Questions_and_Answers.pdf

PDF 22 KB Posted

Attached to
Tree and Brush Removal
Solicitation number
F5B3234136A001
Issued by

View the file

Other files

File Type Posted
Revised_SOW_Drawings.pdf PDF
Initial_Site_Visit_Sign_in_Sheet.pdf PDF
Questions_and_Answers.pdf PDF
Revised_Statement_of_Work.pdf PDF
Seed_Blend.pdf PDF
Close_up_of_Utilities_in_Area.pdf PDF
Legend_for_Utilities.pdf PDF
Image_of_Removal_Area.pdf PDF
Site_Visit_Sign_in_Sheet.pdf PDF
Required_SeedBlends.pdf PDF
UFC_3-260-01.pdf PDF
DARB_4_Form.pdf PDF
Wage_Determination.pdf PDF
Statement_of_Work.pdf PDF
Environmental_Requirements_Section_01560.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Question: Availability of Windy Hill gate for use in lieu of Gate 2:

Answer: Security Forces (SFS) can accommodate the use of Windy Hill gate; however, the contractor must provide 30 minute prior notification to SFS to allow opening of the gate. The Windy Hill gate will not be continuously manned at any time.

2. Question: What do the blue flag markings represent:

Answer: Water line

3. Question: Can contractors fill their water trucks, for watering hydroseed, from base hydrants:

Answer: Yes - Contractor will be given the location of water hydrant per advisement from the Fire Dept.

4. Question: Watering seeds: Can additional days be given in order to water seeds until grass grows?

Answer: Thirty (30) additional days will be provided for this effort.

5. Question: Does the Government want Sod or netting used on the slope:

Answer: Contractor is responsible for ensuring grass takes/grows. Repair of any erosion that occurs prior to grass taking hold is the contractor’s responsibility.