1354510_HAZY_Parking_Control_Upgrade_SPECS_(3).pdf
PDF 3 MB Posted
- Attached to
- RFP For PARCS Improvement at NASM-Hazy
- Solicitation number
- F15SOL10041
About this file
Proposed specifications for RFP F15SOL10041
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IT-960-TN14.pdf | ||
| Geotechnical_Engineering_Report_2014-Jun-25.pdf | ||
| Am_1_F15SOL10041.pdf | ||
| Special-Cond-for-AE-Services-2011-Oct-03.pdf | ||
| RFPF15SOL10041.pdf | ||
| Plans_1354510_2014-11-21_SIGNED_(2).pdf | ||
| Past_Perf_ _Exp_PARCS.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
Division Description No. of Pages
00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
01 - GENERAL REQUIREMENTS
010000 General Requirements 1-4 011000 Summary 1-3 011400 Work Restrictions 1-8 012100 Allowances 1-4 012200 Unit Prices 1-2 012300 Alternates 1-2 012600 Contract Modification Procedures 1-4 012900 Payment Procedures 1-6 013100 Project Management and Coordination 1-12 013200 Construction Progress Documentation 1-14 013233 Photographic Documentation 1-6 013300 Submittal Procedures 1-14 014000 Quality Requirements 1-8 014100 Testing Laboratory Services 1-12 014200 References 1-10 015000 Temporary Facilities and Controls 1-21 016000 Product Requirements 1-9 017300 Execution Requirements 1-8 017329 Cutting and Patching 1-6 017700 Closeout Procedures 1-8 017823 Operations and Maintenance Data 1-9 017839 Project Record Documents 1-5 017900 Demonstration and Training 1-6 018113 Sustainable Design Requirements (LEED 2.2) 1-10 018114 VOC Limit/Indoor Finishing Performance Requirements 1-9 018115 Construction Waste Management and Disposal 1-11 018116 Indoor Air Quality Requirements 1-6 018117 Erosion and Sedimentation Control 1-2 019113 Commissioning 1-22
02 - EXISTING CONDITIONS
024119 Selective Demolition 1-6
03 - CONCRETE
033000 Cast-In-Place Concrete 1-17
11 - EQUIPMENT
111211 Parking Program System 1-90
26 - ELECTRICAL
260500 Common Work Results for Electrical Security Supplement 1-11
260519 Low-Voltage Electrical Power Conductors and Cables 1-2 260526 Grounding and Bonding for Electrical Systems 1-5 260533 Raceway and Boxes for Electrical Systems 1-7 262000 Low-Voltage Electrical Transmission 1-3 262200 Low-Voltage Transformers 1-4 262716 Electrical Cabinets and Enclosures 1-4
27 - COMMUNICATIONS
271300 Communications Backbone Cabling 1-7 275100 Distributed Audio-Visual Communication, Security Supplement 1-5
28 - ELECTRONIC SAFETY & SECURITY
280500 Common Work Results for Electronic Security 1-15 280513 Conductors and Cables for Electronic Safety and Security 1-22 281300 Access Control 1-7 281600 Intrusion Detection 1-7 282300 Video Surveillance 1-5
31 - EARTHWORK
311000 Site Clearing 1-6 312000 Earth Moving 1-11
32 - EXTERIOR IMPROVEMENTS
321216 Asphalt Paving 1-9 321313 Concrete Paving 1-6 321373 Concrete Paving Joint Sealants 1-5 321723 Pavement Markings 1-2 321726 Tactile Warning Surfacing 1-5 329200 Turf and Grasses 1-6
33 - UTILITIES
334100 Storm Utility Drainage Piping 1-6
SPECIAL PROVISIONS
Dedicated Dynamic Message Signs 1-21 Level 2 Electric Vehicle Charging Stations 1-11
11/21/14 OFEO Project No. 1354510
Parking Entrance Control Upgrades Smithsonian Institution National Air and Space Museum Udvar-Hazy Center
01 00 00 - 1 of 4
SECTION 01 00 00 – GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. The Contract Documents in their entirety, including the Drawings, Specifications/Project
Manual, Construction Contract Clauses, and any other documents issued as part of the Contract, apply to this Section.
B. Other Related Documents include:
1. Smithsonian Institution Contract Clauses for Fixed Price.
2. Drawings, dated November 21, 2014, sheets 1 through 33 and Specifications, dated
November 21, 2014 pages 1 through 549.
3. Other Documents, including: Geotechnical/Soils Reports, and Project Survey.
1.2 PROJECT INFORMATION
A. Project No.: 1354510
B. Project Title: Parking Entrance Control Upgrades
C. Project Location: National Air and Space Museum. Udvar-Hazy Center 14390 Air & Space Museum Parkway Chantilly, VA 20151
D. Smithsonian Institution Contacts:
Contracting Officer (CO) Address for Fed Ex and UPS Delivery:
Contracting Officer Smithsonian Institution Office of Contracting
MRC 1200
2011 Crystal Drive Arlington, VA 22202
01 00 00 - 2 of 4
Contracting Officer (CO) Address for USPS Delivery:
Contracting Officer Smithsonian Institution Office of Contracting
MRC 1200
P.O. Box 37012 Washington, DC 20013-7012
Contracting Officer's Technical Representative (COTR)* Address for Fed
Ex and UPS Delivery:
Contracting Officer’s Technical Representative
Smithsonian Institution Office of Engineering Design & Construction
MRC 511
600 Maryland Avenue SW Suite 5001 Washington, DC 20024
Contracting Officer's Technical Representative (COTR)* Address for USPS
Delivery:
Contracting Officer’s Technical Representative
Smithsonian Institution Office of Engineering Design & Construction
MRC 511
P.O. Box 37012 Washington, DC 20013-7012
* The Drawings and Specifications contain numerous referances to the Contracting Officer’s
Technical Representative (COTR) which means the same thing as COR. COR is the proper term and should be used by the Contractor.
1.3 AVAILABILITY OF DOCUMENTS
A. The administrative solicitation documents (Request for Proposal, Construction Contract Clauses) are available, at no cost to the bidder/offeror, from the Contracting Officer. Technical documents, such as Drawings, Project Manual/Specifications, and other reports, are available as listed below.
B. Copies of the Drawings and Specification may be obtained from:
MBC Precision Imaging.
2000 L Street, NW Washington, DC 20036 Telephone No.: 202-331-0576
01 00 00 - 3 of 4
All drawings shall be printed at full size only. The cost of printing and delivery of copies of the Drawings and Specifications shall be borne by the bidder/offeror. The Final Geotechnical Report and Soils Classification Report are available separately from the printer as it is not a Contract Document. All these costs are non-refundable.
C. The successful Contractor will be supplied with 10 sets of the Drawings and Specifications after award of the Contract, at no expense to the Contractor.
1.4 DRAWING FORMATS AND CONVENTIONS
A. Drawing Format: The Drawings are organized in industry-standard discipline format.
1. Sheet / Drawing Numbering: The sheets of the drawing set display a dual numbering system. Drawings are numbered with letters identifying the discipline and numbers identifying both the drawing type and sequence. In addition, the sheets are numbered sequentially (1 of “total number in set”) from the Cover/Title Sheet to the final sheet in the set.
2. Volumes: The Drawings may be divided into two or more volumes for ease of binding.
B. Drawing Content: The Drawings use industry-standard conventions for the style of language, symbols, and layout.
1.5 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification/Project Manual Format: The Specifications are organized into Divisions and
Sections using the 50-division format and CSI/CSC's "MasterFormat" numbering system.
1. Section Identification: The Specifications use section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Specifications/Project Manual are in numeric sequence; however, the sequence may be incomplete. Consult the table of contents at the beginning of the Specifications/Project Manual to determine numbers and names of sections in the Contract Documents.
2. Page Numbering: The pages of the Specifications/Project Manual are numbered sequentially in the upper right hand corner (header). Individual sections may or may not include subordinate section page numbering at the bottom of the page (footer).
3. Volumes: The Specifications/Project Manual may be divided into two or more volumes for ease of binding.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract
Documents is abbreviated. Words and meanings shall be interpreted as appropriate.
01 00 00 - 4 of 4
Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
1.6 ELECTRONIC DATA
A. General: Electronic copies of CAD Drawings of the Contract Drawings may or may not be provided by the COTR for Contractor's use in preparing submittals. If provided, however, electronic data is non-contractural. It is provided for reference purposes only for the convenience of the Contractor and may not be used for any other facility other than that for which it was prepared. Neither the Architect/Engineer nor the Smithsonian Institution guarantee that the files are complete, current, and accurate; thus use of electronic data is at the Contractor’s risk. By accepting these CAD files, the Contractor agrees to defend, indemnify, and hold harmless both the Architect/Engineer, its consultants, and the Smithsonian Institution from any and all claims, damages, losses and expenses arising from the use of the electronic data. The “hardcopy” Construction Documents (Drawings and Specifications/Project Manual) are the official and legally recognized Contract Documents.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01 00 00
01 10 00 - 1 of 3
SECTION 01 10 00 - SUMMARY
1.2 CONTRACT
A. Project will be constructed under a general construction contract.
1.3 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents
2. Type of the Contract
3. Work Phases
4. Work under other contracts
5. Owner-furnished products
6. Use of premises
7. Owner’s occupancy requirements
8. Work restrictions
9. Specification formats and conventions
10. Project indentification and temporary signs
11. Compliance with industry standards
12. Electrical ratings
13. References
B. Related Sections include the following:
1. Division 01 Section “Temporary Facilities and Controls” for limitations and procedures giverning temporary use of Owner’s facilities.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Project consists of reconstruction of vehicular entry and exit lanes in association with the implementaion of a Parking Access and Revenue Control System
(PARCS).
1. Project Location: 14390 Air and Space Museum Parkway, Chantilly, Virginia 20151
01 10 00 - 2 of 3
2. Owner: Smithsonian Institution, Washington, DC 20560
B. Architect/Engineer (A/E) Identification: The Contract Documents, dated November 3, 2014, were prepared by Kimley-Horn and Associates, Inc. and The Protection Engineering Group.
C. Construction Manager: TBD has been engaged as Construction Manager for this Project to serve as an advisor to the Smithsonian Institution and to provide assistance in administering the Contract for Construction between the Smithsonian Institution and Contractor, according to a separate contract between the Smithsonian Institution and Construction Manager.
D. Provide all supervision, labor, materials, and equipment needed for the project description below and, as set forth in the Drawings for OFEO Project Number 1354510, Sheets 1 through 33, and in these specifications (both dated November 21, 2014).
1. The Work includes, but is not limited to: Demolition and reconfiguration of existing site entry ticket booths and vehicle entry/exit lanes. Implementation of new Parking Access and Revenue Control System (PARCS) and reconstruction of vehicular entry/exit lanes.
2. The successful Contractor shall be fully qualified to perform the complete Work, including all critical elements of the Work. Upon request of the Contracting Officer, submit a statement of qualifications for the following critical elements of the Work:
• Phasing of the work including lane closures and areas of work.
E. The Work will be constructed under a single prime contract.
1.5 CONTRACT TIME FOR COMPLETION
A. Begin work under this contract within ten (10) calendar days after the Notice-to-Proceed (NTP) and complete all work within the total Contract Time. Complete all work, including project close-out activities, in every respect within the Contract Time.
B. The start date and completion date shall be as stated in the Notice-to-Proceed issued by the
Contracting Officer. The duration of Contract Time is 120 CALENDAR days.
1.6 WORK SEQUENCE
A. The Work shall be conducted in 3 phases. See design plan plan sheets C 112 through C 114 for additonal phasing information
1.7 USE OF PREMISES
A. General: Contractor shall have use of premises for construction operations, including use of
Project site, during construction period, as described in Division 1, Section 01 14 00, “Work
01 10 00 - 3 of 3
Restrictions”. Contractor's use of premises may be limited by the Smithsonian Institution's right to perform work or to retain other contractors on portions of Project.
1.8 WORK UNDER OTHER CONTRACTS
A. NOT USED
1.9 MISCELLANEOUS PROVISIONS
A. Museum Artifacts and Scientific Research Materials: The handling of museum artifacts or scientific research experiments by the Contractor is strictly prohibited without written consent of the Smithsonian Institution. The existing museum artifacts and research related materials may be moved only by authorized Smithsonian museum curatorial personnel. An offender of this clause may be subject to arrest or removal from the premises and project by Smithsonian security officers.
1. If temporary relocation of artifacts or research experiments is necessary, give notice to the COTR at least five working days in advance of the time that the relocation is needed.
2. Take reasonable care to minimize fluctuations in air conditions and quality, particularly in areas containing artifacts, storage collections, laboratories, and scientific research experiments. Humidity and temperature controlled areas require consistency of utility operation.
B. Protection of Historic Properties and Archaeological Material: Cultural resources are protected under the National Historic Preservation Act, other federal legislation, and the Smithsonian Institution Policy on Historic Preservation.
C. Hazardous Materials: Notify the COTR immediately if any suspected asbestos-containing materials, lead paint, PCB’s, or other hazardous materials are uncovered during the course of the Work.
PART 2 - PRODUCTS (Not Used)
PART 3 – EXECUTION (Not Used)
END OF SECTION 01 10 00
01 14 00 - 1 of 8
SECTION 01 14 00 - WORK RESTRICTIONS
1.2 USE OF PREMISES
A. Use of Site: During the construction period, the Contractor shall have full use of the premises for construction operations, including use of the site within the “Limits of Construction”. The Contractor’s use of the premises is limited only by the Smithsonian Institution’s right to perform work or retain other contractors on portions of the Project. Security of the site is the responsibility of the Contractor.
B. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to the entry security building and in the immediate surrounding area. These areas are indicated on the Contract Documents as “Limits of Disturbance.” Space allocation and availabilty are subject to change, at the discretion of the SI to meet the needs of all parties requiring access and space within the building and surrounding areas.
2. Smithsonian Institution (SI) Occupancy: Allow for SI occupancy of the premises in the following areas: Existing Security Building during the construction of the entry/exit lanes and PARCS system. Non-Public, Tenant, and Secured Spaces: Certain tenant spaces, non-public spaces, utility and equipment rooms, and other areas related to or used for purposes of storage, conservation, research, curation of museum collections and artifacts or for scientific research may have restricted access.
3. Access to Areas outside the Project Site: Identify to the COTR as soon as possible, but no less than 2 working days in advance, any occupied areas that the Contractor must access that are located ouside the limits of the Project Site. Identify in writing: a) location of restricted areas needing access (room names and numbers), b) specific reason for needing access, c) nature of the work to be performed, d) date(s) and hours needed to complete construction work activity.
5. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to the Smithsonian Institution, SI's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
01 14 00 - 2 of 8
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
c. Provide traffic control during business hours for both vehicular and service access to the project area. Control must include deliveries along main access road to project area.
d. All Contractor staff associated with traffic control shall be trained and certified.
6. Contractor Parking: Arrangments for Contractor parking are the sole responsibility of the Contractor.
a. Any assigned space(s) can only be used by the company vehicle. The vehicle must be clearly marked with the company name and/or logo. Vehicles not in compliance with this paragraph are subject to ticketing and towing. Costs associated with parking violations are the sole responsibility of the Contractor.
b. Parking is available from the Smithsonian Institution at the Project Site in an area to be identified by the COTR at the Pre-Construction Conference.
7. Contractor Deliveries, Hauling, and Access: The Contractor’s materials and equipment shall be delivered, received, and handled by the Contractor’s personnel.
a. Access to the building for on- and off-loading of all materials, structures, and equipment is through the main acces road. Access is restricted to the following times: business hours or as coordinated with the COTR.
C. Use of Existing Building: Maintain existing building in a weathertight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
1. Close and secure any temporary opening in the building perimeter or between non-public and public interior spaces with a means acceptable to the COTR at the end of each workday. Maintain a clear and safe path at all times to allow circulation. Secure Contractor facilities and equipment during non-working times at Contractor’s expense.
Authorized SI personnel shall have access to the Project Site.
D. Use of Utilities: When existing utilities are available for the Contractor’s use, per the Contract
Clauses, observe the following:
1. Any planned interruption in utility service shall be approved by and coordinated through the COTR. Submit a written request as far in advance of the scheduled interruption as possible, but no less than 2 full working days in advance. Make the necessary temporary provisions to supply continuous electric power, HVAC space conditioning, and security as required during periods when service is interrupted.
2. The Contractor’s work efforts to restore service shall be continuous until the interrupted utility is back in service.
3. The electric power for for all areas may not be interrupted.
01 14 00 - 3 of 8
E. Welding, and Cutting: Obtain a daily permit from the Building Manager’s Office (through the
COTR) for each day that welding, torch cutting, or other heating operations are to occur inside existing SI structures. Apply for daily permit at least 2 working days in advance of the start of such operations. Post permit at jobsite prior to beginning the scheduled work.
1. Perform no welding or torch cutting without adequate fire protection. Maintain a “fire watch” for the duration of the welding, cutting, and heating operations and for at least 30 minutes after the “hot” work has stopped. Provide adequate ventilation to prevent air contamination or the accumulation of toxic fumes. Provide access to a fire extinguisher (minimum 10 pounds, dry-chemical type, typical) during and after welding, cutting, and heating operations.
F. Drilling: The use of impact hammers or other equipment causing vibration, noise, and dust my be harmful to Smithsonian collections, historic structures and fabric, and/or building occupants.
Request approval from the COTR at least 5 working days prior to beginning this type of work.
G. Existing Fire Protection Systems: During the course of the Work, all existing smoke and heat detectors and sprinkler heads must remain operable. Coverings may be applied to protect them from spray coatings or other hazardous conditions only during the actual construction operation. Coverings must be removed immediately after the operations have concluded.
Damaged detectors and sprinklers heads shall be replaced immediately byt the Contractor at no cost to the SI. Test all replacements after installation to the satisfaction of the COTR.
H. Existing Building Alarm Systems: Notify the Building Security Control Room (through the
COTR) prior to disturbing any security alarm wiring, device, or system. Coordinate planned distrubances at least 2 working days in advance of the scheduled work.
1. Report any unscheduled disturbance of alarm wiring, devices, or systems to the Building
Security Control Room within 3 minutes of the occurrence.
2. If any system or component is damaged by the Contractor, the SI Office of Protection
Services will determine the procedures for repairing the damage and who will perform the repair work. The Contractor shall bear the cost of the repair, including any related overtime charges.
3. Any existing to remain system being taken out of service shall have an impairment permit submitted and approved by the COTR.
I. Hours of Work, Workdays, and Government Holidays: Observe the following restrictions for normal hours and overtime work operations:
1. Perform Work under this Contract during the normal workdays of Monday through Friday, except Government Holidays as specified herein, and during the normal work hours of 7:00 am to 3:30 pm.
01 14 00 - 4 of 8
2. Smithsonian Institution / Government Holidays: For holidays that fall on Saturday, the Smithsonian holiday is observed on the previous Friday. For holidays that fall on Sunday, the Smithsonian holiday is observed on the following Monday. Official holidays are:
New Year’s Day January 1 Martin Luther King Jr.’s Birthday January, third Monday President’s Day February, third Monday Memorial Day May, last Monday Independence Day July 4 Labor Day September, first Monday Columbus Day October, second Monday Veteran’s Day November 11 Thanksgiving Day November, fourth Thursday Christmas Day December 25 President’s Inaguration Day January ___, every four years
J. Off-Hours Work and Overtime: For each occasion the Contactor chooses to work on Saturdays, Sundays, or Smithsonian holidays, or during hours other than those indicated above, obtain written permission from the COTR at least 3 working days in advance.
1. Reimburse the SI for overtime security and inspection services provided by the SI when working ouside the normal workdays and hours. If, in the opinion of the COTR, the Work cannot be accomplished during the normal workdays and hours and must be done on off-hours, overtime charges will not be incurred.
2. If the Contractor is required to accelerate the Work in order to complete the Project within the specified Contract Time, or if other conditions arise as a result of the Contractor’s management of the Work that require construction to be accomplished during other than the normal workdays and hours defined for the Project, the Contractor shall assume the cost of any additional secuity guard or inspection services at over rates.
1.3 OCCUPANCY REQUIREMENTS
A. The immediate work area will be unoccuppied; however, the Smithsonian Institution will occupy site and existing museum building. Additionally the project area will be continually in use as the primary public entrance and exit during the duration of the project. The Contractor must maintain vehicular traffic flow for entrance to and exit from the museum site during the duration of construction.. Cooperate with the SI during construction operations to minimize conflicts and facilitate SI and public usage. Perform the Work so as not to interfere with the SI's operations.
1.4 CONTRACTOR BEHAVIOR
01 14 00 - 5 of 8
A. Dress and Deportment: Contractors and subcontractors on SI-property shall conduct themselves at all times in a manner appropriate to a public place, abiding by all federal, state, and local laws and ordinances.Contractor and subcontractor personnel shall be fully and appropriately clothed at all times. The COTR may require removal of any individual from the premises and Project for unacceptable dress, demeanor, or disruptive conduct, if the Contractor’s Superintendent fails to correct conditions in violation of this paragraph.
B. Eating and drinking in Smithsonian buildings or leased space will be allowed only in designated areas. Offenders may be subject to removal from the premises and project should the Contractor's Superintendent fail to correct conditions which, in the opinion of the COTR, violate this clause.
C. The consumption of alcoholic beverages by the Contractor's personnel is prohibited in all
Smithsonian buildings or leased space.
D. Smoking or carrying lighted tobacco products is prohibited in all Smithsonian buildings or leased space, in exhibition and public spaces, in areas where hazardous materials are stored or handled, and in areas undergoing construction, renovation, or repair. Acceptable areas for smoking are outside of the building, as designated by the Smithsonian Institution.
E. The possession, sale and/or use of narcotic or other illegal substances or firearms by Contractor employees is strictly prohibited in all Smithsonian facilities and leased space. Working on the project under the influence of alcohol or illegal substances is strictly prohibited.
1.5 JOB-SITE SAFETY
A. Safety Coordinator: Designate a person responsible for safety at the project site for the duration of the project.
B. Job-Site Safety Plan: Submit a Job-Site Safety Plan within 30 calendar days of the Contract
Award and at least 10 calendar days prior to mobilization to the site for approval by the COTR.
Detail the procedures, designated persons, instructions, and reports to be used to assure job-site safety for all contractors, subcontractors, Smithsonian personnel, the public, and others on the site.
C. Occupational Safety and Health: This contract is subject to Title 29 of the Code of Federal
Regulations, Part 1910 "Occupational Safety and Health Standards" and Part 1926 "Safety and Health Regulations for Construction" pursuant to the Occupational Safety and Health Act (OSHA) of 1970 administered by the US Department of Labor, Occupational Safety and Health Administration.
D. Emergency Assistance: Post at the site telephone numbers for reporting emergencies, including the Smithsonian Office of Protection Services (OPS), ambulance, police, fire department, gas
01 14 00 - 6 of 8 utility, electric utility, water/sewer utility, poison prevention aid, and hazardous-waste handling. Post this information in a conspicuous location within the project area prior to the start of any work at the site.
E. Safety Signs: Post legible accident prevention signs in construction areas in accordance with
OSHA standards. Safety signs shall conform to ANSI 235.1 and 235.2 Vehicular traffic control devices, barricades, and signals shall conform to ANSI D6.1.
F. Report of Accident or Illness: In the event of any accident or illness for which medical assistance is required, any criminal action, or any fire, notify the appropriate authority (ambulance, police, fire department), Smithsonian Security, and the COTR.
G. Emergency Evacuation: Post evacuation routes and facility emergency/self-protection plans at the site and train all employees in emergency procedures. In the event of a fire, immediately activate the alarm at the nearest fire alarm pull station and notify building security. Upon the activation of the audible alarm, the building will be evacuated. No personnel shall reenter the facility until security personnel signal that the building is safe.
H. Contractor Personnel to be Contacted: Submit a written list of emergency telephone numbers and names of persons to contact for the General Contractor superintendent and for each major sub-contractor working on the project site. The initial list shall be submitted to the COTR at the Preconstruction Meeting. Update and resubmit this list to the COTR as needed.
1.6 TOXIC AND HAZARDOUS SUBSTANCES
A. Submit to the COTR, at least ten working days prior to their intended use, a written list of toxic and hazardous substances that will be used on the project. Submit a "Material Safety Data Sheet" similar to OSHA Form No. 20 for these substances to identify the following information:
1. Product Identification
2. Hazardous Ingredients
3. Physical Data
4. Fire and Explosion Hazard Data
5. Health Hazard Data
6. Emergency and First Aid Procedures
7. Reactivity Data
8. Spill or Leak Procedures
9. Special Protection Information
10. Special Precautions
B. Monitor the use of all toxic and hazardous substances to ensure that the specified Threshold Limit Values (TLV's) and/or Permissible Exposure Limits (PEL's) are not exceeded. Exposure of the Contractor's personnel and Smithsonian Institution employees and visitors to air-borne or
01 14 00 - 7 of 8 any other physical contact with any substance shall not exceed allowable concentrations specified in:
1. "Threshold Limit Values and Biological Exposure Indices" of the American Conference of Governmental Industrial Hygienists, and
2. Title 29 CFR Part 1910, Subpart Z - "Toxic and Hazardous Substances" of the
Occupational Safety and Health Standards.
C. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances and pollutants produced by construction operations. Remove contaminated waste in compliance with applicable laws and regulations.
D. To achieve compliance with the requirements of this section, administration or engineering controls shall first be implemented whenever feasible. When such controls are not feasible to achieve full compliance, protective equipment or other protective measures shall be used to keep exposure of all persons within the prescribed limits. Descriptions of equipment or technical measures to be used for this purpose must be submitted to the COTR for approval.
The Contractor's requirements for compliance with all applicable local, federal, and state regulations remain in force.
1.7 PERSONAL PROTECTIVE EQUIPMENT
A. Personal protective equipment for eyes, face, ears, nose, head, extremities, and/or full body shall be provided, used, and maintained by the Contractor whenever necessitated by reasons of hazards encountered in a manner capable of causing illness, injury, or impairment in the function of any part of the body.
B. Persons required to use personal protective equipment shall be thoroughly trained. Training programs shall, as a minimum, meet OSHA and EPA requirements where applicable. The Contractor shall submit proof and criteria for employee training as requested.
1.8 GENERAL SECURITY REQUIREMENTS
A. Comply with security requirements imposed by the Smithsonian Institution, including any necessary security clearances. Failure to inspect the site or obtain knowledge of security regulations shall not relieve the Contractor from security requirements or from performance of any part of the work.
B. Prior to the start of work on the site, submit to the COTR for approval, a list of the names, social security numbers, and addresses of all Contractor and subcontractor employees. Identify the Prime Contractor and each subcontractor and trade. Update list as necessary to accurately identify all workers who will be working on the site during the Project.
01 14 00 - 8 of 8
C. Provide the name and telephone number of the Contractor's Superintendent and authorized alternate individual who can be reached on a 24-hour basis at the Preconstruction Meeting.
D. Identification Badges
1. Controlled Access: Contractor and subcontractor employees shall sign in and out with the security officer on a daily basis for the duration of the Contract Time. Access to the site will be granted only to Contractor employees who sign the Site and Building Entry and Departure Register at designated entrances and who wear a Contractor Identification Badge or Day Pass in plain view for inspection. Photo identification badges with serial numbers and information about allowed access may be issued by the Smithsonian to some Contractor employees.
E. Contractor will provide and maintain a list of all personnel on site and maintain and monitor their whereabouts on a regular and daily basis.
F. Access and Property Control
1. Access to secured areas will be strictly controlled and Contractors working within them must be escorted at all times. Arrangements for security escorts must be made at least 72 hours in advance of any work being done within secured areas.
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 14 00
01 21 00 - 1 of 4
SECTION 01 21 00 - ALLOWANCES
1.2 SUMMARY
A. This Section includes administrative and procedural requirements governing allowances.
1. Certain materials and equipment are specified in the Contract Documents by allowances.
In some cases, these allowances include installation. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order.
B. Types of allowances include the following:
1. Lump-sum allowances.
2. Unit-cost allowances.
3. Testing and inspecting allowances.
4. Quantity allowances.
C. Related Sections include the following:
1. Division 1, Section 01 26 00, "Contract Modification Procedures" for procedures for submitting and handling Change Orders.
2. Division 1, Section 01 22 00, "Unit Prices" for procedures for using unit prices.
3. Division 1, Section 01 40 00, "Quality Requirements" for procedures governing the use of allowances for testing and inspecting.
1.3 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise COTR of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work. Designate in the construction progress schedule the delivery dates for projects specified under each allowance. Designate in the schedule of values the quantities of materials required under each unit cost allowances.
01 21 00 - 2 of 4
B. At the COTR’s request, obtain proposals for each allowance for use in making final selections.
Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by COTR from the designated supplier.
1.4 SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.
B. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
1.5 UNIT-COST ALLOWANCES.
A. Allowance shall include cost to Contractor of specific products and materials ordered by SI under allowance and shall include taxes, freight, and delivery to project site.
B. Contractor’s costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by SI under allowance shall be included as part of the Contract Sum and not part of the allowance.
1.6 SELECTION OF PRODUCTS UNDER ALLOWANCES
A. Contractor’s Duties
1. Assist COTR in determining qualified suppliers or installers.
2. Obtain proposals from suppliers and installers when requested by COTR
3. Provide COTR with certified copy of costs for allowance including ALL discounts, with
COTR cost being the amount the Contractor will have to pay, deleting all discounts, paybacks, etc.
4. Make appropriate recommendations for consideration of the COTR.
5. Notify COTR promptly of:
a. Any reasonable objections Contractor may have against any supplier, or party under consideration for installation.
b. Any effect on the Construction Schedule antidcipated by selections under consideration.
1.7. CONTRACTOR RESPONSIBILITY FOR PURCHASE, DELIVERY AND INSTALLATION.
A. On notification of selection, execute purchase agreement with designated supplier.
B. Arrange for and process ShopDrawings, Product Data and Samples, as required.
01 21 00 - 3 of 4
C. Make all arrangements for delivery.
D. Upon delivery, promptly inspect products for damage or defects.
E. Submit claims for transportation damage
F. Install and finish products in compliance with requirements of referenced specification sections.
1.8. ADJUSTMENT OF COSTS
A. Should the net cost be more or less than the specified amount of the allowance, the Contract Sum will be adjusted accordingly by Change Order.
1. The amount of the Change Order will recognize any changes in handling costs at the site, labor, installation costs, overhead, profit, and other expensed CAUSED by the selection under the allowance, except the Contractor will not be required to include a reduction in overhead and profit in the event the net cost is less than the specified amouont of the allowance
2. For products specified under a unit cost allowance, the unit cost shall apply to the quantities actually used with a nominal allowance for waste, as determined by receipted invoices, or by field measurement.
B. Submit any claims for anticipated additional costs at the site, or other expenses CAUSED by the selection under the allowance, prior to execution of the work.
C. Failure to submit claims within the designated time will constitute a waiver of claims for additional costs.
D. At contract closeout, reflect all approved changes in contract amounts in the final statement of accounting.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects.
Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
01 21 00 - 4 of 4
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. 1:
B. Allowance No. 2:
C. Allowance No. 3:
END OF SECTION 01 21 00
01 22 00 - 1 of 2
SECTION 01 22 00 - UNIT PRICES
A. This Section includes administrative and procedural requirements for unit prices.
1. Division 1, Section 01 21 00, "Allowances" for procedures for using unit prices to adjust quantity allowances.
2. Division 1, Section 01 26 00, "Contract Modification Procedures" for procedures for submitting and handling Change Orders.
3. Division 1 Section 01 26 00 “Contract Modifcation Procedure” for procedures for measurement and payment for implementation of unit prices as directed by COTR.
1.3 DEFINITIONS
A. Unit price is an amount proposed by bidders/offerors, stated on the Bid/Offer Form, as a price per unit of measurement for materials or services added to or deducted from the Contract Sum by appropriate modification, if estimated quantities of Work required by the Contract Documents are increased or decreased.
1.4 PROCEDURES
A. Unit prices include all necessary material, submittals, access to work areas, supervision, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
C. If requested by the COTR, provide material, equipment, and personnel to verify or determine changes in quantities. Contractor measurements and calculations shall be subject to verification by the COTR. The SI reserves the right to reject Contractor's measurement of
01 22 00 - 2 of 2 work-in-place that involves use of established unit prices and to have this work measured, at the SI’s expense, by an independent surveyor acceptable to Contractor.
D. List of Unit Prices: A list of unit prices is included at the end of this Section. Specification
Sections referenced in the schedule contain requirements for materials described under each unit price.
E. The unit prices in the following schedule shall be submitted as part of the bid/offer. The SI reserves the right to accept or reject any or all unit prices.
F. The Contractor agrees that, in the event that the Contractor is directed by the SI to increase of decrease the quantities of Work required by the Contract Documents on items listed below, the Contract amount will be adjusted on the following unit prices.
G. The unit prices are binding for the duration of the Project. No escalation or other variation is permitted unless specifically noted in the Contract.
3.1 LIST OF UNIT PRICES
A. Unit Price No. 1:
B. Unit Price No. 2:
C. Unit Price No. 3:
D. Unit Price No. 4:
E. Unit Price No. 5:
F. Unit Price No. 6:
G. Unit Price No. 7:
END OF SECTION 01 22 00
01 23 00 - 1 of 2
SECTION 01 23 00 - ALTERNATES
A. This Section includes administrative and procedural requirements for alternates.
A. Alternate: An amount proposed by bidders/offerors and stated on the Bid/Offer Form for certain work defined in the Solicitation Documents that may be added to or deducted from the Base Bid amount if the SI decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. The cost or credit for each alternate is the net addition to or deduction from the Contract
Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum.
2. The time limitation on the SI’s acceptance of the Alternate or Option will be stated in the Solicitation Documents.
1.4 PROCEDURES
A. Coordination: Modify or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.
1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.
01 23 00 - 2 of 2
B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated modifications to alternates.
C. Execute accepted alternates under the same conditions as other work of the Contract.
D. Schedule: A Schedule of Alternates is included at the end of this Section. Specification
Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.
3.1 SCHEDULE OF ALTERNATES
A. Alternate No. 1:
B. Alternate No. 2:
C. Alternate No. 3:
D. Alternate No. 4:
E. Alternate No. 5:
F. Alternate No. 6:
END OF SECTION 01 23 00
01 26 00 - 1 of 3
SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES
Contract, apply to this Section. OCON Form 6 must be used as the format for all pricing and cost information.
A. This Section specifies administrative and procedural requirements for handling and processing
Contract modifications.
1. Division 1, Section 01 21 00, "Allowances" for procedural requirements for handling and processing allowances.
2. Division 1, Section 01 23 00, "Alternates" for administrative requirements for accepting
Alternates.
3. Division 1, Section 01 22 00, "Unit Prices" for administrative requirements for using unit prices.
4. Division 1, Section 01 60 00, "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.
1.3 MINOR CHANGES IN THE WORK
A. The COTR will issue supplemental instructions, prepared by the SI or the Architect/Engineer, authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions", as responses to Contractor Requests for Information (RFI’s), or in letter format. The Contractor shall notify the COTR in writing within 5 working days if, in the Contractor’s opinion, the supplemental instructions do involve a potential change in Contract Sum or Contract Time.
1.4 PROPOSAL REQUESTS
A. Smithsonian Institution-Initiated Proposal Requests: The COTR will issue a letter requesting a cost proposal from the Contractor for proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. The letter will identify the request with a “Proposed Change Number (PCN)” and a detailed description of the proposed change. If necessary, the description will include supplemental or revised Drawings and Specifications, 01 26 00 - 2 of 3 prepared by the SI or by the Architect/Engineer on AIA Document G709, “Proposal Request”, or similar format.
1. Proposal Requests issued by the COTR are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change, unless notified otherwise.
2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. Break out labor, material and equipment for Contractor and Subcontractor direct costs.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
d. Use the standard SI Change Order estimate format, available from the Contracting Officer.
B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the
Contract, Contractor may propose changes by submitting a written request for a change to the
COTR.
1. Include a statement outlining reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. Break out labor, material and equipment for Contractor and Subcontractor direct costs.
3. Include labor costs.
4. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
5. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Division 01, Section 01 60 00, "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.
7. Request that the COTR concur that the condition is indeed a “change” and that a Proposed Change Number (PCN) be assigned.
01 26 00 - 3 of 3
1.5 ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, base each Change Order proposal on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.
3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances.
4. The SI reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the Purchase Order amount or Contractor's handling, labor, installation, overhead, and profit. Submit claims within 21 days of receipt of the Change Order, Construction Change Directive, or authorization for work to proceed. The SI will reject claims submitted later than 21 days after such authorization.
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
1.6 CHANGE ORDER PROCEDURES
A. The COTR will review the Contractor’s estimate of costs and time adjustments for proposed changes. Negotiations may follow. If an agreement is reached on price and/or time adjustment, the COTR will issue a confirmation to the Contractor in writing and begin processing the Change Order in accordance with SI standard…