6000001982 - Concrete Pumping Services
Solicitation number
0000000343
Issued by
California

About this file

This is a rate sheet (Exhibit B-1) from the California Department of Corrections and Rehabilitation (CDCR) for concrete pumping services at the California State Prison, Los Angeles County under Bid Number 6000001982. The document outlines equipment requirements and estimated usage for six different types of concrete pumping equipment: 85' Boom, 100' Boom, 120' Boom, maximum 1" aggregate hose pump, 3/8" Pea gravel line hose pump, and grout pump. Each equipment type requires hourly rates for equipment and operator, rate per yard of material, and setup/cleanup fees with round trip travel. Estimated usage varies by equipment, ranging from 20 to 33 hours of operation and 500 to 1,000 yards of material.

The pricing structure requires bidders to submit rates for all items, with zero dollar amounts being interpreted as services provided at no cost to the state. CDCR provides an Excel version of the rate sheet to assist with bid calculations, and bidders must submit both electronic (CD/diskette) and printed versions. A prompt payment discount of at least 0.5% or $50.00 minimum is available for invoices paid within 30 days, with this discount serving as a tiebreaker in the event of equal bids. The quantities listed are estimates only and the state reserves the right to modify work quantities as needed.

View the file

Other files

File Type Posted
ExhibitB-1RateSheet_Group_10(protect).xlsx XLSX spreadsheet
ExhibitB-1RateSheet_Group_5(protect).xlsx XLSX spreadsheet
ExhibitB-1RateSheet_Group_7(protect).xlsx XLSX spreadsheet
IFB_6000001982.pdf PDF
ExhibitB-1RateSheet_Group_4(protect).xlsx XLSX spreadsheet
ExhibitB-1RateSheet_Group_8(protect).xlsx XLSX spreadsheet
ExhibitB-1RateSheet_Group_9(protect).xlsx XLSX spreadsheet
ExhibitB-1RateSheet_Group_2(protect).xlsx XLSX spreadsheet
ExhibitB-1RateSheet_Group_3(protect).xlsx XLSX spreadsheet
ExhibitB-1Rate_Sheet_Group_1(protect).xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

CONCRETE PUMPING SERVICES
Inmate Ward Labor Program

Any quantities listed on Exhibit B-1 are CDCR's estimates only and are offered as a basis for comparison of bids. The State does not expressly or by implication agree that the actual amount of work will correspond therewith and reserves the right to omit portions of the work as may be deemed necessary or advisable by the State.

Electronic bid packages include an Excel version of the Rate Sheet (Exhibit B-1) in addition to the PDF file in order to assist bidders in computing accurate totals. Bidders should download the Excel version and complete all highlighted cells. Bidders should include a Compact Disk or diskette of the completed Excel version of the Rate Sheet along with the printed version when submitting their bid.

NOTE: Bidder is required to bid each item. Rates must include all fees and taxes. Failure to indicate a dollar amount in any item will be grounds to reject the entire bid. A zero dollar ($0.00) amount listed for any and all items will be interpreted and understood by the State to mean that the bidder indicating a zero dollar amount shall perform any such services at no cost to the State.

GROUP 6 - California State Prison, Los Angeles County

A. 85' Boom (or equivalent)

1. Rate per hour for Equipment & Operator hr. X 30 hours = $ - 0

2. Rate per yard X 1000 yards (est.) = $ - 0

3. Total Fee for Setup/Cleanup & Round Trip Travel X 2 Trips = $ - 0

ITEM A SUBTOTAL (Add 1 thru 3) = $ - 0

B. 100' Boom (or equivalent)

1. Rate per hour for Equipment & Operator hr. X 33 hours = $ - 0

2. Rate per yard X 1000 yards (est.) = $ - 0

3. Total Fee for Setup/Cleanup & Round Trip Travel X 2 Trips = $ - 0

ITEM B SUBTOTAL (Add 1 thru 3) = $ - 0

C. 120' Boom (or equivalent)

1. Rate per hour for Equipment & Operator hr. X 20 hours = $ - 0

2. Rate per yard X 1000 yards (est.) = $ - 0

3. Total Fee for Setup/Cleanup & Round Trip Travel X 2 Trips = $ - 0

ITEM C SUBTOTAL (Add 1 thru 3) = $ - 0

D. Maximum 1" aggregate hose pump

1. Rate per hour for Equipment & Operator hr. X 30 hours = $ - 0

2. Rate per yard X 1000 yards (est.) = $ - 0

3. Total Fee for Setup/Cleanup & Round Trip Travel X 2 = $ - 0

ITEM D SUBTOTAL (Add 1 thru 3) = $ - 0

E. 3/8" Pea gravel line hose pump

1. Rate per hour for Equipment & Operator hr. X 30 hours = $ - 0

2. Rate per yard X 500 yards (est.) = $ - 0

3. Total Fee for Setup/Cleanup & Round Trip Travel X 2 = $ - 0

ITEM E SUBTOTAL (Add 1 thru 3) = $ - 0

F. Grout pump

1. Rate per hour for Equipment & Operator hr. X 30 hours = $ - 0

2. Rate per yard X 500 yards (est.) = $ - 0

3. Total Fee for Setup/Cleanup & Round Trip Travel X 2 = $ - 0

ITEM F SUBTOTAL (Add 1 thru 3) = $ - 0

GROUP 1- TOTAL BID AMOUNT (Add Subtotals A through F)=$ - 0
BASIS OF AWARD

TOTAL BID AMOUNT $ - 0

Contractor may offer a discount on invoices in order for the invoices to be pad within 30 days of receipt Discount offered must be at least one-half of one perent and a minimum of $50.00.

Discount offered on invoices to be paid within 30 days of receipt = %

In the event of a tie absent other determining factors, the lowest responsible bid with the highest discount shall prevail.

California Department of Corrections and Rehabilitation (CDCR) Rate Sheet Bid Number 6000001982 Exhibit B-1

&P of 2

Sheet2

Sheet3

File details come from the government source that posted it. Updated .