for oversized or overweight loads, should they be required. The vendor must identify if such permits are necessary based on final cargo dimensions. |
| Will loading and unloading assistance (personnel or equipment) be provided at origin and destination, or should this be included in the contractor’s scope? | As defined in the SOW (Section 3.2) "The contractor is not responsible for the disassembly or reassembly of the AN/TPY-4(V)1. The government is responsible for providing any required Material Handling Equipment (MHE), such as cranes or forklifts, for loading and unloading the primary components at the origin and destination unless otherwise proposed by the contractor (e.g., use of RGN trailers)." |
| Are there any restrictions on routes, travel times, or staging requirements during transit? | No-routes can include overnights as specified in requirements |
| Is there a required delivery schedule beyond the stated dates (e.g., specific time windows, coordination points, or check-ins during transit)? | No-Vendor needs to ensure timely pickup and delivery according to the agreed-upon schedule. |
Maintain communication with the designated points of contact at the origin and destination.
| Are there any reporting or communication requirements during transport (e.g., GPS tracking, daily updates)? | Section 4.6 of SOW "All Vehicles in the convoy must be equipped with an active, real-time satellite GPS tracking system.” The contractor shall provide the government point of contact (POC) with the location of the shipment upon request at any moment during transit." |
| SOW Section 4.3 -- The SOW specifies two Enclosed Box Trucks with Liftgates but provides only length requirements. Can you provide minimum required interior dimensions (height and width) for each box truck? Please confirm which specific cargo components are intended to be loaded into each truck (packing list/load plan) and the dimensions of all the loose pieces that are planned for box truck loading. | It is at the descretion of vendor to transport radar and components to meet requirements given specifications- do not have that information |
| Can the Government confirm the minimum liftgate capacity requirement for the 20-26 ft box truck? The SOW specifies a 1,000 lb minimum only for the 15-16 ft truck. | only have the 1,000 lb requirement |
| The Combined Synopsis lists NAICS 484121, while the Model Contract (SF 1449) lists NAICS 484230. Please confirm which NAICS code governs this acquisition for size standard and certification purposes. | NAICS 484230 |
| What is the required lead time for installation access requests for White Sands Missile Range (WSMR)? Are there specific personnel vetting forms or systems (e.g., DBIDS, RAPIDGate) required for contractor access? | Yes, there are speciifc forms needed Form 301 Access Badge, Form 300, WSMR photo brief form, WSMR site wide hazard analysis --- have to verify with WSMR POC lead time and processing of forms |
| Confirm the Government will provide all Material Handling Equipment (MHE) including forklifts and cranes at both origin (WSMR) and destination (Site A-17). If not, specify what the contractor must provide (e.g. pallet jacks in Box Trucks?) | Cranes only be provided by Government |
| Are there any route restrictions, mandatory corridors, or base-coordinated convoy lanes for movement through or near White Sands Missile Range and Eglin AFB installations? | No there are no route restirctions in transit -- however, need to follow up with WSMR POC for WSMR specific routes for trucks to enster base |
| Will you coordinate any special military convoy authorizations or state permit waivers, or is the contractor fully responsible for all oversize/overweight permits independently? | Vendor is responsible for: Cost or provision of special state/federal permits for oversized or overweight loads, should they be required. |
| Are there pre-approved secure overnight stop locations along the route, or must the contractor independently identify and have those locations approved? | No- there are specific routes indentified at the deiscretion of vendor |
| FAR 52.232-18 (Availability of Funds) is cited. Can the Government confirm the anticipated date funds will be authorized so the contractor can assess operational risk? | Per FAR 52.232-18, the Government's obligation is contingent upon the availability of appropriated funds. While funds are set aside for this requirement, a specific authorization date cannot be guaranteed. |
| What contractor information is required in Block 17 of the SF 1449 at time of quote submission vs. at time of award? | The Contractor's CAGE code and Unique Entity ID |
| Please provide full dimensions and weight for each of the items that will need to be transported (step decks + box trucks) – a full Load List or Packing List will be appreciated. | Full dimensions of each items have been provided in requirement document --- do not have a full load packing list |
| Do the items that will be loaded on step decks need to be tarped? | Yes, items need to be tarped based on water intrusion issues |
| The government roads near pickup and delivery appear capable of supporting semi truck weights and dimensions, but I can't confirm this due to restrictions and survey data. Is it confirmed on your end that semi-trucks can access these roads? | Yes- no road restrictions as radar was delivered to both locations etc./no issues |
| Could you clarify the exact trailer and how many are needed for the main component of the load? | Review requirements -- Vendor discretion on how many trucks |
| Can the remaining components of the load be loaded onto a flatbed trailer and tarped to protect them instead of using box trucks? | Vendor discretion on transport configuration meeting requirments - tarped for all exterior transportation |
| Is it imperative to use box trucks with liftgates for the transport? | Vendor discretion on transport configuration given requirement document |
| Is this to be considered an oversize load? Will route permits and escorts be required for this transport? | Vendor discretion on transport configuration given requirement document -- will dictate oversize load determination |
| We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number? | This is a new requirement. |