Ques_Responses_20180629.docx

DOCX document 19 KB Posted

Attached to
Amendment: Fire Equiment Maintenance Federal contract opportunity
Solicitation number
F4D3D48127AQ01
Issued by
Department of the Air Force Space Command

About this file

Response to Questions

View the file

Other files for this federal contract opportunity

Other files attached to Amendment: Fire Equiment Maintenance, newest first.
File Type Posted
Amended_2_Atch_1_RFQ_Fire_Equipment_Maintenace_20180709.xlsx XLSX spreadsheet
Amended_Atch_1_RFQ_Fire_Equipment_Maintenace_20180613.xlsx XLSX spreadsheet
Atch_1_RFQ_Fire_Equipment_Maintenace_20180613.xlsx XLSX spreadsheet
Atch2_PWS_Fire_Equip_20180514.docx DOCX document
Atch4_TO_35E1_2_13_1_manual.pdf PDF
Atch3_WD_2015-5647_R5_20180110.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS:

Fire Equipment Maintenance

#RFQ F4D3D48127AQ01

Questions were due to 30 CONS by 25 June 2018. The following questions were received and answers are provided below. Here are the responses to those respective questions. As a friendly reminder, proposals are due by 10:00 AM PST on 09 July 2015. Please respond to the #RFQ F4D3D48127AQ01.

Question 1: Please clarify 2.1.1 it states that personnel will be certified by WRG Fire Trainer Simulations Systems Inc. yet there is only mention of Kiddie Equipment. Please provide information including Make Model Year and Serial number of AFTF

Response 1: The Fire Trainer Simulations Systems was built around 2007 and built to T.O. 35E1-2-13-1 specs. If contractors can verify that they can work to the T.O specs (manual was included in RFQ package) than WRG certification is not required.

Question 2: 2.1.6 Fire House testing. In order to be in compliance with NFPA there should be testing of the nozzles and appliances. Is there data that you wish to include to cover this requirement?

Response 2: We just need to the hose tested.

Please Note the following quantity changes on the RFQ:

CLIN 0001 was changed from one (1) to two (2) inspections, CLIN 0003 changed to 4 inspections (quarterly inspection, but still 9 props for each inspection) CLIN 0006 Changed from 500,000 to 50,000 (typo)