(x)

33330222RF0010013

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

OCON

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

SMITHSONIAN INSTITUTION

01/18/20220001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

01/18/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This is amendment 1 to F22R010013. Questions and answers attached to this standard form are integrated into the solicitation by reference. The submission date is unchanged.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Thomas Dempsey

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

SI RFI # QUESTION RESPONSE

1 May relevant projects include design competition entries, projects currently in design, and projects currently under construction?

Projects that have completed construction are preferred.

How many firms do you plan to shortlist before the design concept/interview phase? A final determination of the number of firms cannot be made at this time but is anticipated to be no fewer than 3 and no more than 8 firms.

What form of stipend or honorarium will shortlisted firms receive for the design concept? No honorarium will be offered.

How many renderings are required as part of the design concept? If you could be more specific we’d appreciate it.

Shortlisted bidders will be asked to provide an adequate number of renderings to show the exterior architecture of the building and how it fits contextually with the site and existing museum.

What level of BIM are you expecting? If you could be more specific we’d appreciate it. The model should be able to descibe the architectural elements and massing of the building as it relates to the context of the site and its relationship with the existing museum.

Will the design concepts be anonymous when shared publicly? Yes.

How will the appendix resumes and projects be evaluated? Please see p.6, Section 6 titled Project Team Qualifications: Members of the A/E project team must have the educational and professional qualifications to provide the services, including registration with the appropriate regulatory and professional entities. Firms are encouraged to minimize duplication within disciplines and in project roles in the selection of subconsultants or joint venture partners. The demonstrated extent of involvement and quality of staff’s contributions to projects should be emphasized. The evaluation of these disciplines will consider education, training, and the overall quality and performance on relevant projects of similar complexity and scope. The A/E team must also have a minimum of:

a) all disciplines listed under Section 2. Services (clearly identify the disciplines to be performed in-house and those to be subcontracted).

b) three registered architects.

c) architectural licensure in any US State or the District of Columbia prior to contract award.

d) one registered engineer for every engineering discipline.

e) project leads for each discipline should have a minimum of 10 years of relevant experience;

and

f) construction phase support services.

2 How many firms will be short listed for the second stage? Please see above.

Is there a stipend for the firms short listed for Phase II? Please see above.

3 Regarding IX. Subcontracting Plan Requirements, specifically A minimum of 40% of the total planned subcontracting dollars shall be placed with small business concerns.

Can you please clarify small business for the purpose of this project?

The North American Industry Classification Code (NAICS) for this procurement is 541310

(Architectural Services) and the size standard under this code is $7,500,000 (maximum average annual receipts to qualify as a Small Business per 13 CFR § 121.104 a).

4 In the RFQ it indicates a 1” margin on the pages. If we use the standard SF330 Part I and II forms, the margin is outside of that 1”. Could you clarify the 1” margin?

SF330 Parts I and II should be utilized without reformatting. All attached, additional pages should be formatted with 1" margins.

5 I noticed that F22R010013 was released under the 236220 (Construction) NAICS. Based on the scope, do you intend to modify this to an AE NAICS so design firms are able to respond?

Yes; please see above.

6 I viewed the attachment on Sam.gov and did not see any information about the walk-through date and time. Is there anyway you provide me with that information?

Please see the third paragraph on page 10: There will not be a scheduled tour of the NASM Mall site prior to submission of responses to this solicitation.

RFP - F22R010013/Multidisciplinary A/E

RESPONSES TO BIDDER QUESTIONS

File details come from the government source that posted it. Updated .