The document provided appears to be Salient Characteristics for two lift station pumps and control panels required for the Building 97 and Building 509 sewage lift stations at Joint Base Charleston Air Base in South Carolina. The key details are:
The Building 97 sewage lift station requires 4 HP, 208V, 3-phase grinder pumps with 32' cables, and a duplex control panel in a NEMA 4X 304 stainless steel enclosure with main and emergency circuit breakers, pump circuit breakers, generator receptacle, alarm light and horn. The Building 509 sewage lift station requires 208V, 3-phase, 15 HP pumps with 49' cables and a quadraplex control panel with various features including a HydroRanger 200 HMI, backup level control system, and alarm telemetry.
These lift station pumps and control panels are being procured to ensure proper operation of the base's sewer system. The related federal contract opportunity is Solicitation Number F1M3E34115AQ01 for FY24 Lift Station Repair at Buildings 97 and 509, issued by the Department of the Air Force Air Mobility Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SALIENT CHARACTERISTICS
Building 97 Sewage Lift Station Pumps/Control Panel
I. GENERAL OVERVIEW.
628 CES Water and Fuel Systems shop requires the purchase of the following lift station pumps and control panel to ensure the proper operation of the base’s sewer system.
II. SPECIFICATIONS.
At a minimum the equipment and accessories shall possess the following specifications:
- Specifications:
- 4 HP
- 208v
- 3 phase grinder pumps
- 32’ cables
- Duplex DEP Economy Pump Control Panel In A NEMA 4X 304 SS
- Enclosure With Main & Emergency Circuit Breakers Interlocked
- Pump Circuit Breakers, Generator Receptacle, Alarm Light And
- Horn For Operation with Floats
III. APPLICATION.
These pumps will be installed in the wet well at the building 97 sewage lift station. The pumps are critical in transferring the sewage from building 97 to the waste system.
Flight Line Building 509 Sewage Lift Station Pumps/Control Panel
I. GENERAL OVERVIEW.
628 CES Water and Fuel Systems shop requires the purchase of the following lift station pumps and control panel to ensure the proper operation of the base’s sewer system.
II. SPECIFICATIONS.
At a minimum the equipment and accessories shall possess the following specifications:
- Specifications:
- 208v
- 3 phase
- 49’ cables
- XFP 150E CB-1.4 PE-105/4, 208v / 3 Phase,
- With 49' Cables & SS Lifting Bails
- Equipment To Include: Main Power Distribution Block, Individual Pump
- Circuit Breakers Inner Door Operable, IEC Rated Starters With 3 Leg
- Overload Protection, Power/Phase Monitoring Relay With Circuit Breaker
- Protection, Dual LED Interior Lights Motion Activated, Condensation Heater
- With Thermostat, GFI Convenience Receptacle, 120 Volt Control Transformer
- With Circuit Breaker Protection, Primary Level Control HydroRanger 200 HMI
- With XPS-15 Transducer, Back-Up Level Control System, Intrinsically Safe,
- Float Back-Up Active Light Inner Door Mounted, Seal Fail Relays With Seal
- Fail Indicator Lights, Motor Overtemp Lights, Pump Failed To Run Lights,
- Pump Run Lights, Hand-Off-Auto Selector Switches, Elapsed Time Meters,
- Quadraplex Alternator With Pump Omit Selector Switch, Panel Will Operate
- As A Duplex System With Automatic Switchover On Pump Failure, Dead Front
- Anodized Aluminum Inner Doors, Alarm Light For High Level Enclosure
- Mounted, Alarm Telemetry Dry Contacts And Relays, Spare Space For Existing
- Alarm Dialer, Terminals And Ground Bar For Field Connections, UL Listed,
- Quadraplex, 208 Volt, 3 Phase, 15 HP Pumps
III. APPLICATION.
These pumps will be installed in the wet well at the building 509 sewage lift station. The pumps are critical in transferring the sewage from the flight line buildings to the force main that runs off base to the wastewater treatment facility.