DEPARTMENT OF THE AIR FORCE
AIR FORCE RESERVE COMMAND
2 July 2014
REVISED STATEMENT OF WORK (SOW)
DOBBINS ARB PROJECT FGWB 14-0013 AIRFIELD PRIORITY TREE REMOVAL
1. Contractor to clear/remove trees and bushes of various sizes in Area 1 and Area 2 (see drawing). Area 1 of this project consists of cutting and removing approximately 20 trees and bushes, including roots, as well as clearing, grubbing, and leveling for future mowing.
Area 2 of this project consists of cutting and removing approximately three (3) acres of trees and bushes, including roots, clear, grub, and prepare the site to be hydro seeded.
Contractor shall perform hydro seeding function using seed blend as defined in attachment titled, “Seed Blend.” Watering newly seeded area is responsibility of contractor, until grass grows and is established. Contractor shall dispose of all removed material off base, per attached Specification Section 01560 ENVIRONMENTAL REQUIREMENTS. Contractor shall meet all requirements in accordance with attached UFC 3-260-01Airfield and Heliport Planning Design and all other applicable regulations and codes.
2. All work associated with this project shall be completed within 30 calendar days; not including watering/establishment of grass.