AM_1_QA_NMAH_Roof_F16SOL10043.pdf

PDF 548 KB Posted

Attached to
Roof Repair at National Museum of American History
Solicitation number
F16SOL10043
Issued by

View the file

Other files

File Type Posted
FINAL_AMENDMENT_TO_F16SOL10043.pdf PDF
AM_2_QA_NMAH_Roof_F16SOL10043.pdf PDF
FINAL_F16SOL10043.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

F16SOL10043

x x

3 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

OCON

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

SMITHSONIAN INSTITUTION

130310105/06/2016000001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/06/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The solicitation numbered F16SOL10023 is hereby amended as follows:

1) Questions submitted as of May 26, 2016 and answers thereto are attached hereto and incorporate by reference;

2) Please send a pdf copy of your proposal to Eve Errickson at ErricksonE@si.edu, without supporting documents (ie, any document that does not count toward the page limitation) June

9, 2016, at 3:00 pm. The pdf counts as timely submission of the proposal in the event of late deliveries of hard copies.

3) Please provide three(3) paper copies each of your technical and cost proposals.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Dorothy A. Leffler

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Erricksone Typewritten Text X

Erricksone Typewritten Text

Erricksone Typewritten Text

Erricksone Typewritten Text

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

F16SOL10043/000001

Proposals are due June 9, 2016, at 3:00 PM Eastern Standard Time.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Smithsonian Institution Last Updated 5/26/16 915 AM EE

Office of Planning Design & Construction

PROJECT: NMNH Roof Repairs & Improvements, F16SOL10043

SI RFI Number Date Company Request for Information SI Response

S001 Grunley 1 1. The RFP requires tape bound submission. Can there be an alternative means of submitting the proposal?

A three ring binder is acceptable. Tape binding is preferred.

Grunley 2 2. The RFP requires that we provide a project-specific Contractor Quality Control

Plan. Can the CQC Plan be bound separately from the Technical Proposal?

Yes.

Grunley 3 3. The RFP requires that we provide a preliminary job-site safety plan. Can this plan be bound separately from the Technical Proposal?

Yes.

Grunley 4 4. L.14.3 is titled Past Performance, but the requirements are listed to respond to an approach to schedule management not past performance. Please clarify if the title needs to be changed or if the content should be related to past performance?

Your response should show your firm's track record of managing project schedules.

We do apologize for the confusion.

Grunley 5 With regard to the Key Personnel and Subcontractors section (L.14.2) of the RFP, please specify the positions for which resumes should be provided by the subcontractors (i.e., Project Manager, Foreman)?

The key personnel resumes for subcontractors should at a minimum include representatives from key trades as you deem necessary for successful completion of the project.

Grunley 6 For the References section (L.14.4) of the RFP, it indicates the inclusion of "three references/former clients. Include relevant project information . . . " Can you please clarify what project information needs to be included?

The reference information should include anything from the past project that you think is relevant to our selection process.

Grunley 7 The RFP indicates the provisions of Sections G, H, and K, but these sections are not specified in the documents. Can you please indicate or provide these sections?

Please accept our apologies for the confusion. The Sections in Exhibit A are as follows: Section G is Contract Administration; Section H is Special Contract

Requirements; and Section K is Representations & Warranties.

Grunley 8 The deadline for technical clarifications is stated in Section L.13.8 as June 3, 2016.

What does this mean?

Generally, all questions relating to the bid should be sent well in advance of the bid date to allow us reasonable time to respond. However, any significant technical concern identified during your review should be sent as soon as feasible.

Grunley 9 Please provide the HazMat report for this project. A HazMat report specific to this project was not prepared. Please follow the specifications for hazardous materials protocols. Areas with suspected lead based paint or ACM include: steel dunnage supporting cooling towers, original waterproofing under monumental stair ramps, pipe insulation, and the steel support structure at the Infinity Sculpture. OSHEM IH will come and perform testing upon request for suspected hazmat.

S002

Grunley 1

Per the note on sheet G1 01 we are to construct stairs fron 2nd floor terrace to 5th floor terrace in a planter. The note goes on to say demo and replace new trees and landscaping. Please provide a plant list of all items required to be replaced.

Contractor is to remove (8) crepe myrtle trees from (4) east side planters, and remove all other plantings present. SI will replace all plantings.

Smithsonian Institution Last Updated 5/26/16 915 AM EE

Office of Planning Design & Construction

PROJECT: NMNH Roof Repairs & Improvements, F16SOL10043

SI RFI Number Date Company Request for Information SI Response

Grunley 2

Please clarify if the FY2016 and FY2017 Funding Increment breakdowns on pages

12 and 13 of the RFP are to include costs for the base bid only or base bid and options?

Yearly increment break down should cover the base bid only.

Grunley 3 Please provide the correct proposal delivery address because page 16 of the RFP conflicts with the SF 1442.

Smithsonian Facilities/Capital Gallery West/600 Maryland Avenue SW/Suite

5001/Washington, DC 20024/ATTN: EVE ERRICKSON

Grunley 4 Please confirm that a bid guarantee is required per page 39 of the RFP. This currently conflicts with the SF 1442 checkbox.

A bid guarantee is required.

Grunley 5

Please provide the wage scale to be used for this solicitation as mentioned in the

RFP part L43.

The wage determination DC2 current as of June 9, 2016.

Grunley 6

Page 74 of the RFP states that the base bid work is to be complete by May 1, 2017.

Do you have an anticipated award date and revised completion date to be used in the technical proposal schedule?

Our current schedule lists anticipated award date by September 30, 2016; substantial completion for the project must be achieved by Sept 30, 2017. The May 1st deadline will be required for completion of the west terrace and the front entry. This is reflected in notes #8 and 9, page BB-G103.

Grunley 7

Please consider postponing the bid date 1 week to allow for sufficient subcontractor participation in the bid pricing and technical approach process required for this bid.

The bid due date is extended to June 9, 2016, 3 pm EST.

Grunley 8

Please confirm that Options 2, 3 & 5 of this bid will not be exercised prior to or without Option 4 as indicated per the RFP, page 14, Part C.3.

Correct. Options 2, 3, and 5 will not be exercised prior to, or without, Option 4.

End of RFIs