Revised_Statement_of_Work.pdf

PDF 72 KB Posted

Attached to
Tree and Brush Removal
Solicitation number
F5B3234136A001
Issued by

About this file

Revised Statement of Work

View the file

Other files

File Type Posted
Revised_SOW_Drawings.pdf PDF
Initial_Site_Visit_Sign_in_Sheet.pdf PDF
Questions_and_Answers.pdf PDF
Seed_Blend.pdf PDF
Close_up_of_Utilities_in_Area.pdf PDF
Legend_for_Utilities.pdf PDF
Image_of_Removal_Area.pdf PDF
Site_Visit_Sign_in_Sheet.pdf PDF
Questions_and_Answers.pdf PDF
Required_SeedBlends.pdf PDF
UFC_3-260-01.pdf PDF
DARB_4_Form.pdf PDF
Wage_Determination.pdf PDF
Statement_of_Work.pdf PDF
Environmental_Requirements_Section_01560.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE RESERVE COMMAND

2 July 2014

REVISED STATEMENT OF WORK (SOW)

DOBBINS ARB PROJECT FGWB 14-0013 AIRFIELD PRIORITY TREE REMOVAL

1. Contractor to clear/remove trees and bushes of various sizes in Area 1 and Area 2 (see drawing). Area 1 of this project consists of cutting and removing approximately 20 trees and bushes, including roots, as well as clearing, grubbing, and leveling for future mowing.

Area 2 of this project consists of cutting and removing approximately three (3) acres of trees and bushes, including roots, clear, grub, and prepare the site to be hydro seeded.

Contractor shall perform hydro seeding function using seed blend as defined in attachment titled, “Seed Blend.” Watering newly seeded area is responsibility of contractor, until grass grows and is established. Contractor shall dispose of all removed material off base, per attached Specification Section 01560 ENVIRONMENTAL REQUIREMENTS. Contractor shall meet all requirements in accordance with attached UFC 3-260-01Airfield and Heliport Planning Design and all other applicable regulations and codes.

2. All work associated with this project shall be completed within 30 calendar days; not including watering/establishment of grass.