Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040341038
FWS, DIVISION OF CONTRACTING AND GE
LAKE PLAZA NORTH
134 UNION BOULEVARD
LAKEWOOD CO 80228-1807
F06
FWS, DIVISION OF CONTRACTING AND GE
LAKE PLAZA NORTH
134 UNION BOULEVARD
LAKEWOOD, CO 80228-1807
Ryan Cope 303-236-4349
17-019 x 07/11/2017
F17PS00802
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
REPAIR SEWER PIPE SYSTEM AT JONES HOLE NATIONAL FISH HATCHERY, UT
SETASIDE: Total Small Business
NAICS: 237110 - Water and Sewer Line and Related Structures Construction
PROJECT MAGNITUDE: Between $100,000 and $250,000
TECHNICAL/SPECIFICATIONS:
1. Statement of Work, 33 pages
2. Drawings, 4 pages
3. Wage Determination - UT170002, 4 pages
4. Notice to Offerors, 3 pages
WORK UNDER THIS CONTRACT:
The contractor shall provide all labor, material, and equipment necessary to replace approximately 325 feet of 8-inch diameter sewer pipeline with 8-inch PVC sewer pipe at the Jones Hole National Fish Hatchery, UT in accordance with the attached
Statement of Work and Drawings. A CCTV investigation has identified seven (7)
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 60 calendar days and complete it within ________________ ________________ calendar days after receiving
FAR 52.211-10
08/10/2017
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
FWS, DIVISION OF CONTRACTING AND GE
LAKE PLAZA NORTH
134 UNION BOULEVARD
LAKEWOOD CO 80228-1807
F06
Jon Morse
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 45
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
F17PS00802
sections of collapsed or broken pipeline.
Excavation and replacement of each section of pipe is required to eliminate ground water intrusion to the septic tank system. The performance period is 60 calendar days from the
Notice to Proceed date. The NTP will be issued once the required bonds and insurance are received.
LOCATION AND INSPECTION OF THE SITE:
The site of the work is at Jones Hole National
Fish Hatchery, located approximately 45 miles north east of Vernal, Utah. The address is 24495
East Jones Hole Hatchery Road, Vernal, Utah
84078. Failure of the contractor to ascertain the nature, location, and conditions which affect the work will not relieve the contractor from the responsibility for successfully performing the work without additional expense to the Government.
GENERAL INFORMATION:
This procurement action is being solicited as a
Total Small Business Set-aside. The NAICS code is
237110, Water and Sewer Line and Related
Structures Construction; with a size standard of
$36.5 Million. The estimated magnitude for this project is between $100,000 and $250,000. The performance period is 60 calendar days from the
Notice to Proceed date. The Notice to Proceed date will be negotiated based on the site conditions. Copies of the Request for Proposal, Statement of Work, and Drawings can be obtained at http://www.fedconnect.net and https://www.fbo.gov once available for issuance.
All questions regarding the subject requirement shall be submitted in writing via email to Ryan
Cope at ryan_cope@fws.gov. Please include the solicitation number, your company name, address, telephone number, and contact name on any correspondence.
PROSPECTIVE OFFERORS MUST BE REGISTERED WITH THE
SYSTEM OF AWARD MANAGEMENT AT:
http://www.sam.gov
Legacy Doc #: FWS
Delivery: 60 Days After Notice to Proceed
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 45
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
F17PS00802
Delivery Location Code: 0008350233
FWS JONES HOLE NFH
1380 SOUTH 2350 WEST
VERNAL UT 84078-4328 US
FOB: Destination
Period of Performance: 09/11/2017 to 11/10/2017
00010 REPAIR SEWER PIPE SYSTEM AT JONES HOLE NATIONAL
FISH HATCHERY, UT
The contractor shall provide all labor, material, and equipment necessary to replace approximately
325 feet of 8-inch diameter sewer pipeline with
8-inch PVC sewer pipe at the Jones Hole National
Fish Hatchery, UT in accordance with the attached
Statement of Work and Drawings. A CCTV investigation has identified seven (7) sections of collapsed or broken pipeline. Excavation and replacement of each section of pipe is required to eliminate ground water intrusion to the septic tank system.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Document No.
F17PS00802
Document Title
REPAIR SEWER PIPE SYSTEM AT JONES HOLE NATIONAL
FISH HATCHERY, UT
TABLE OF CONTENTS
A - Solicitation/Contract Form
B - Supplies or Services/Prices
C - Description/Specifications
E - Inspection and Acceptance
F - Deliveries or Performance
G - Contract Administration Data
I - Contract Clauses
J - List of Documents, Exhibits and Other Attachments
K - Representations, Certifications, and Other Statements of Bidders
L - Instructions,Conditions, and Notices to Bidders
M - Evaluation Factors For Award……………………………………………………………………
Document Title
A - Solicitation/Contract Form
See the SF 1442
B - Supplies or Services/Prices
BID SCHEDULE
REPAIR SEWER PIPE SYSTEM
JONES HOLE NATIONAL FISH HATCHERY, UT
Furnish all labor, materials, and equipment to complete the following work in accordance with the attached descriptions/specifications and drawings
BASE BID
ITEM NO. DESCRIPTION QTY UNIT UNIT PRICE TOTAL AMOUNT
1 Bonding 1 LS $_________ $______________
2 Mobilization & Demob ____ _____ $_________ $______________
3 Excavation ____ _____ $_________ $______________
4 Labor ____ _____ $_________ $______________
5 Materials ____ _____ $_________ $______________
6 Resurfacing ____ _____ $_________ $______________
7 Overhead & Profit ____ ______ $_________ $______________
BASE TOTAL PRICE $_____________
Document Title
C - Description/Specifications
The Specifications and Drawings are attached (See Section J)
E - Inspection and Acceptance
52.246-12 Inspection of Construction (APR 1996)
52.246-21 Warranty of Construction (MAR 1994)
F - Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the Notice To Proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days after the date the contractor receives the Notice To Proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 Liquidated Damages - Construction (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $199.60 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
G - Contract Administration Data
Prohibition on Text Messaging and Using Electronic Equipment Supplied by the Government while Driving (October 2009)
Prohibition on Text Messaging and Using Electronic Equipment Supplied by the Government while Driving (October 2009)
Executive Order 13513 , Federal Leadership On Reducing Text Messaging While Driving , was signed by President Barack Obama on October 1, 2009 (Ref: http://edocket.access.gpo.gov/2009/pdf/E9-24203.pdf).
This Executive Order introduces a Federal Government-wide prohibition on the use of text messaging while driving on official business or while using Government-supplied equipment. Additional guidance enforcing the ban will be issued at a later date. In the meantime, please adopt and enforce policies that immediately bans text messaging while driving company-owned or rented vehicles, government owned or leased vehicles, or while driving privately owned vehicles while on official government business or when performing any work for or on behalf of the government.
End of Clause
Document Title
(DOI) Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor.
To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is:
https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
A copy of the Invoice must be submitted to the Contracting Officer (CO) and the Contracting Officer’s Representative (COR) for approval, prior to submission into IPP.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
Document Title
I - Contract Clauses
52.202-1 Definitions (NOV 2013)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (MAY 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7 Anti-Kickback Procedures (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-16 Preventing Personal Conflicts of Interest (DEC 2011)
52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011)
52.204-13 System for Award Management Maintenance (OCT 2016)
52.204-14 Service Contract Reporting Requirements (OCT 2016)
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (NOV 2015)
52.211-18 Variation in Estimated Quantity (APR 1984)
52.215-10 Price Reduction for Defective Certified Cost or Pricing Data (AUG 2011)
52.215-12 Subcontractor Certified Cost or Pricing Data (OCT 2010)
52.219-8 Utilization of Small Business Concerns (NOV 2016)
52.219-9 Small Business Subcontracting Plan (JAN 2017)
52.219-14 Limitations on Subcontracting (JAN 2017)
52.222-3 Convict Labor (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation (MAY 2014)
52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 2014)
52.222-6 Construction Wage Rate Requirements (MAY 2014)
52.222-7 Withholding of Funds (MAY 2014) https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1138393
Document Title
52.222-8 Payrolls and Basic Records (MAY 2014)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (MAY 2014)
52.222-12 Contract Termination - Debarment (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014)
52.222-21 Prohibition of Segregated Facilities (APR 2015)
52.222-22 Previous Contracts and Compliance Reports (FEB 1999)
52.222-26 Equal Opportunity (SEP 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)
52.222-50 Combating Trafficking in Persons (MAR 2015)
52.222-54 Employment Eligibility Verification (OCT 2015)
52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997)
52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)
52.223-6 Drug-Free Workplace (MAY 2001)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)
52.227-1 Authorization and Consent (Dec 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Dec 2007)
52.227-4 Patent Indemnity—Construction Contracts (Dec 2007)
52.228-5 Insurance - Work on a Government Installation (JAN 1997)
52.229-3 Federal, State, and Local Taxes (FEB 2013)
52.232-17 Interest (MAY 2014)
52.232-23 Assignment of Claims (MAY 2014)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)
52.233-1 Disputes (MAY 2014)
Document Title
52.233-3 Protest after Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.242-13 Bankruptcy (JUL 1995)
52.242-14 Suspension of Work (APR 1984)
52.243-4 Changes (JUN 2007)
52.248-3 Value Engineering - Construction (OCT 2015)
52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) - Alternate I
(SEP 1996)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
52.215-8 Order of Precedence - Uniform Contract Format (OCT 1997)
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
(a) The Schedule (excluding the specifications).
(b) Representations and other instructions.
(c) Contract clauses.
(d) Other documents, exhibits, and attachments.
(e) The specifications.
(End of clause)
52.219-28 Post-Award Small Business Program Re-representation (JUL 2013)
(a) Definitions. As used in this clause-
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall re-represent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
Document Title
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts-
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall re-represent its size status in accordance with the size standard in effect at the time of this re-representation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following re-representation and submit it to the contracting office, along with the contract number and the date on which the re-representation was completed:
The Contractor represents that it ___ is, ___ is not a small business concern under NAICS Code [insert NAICS Code] assigned to contract number [insert contract number]. (Contractor to sign and date and insert authorized signer's name and title).
(End of clause)
52.225-9 Buy American - Construction Materials (MAY 2014)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
Document Title
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non-availability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)).
The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
Document Title
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description
Unit of Measure Quantity Price
(Dollars)*
Item 1:
Foreign construction material ________ ________ ________
Document Title
Domestic construction material ________ ________ ________
Item 2:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
52.228-15 Performance and Payment Bonds - Construction (OCT 2010)
(a) Definitions. As used in this clause -
"Original contract price" means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained
Document Title from the U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, 3700 East West Highway, Room 6F01, Hyattsville, MD 20782. Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
(End of clause)
52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if -
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that -
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
Document Title
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the unearned amount), the Contractor shall -
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until -
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as -
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) above shall not apply to that portion of progress payments attributable to bond premiums.
Document Title
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after -
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C. 6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A contract action is any action resulting in a contract, as defined in FAR Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under subparagraph (d)(2) of this clause shall be -
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
(End of clause)
52.232-27 Prompt Payment for Construction Contracts (JAN 2017)
Notwithstanding any other payment terms in this contract, the Government will make invoice payments under the terms and conditions specified in this clause. The Government considers payment as being made on the day a check is dated or the date of an electronic funds transfer. Definitions of pertinent terms are set forth in sections 2.101, 32.001, and 32.902 of the Federal Acquisition Regulation. All days referred to in this clause are calendar days, unless otherwise specified. (However, see paragraph (a)(3) concerning payments due on Saturdays, Sundays, and legal holidays.)
(a) Invoice payments—
(1) Types of invoice payments. For purposes of this clause, there are several types of invoice payments that may occur under this contract, as follows:
(i) Progress payments, if provided for elsewhere in this contract, based on Contracting Officer approval of the estimated amount and value of work or services performed, including payments for reaching milestones in any project.
(A) The due date for making such payments is 14 days after the designated billing office receives a proper payment request. If the designated billing office fails to annotate the payment request with the actual date of receipt at the time of receipt, the payment due date is the 14th day after the date of the Contractor’s payment request, provided the designated billing office receives a proper payment request and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.
(B) The due date for payment of any amounts retained by the Contracting Officer in accordance with the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts, is as specified in the contract or, if not specified, 30 days after approval by the Contracting Officer for release to the Contractor.
https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%202_1.html#wp1145508 https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2032_1.html#wp1024838 https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2032_9.html#wp1032906 https://www.acquisition.gov/sites/default/files/current/far/html/52_232.html#wp1152507
Document Title
(ii) Final payments based on completion and acceptance of all work and presentation of release of all claims against the Government arising by virtue of the contract, and payments for partial deliveries that have been accepted by the Government (e.g., each separate building, public work, or other division of the contract for which the price is stated separately in the contract).
(A) The due date for making such payments is the later of the following two events:
(1) The 30th day after the designated billing office receives a proper invoice from the Contractor.
(2) The 30th day after Government acceptance of the work or services completed by the Contractor. For a final invoice when the payment amount is subject to contract settlement actions (e.g., release of claims), acceptance is deemed to occur on the effective date of the contract settlement.
(B) If the designated billing office fails to annotate the invoice with the date of actual receipt at the time of receipt, the invoice payment due date is the 30th day after the date of the Contractor’s invoice, provided the designated billing office receives a proper invoice and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.
(2) Contractor's invoice. The Contractor shall prepare and submit invoices to the designated billing office specified in the contract. A proper invoice must include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of this clause. If the invoice does not comply with these requirements, the designated billing office must return it within 7 days after receipt, with the reasons why it is not a proper invoice. When computing any interest penalty owed the Contractor, the Government will take into account if the Government notifies the Contractor of an improper invoice in an untimely manner.
(i) Name and address of the Contractor.
(ii) Invoice date and invoice number. (The Contractor should date invoices as close as possible to the date of mailing or transmission.)
(iii) Contract number or other authorization for work or services performed (including order number and line item number).
(iv) Description of work or services performed.
(v) Delivery and payment terms (e.g., discount for prompt payment terms).
(vi) Name and address of Contractor official to whom payment is to be sent (must be the same as that in the contract or in a proper notice of assignment).
(vii) Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.
(viii) For payments described in paragraph (a)(1)(i) of this clause, substantiation of the amounts requested and certification in accordance with the requirements of the clause at 52.232-5, Payments Under Fixed- Price Construction Contracts.
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the https://www.acquisition.gov/sites/default/files/current/far/html/52_232.html#wp1152507
Document Title applicable solicitation provision (e.g., 52.232-38, Submission of Electronic Funds Transfer Information with Offer), contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(xi) Any other information or documentation required by the contract.
(3) Interest penalty. The designated payment office will pay an interest penalty automatically, without request from the Contractor, if payment is not made by the due date and the conditions listed in paragraphs (a)(3)(i) through (a)(3)(iii) of this clause are met, if applicable. However, when the due date falls on a Saturday, Sunday, or legal holiday, the designated payment office may make payment on the following working day without incurring a late payment interest penalty.
(i) The designated billing office received a proper invoice.
(ii) The Government processed a receiving report or other Government documentation authorizing payment and there was no disagreement over quantity, quality, Contractor compliance with any contract term or condition, or requested progress payment amount.
(iii) In the case of a final invoice for any balance of funds due the Contractor for work or services performed, the amount was not subject to further contract settlement actions between the Government and the Contractor.
(4) Computing penalty amount. The Government will compute the interest penalty in accordance with the Office of Management and Budget prompt payment regulations at 5 CFR Part 1315.
(i) For the sole purpose of computing an interest penalty that might be due the Contractor for payments described in paragraph (a)(1)(ii) of this clause, Government acceptance or approval is deemed to occur constructively on the 7th day after the Contractor has completed the work or services in accordance with the terms and conditions of the contract. If actual acceptance or approval occurs within the constructive acceptance or approval period, the Government will base the determination of an interest penalty on the actual date of acceptance or approval. Constructive acceptance or constructive approval requirements do not apply if there is a disagreement over quantity, quality, or Contractor compliance with a contract provision. These requirements also do not compel Government officials to accept work or services, approve Contractor estimates, perform contract administration functions, or make payment prior to fulfilling their responsibilities.
(ii) The prompt payment regulations at 5 CFR 1315.10(c) do not require the Government to pay interest penalties if payment delays are due to disagreement between the Government and the Contractor over the payment amount or other issues involving contract compliance, or on amounts temporarily withheld or retained in accordance with the terms of the contract. The Government and the Contractor shall resolve claims involving disputes, and any interest that may be payable in accordance with the clause at FAR 52.233-1, Disputes.
(5) Discounts for prompt payment. The designated payment office will pay an interest penalty automatically, without request from the Contractor, if the Government takes a discount for prompt payment improperly. The Government will calculate the interest penalty in accordance with the prompt payment regulations at 5 CFR Part 1315.
(6) Additional interest penalty.
(i) The designated payment office will pay a penalty amount, calculated in accordance with the prompt payment regulations at 5 CFR Part 1315 in addition to the interest penalty amount only if— https://www.acquisition.gov/sites/default/files/current/far/html/52_232.html#wp1153462 https://www.acquisition.gov/sites/default/files/current/far/html/52_232.html#wp1153351 https://www.acquisition.gov/sites/default/files/current/far/html/52_232.html#wp1153375 https://www.acquisition.gov/sites/default/files/current/far/html/52_233_240.html#wp1113304
Document Title
(A) The Government owes an interest penalty of $1 or more;
(B) The designated payment office does not pay the interest penalty within 10 days after the date the invoice amount is paid; and
(C) The Contractor makes a written demand to the designated payment office for additional penalty…
This is the start of the file's text. The full file is on GovTribe.