Exhibit Q_Design Review Checklist - Architectural.pdf

PDF 150 KB Posted

Attached to
X1AA--36C24722R0028 | Goose Creek Specialty Care Clinic | New Lease RLP
Solicitation number
36C24722R0028
Issued by

View the file

Other files

File Type Posted
Exhibit E_GSA3517B-16.pdf PDF
Exhibit M_Design Review Checklist - HVAC.pdf PDF
Exhibit C_ Security Level II Standards.pdf PDF
Exhibit V_Design Manual - HVAC.pdf PDF
Exhibit CC_VA Handbook 0730 - Security and Law Enforcement.pdf PDF
Exhibit A_36C24722L0006 - Template Lease.pdf PDF
Exhibit S_Design Manual - Physical Security and Resiliency.pdf PDF
Exhibit D_GSA 3516-12.pdf PDF
Exhibit J_ Seismic Offer Forms.pdf PDF
Exhibit B_ Agency Space Requirements - Rev 1.pdf PDF
36C24722R0028_3.docx DOCX document
Exhibit EE_Design Guide - OIT - Standards Alert.pdf PDF
Exhibit Z_Space Planning - Eye Clinic.pdf PDF
Exhibit DD_Design Guide - Room Finishes.pdf PDF
Exhibit X_ Design Manual - Fire Protection.pdf PDF
Exhibit P_Design Review Checklist - Electrical.pdf PDF
Exhibit AA_Space Planning - Pulmonary.pdf PDF
Exhibit F_GSA 1364 - Proposal to Lease Space.pdf PDF
Exhibit G_GSA 1217 - Lessors Annual Cost Statement.pdf PDF
Exhibit W_Design Manual - Electrical.pdf PDF
Exhibit H_GSA12000-11.pdf PDF
Exhibit K_Telecommunications and Video Surveillance Services or Equipment.pdf PDF
Exhibit FF_Design Guide - OIT - Infrastructure Standard for Telecom Spaces.pdf PDF
Exhibit T_Design Manual - Lighting.pdf PDF
Exhibit Y_Design Manual - Architectural.pdf PDF
Exhibit U_Design Manual - Interior Design.pdf PDF
36C24722R0028.pdf PDF
Exhibit BB_VHA Directive 1061 - Legionella and Scald Prevention.pdf PDF
Exhibit R_Design Manual Plumbing.pdf PDF
Exhibit N_Design Review Checklist - Telecommunications.pdf PDF
Exhibit L_Other Standards and Requirements.pdf PDF
Exhibit I _ Davis Bacon Wage Rate.pdf PDF
Exhibit O_Design Review Checklist - Plumbing.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

March 22, 2021

ARCHITECTURAL

Reviewers should - Use Checklists when reviewing any type of VA construction project for the following disciplines:

Architectural, Boiler Safety Devices – Operation Checklist, Electrical, Heating, Ventilating, and Air Conditioning

(HVAC),

Incineration/Solid Waste, Plumbing, Fire Protection, and Sanitary, Site and Landscape, Steam Distribution, Steam Generation, and Structural.

Reviewers should - Ensure that DESIGN REVIEW Submission Instructions

(PG-18-15) for Schematic, Design Development, and Construction Documents are followed for the various types of VA construction projects.

Reviewers should - Ensure that every VA construction project is in compliance with all life safety issues.

Reviewers should - Be aware that these checklists are not all-inclusive but only provide minimum review items.

DESIGN REVIEW CHECKLIST

ARCHITECTURAL

TITLE________________________________PROJECT NO. ______________

LOCATION___________________________________DATE ______________

REVIEWED BY ___________________________________________________

ORGANIZATION _________________________________________________

The reviewer should be thoroughly familiar with the following VA standards before conducting a design review. These are available on the CFM Internet Web site: https://www.cfm.va.gov/til

ITEM DESCRIPTION

1. MASTER CONSTRUCTION SPECIFICATIONS (PG-18-1)

2. DESIGN AND CONSTRUCTION PROCEDURES (PG-18-3)

3. STANDARD DETAILS (PG-18-4)

4. EQUIPMENT GUIDE LIST (PG-18-5)

5. SPACE PLANNING CRITERIA (PG-18-9)

6. DESIGN MANUALS (PG-18-10)

7. DESIGN GUIDES (PG-18-12)

8. BARRIER FREE DESIGN GUIDE (PG-18-13)

9. ROOM FINISHES, DOOR AND HARDWARE SCHEDULES (PG-18-14)

10. MINIMUM REQUIREMENTS FOR DESIGN REVIEW SUBMISSIONS (PG-18-

15)

11. ENVIRONMENTAL PLANNING GUIDANCE (PG-18-17)

12. CULTURAL RESOURCE MANAGEMENT DIRECTIVE (D-7545)

13. CULTURAL RESOURCE MANAGEMENT PROCEDURES (H-7545)

14. DESIGN ALERTS

15 CAD and VA BIM STANDARDS

GENERAL INFORMATION FOR REVIEWERS

NO. ARCHITECTURAL - LIFE SAFETY ITEM

COMMENTS/

YES/NO/NA

1 The design of all fire safety features in new construction and renovation at VA facilities shall comply with the latest edition (the edition in effect at the bid date) of the National Fire codes (a compilation of National Fire Protection Association Codes, Standards, Recommended Practices, and Manuals). Fire protection features not included in the National Fire Codes shall be designed in accordance with the requirements of the latest edition of the International Building Code (IBC).

2 For existing buildings, the Fire Protection Engineering consultant may propose equivalent fire safety protection. The consultant shall document equivalency requests with sufficient rationale in the fire protection report for the project. VA’s Authority Having Jurisdiction shall approve all equivalency requests prior to the equivalent method being incorporated into the design.

3 Every project should have a comprehensive fire protection design plan which includes protection throughout the building by an approved automatic sprinkler system. A fire protection report, including fire protection drawings that are developed during the design development stage of the project, shall support the fire protection plan. The fire protection report shall include related design considerations and criteria that have been coordinated among all the affected disciplines, and shall serve as the basis for the design, construction, and future operation of the building.

LIFE SAFETY ISSUES

NO. ARCHITECTURAL – SCHEMATIC 1 ITEM

YES/NO/NA

1 Compliance with DESIGN REVIEW Submission Instructions (PG-18- 15)

2 Architectural narrative - Explain alternative designs and their proposed exterior materials and any other constraints affecting overall design.

3 Schematic block plans showing:

a. All floors (new and renovated)

b. Penthouse

c. Roof plan

d. Pipe basement

e. Key plan, title block, north arrow, and scale on each floor plan

f. Temporary index of drawings 4 Exterior dimensions/total building gross area:

a. Circulation

b. Mechanical areas

c. Electrical Areas

d. Exterior walls 5 Size and shape of all departmental functions and services:

a. Label each service or activity

b. Indicate boundaries

c. Show activity code number 6 Location of:

a. Entrances to buildings

b. Main entry point to each functional block

c. Mechanical spaces

d. Expansion joints

e. Structural grid

f. Special seismic structural features 7 Finished floor elevations

SCHEMATIC 1

NO. ARCHITECTURAL – SCHEMATIC 1 ITEM

COMMENTS/

YES/NO/NA

8 Finish grades at corners, entrances, exits, platforms, and ramps 9 Schematic section of building 10 Lead or any other hazardous materials abatement 11 Compliance with VA CAD and BIM standards/manual and NCS

Application Guide and applicable NCS modules.

12 Compliance with applicable requirements of any Record of Decision or Finding of No Significant Impact under NEPA, and/or any commitment or agreement under Section 106 of NHPA.

NO. ARCHITECTURAL – SCHEMATIC 2 ITEM

YES/NO/NA

2 Narrative for building construction, fire and smoke separation, fire sprinkler/standpipe systems, pump sizes, water supply available/maximum demand, water flow testing results, fire alarm systems, and kitchen extinguishing systems.

3 Floor Plans/Drawings;

a. All floors (new and renovated)

b. Penthouse

c. Roof plan

d. Pipe basement 4 Location of:

a. Rooms with room names and numbers, include program net area/design net area

b. Doors

c. Corridors

d. Basic column/grid sizes

e. Expansion and seismic joints

f. Electrical and IT closets

g. Equipment rooms

h. Signal and telephone closets

i. Mechanical shafts and space

j. Stairs

k. Ramps

l. Elevators

m. Automatic conveyances

n. Trash and linen chutes

o. Fire and smoke rated partitions

SCHEMATIC 2

NO. ARCHITECTURAL – SCHEMATIC 2 ITEM

COMMENTS/

YES/NO/NA

5 Program net area/designated net area for all rooms and departments 6 Exterior dimensions/total building gross area 7 Each integral or fragmented service outlined with name and code 8 Layout of critical areas (1:50 - 1/4 in.) showing:

a. Minimum clearances around patient beds

b. Correct bed sizes

c. Dimensions of patient wardrobes in mental health units

d. Accessible toilet and bedrooms

e. All accessible Bathroom & Bathing room floors slope to the shower drain or room drain

f. Compliance with Design Alert 149 (Refer to Women’s Health Directive 1330.2)

9 Exterior building elevations:

a. Significant materials including colors

b. Massing

c. Fenestrations

d. Relationship to adjacent structures

e. Finish grades

f. Floor-to-floor heights

g. Floor elevations

h. Exterior materials

i. Canopies at entrances and loading docks (minimum clearances)

j. Materials and elements (if any) identified for preservation, rehabilitation or restoration; see item 13

10 Building section 11 Coordinate all drawings with other technical disciplines 12 Compliance with VA NCS Application Guide and applicable NCS modules.

13 Compliance with applicable requirements of any Record of Decision or

14 Final specification update using track changes

NO. ARCHITECTURAL – DESIGN DEVELOPMENT ITEM

YES/NO/NA

2 Incorporate all of the revisions required from S2 Review

a. All floors (new and renovated)

b. Penthouse

c. Roof plan (mechanical equipment and architectural screens)

d. Pipe basement (emergency exit, ventilation, and stairs)

e. Pipe tunnel

f. Equipment floor plans 1:50 (1/4 inch) scale coordinated with VA

Equipment List

g. Ceiling Plan

(1) Ceiling Mounted equipment

(2) Lighting Fixtures

(3) Air diffusers

(4) Registers

(5) Tracks

(6) Room names and numbers

(7) Patients lifts

h. Fire Protection plan

(1) Room names and numbers

(2) Door locations and swings

(3) Smoke and fire rated partitions

(4) Areas not protected by sprinklers

(5) Main Fire Alarm Panel 4 Location of:

a. Rooms with room names and numbers

DESIGN DEVELOPMENT

NO. ARCHITECTURAL – DESIGN DEVELOPMENT ITEM

b. Doors and door swings

c. Corridors

d. Basic column/grid sizes

e. Expansion and seismic joints

f. Electrical closets

g. Signal and telephone closets

h. Equipment rooms

i. Mechanical shafts and space

j. Plumbing fixtures

k. Stairs

l. Ramps

m. Elevators

n. Automatic conveyances

o. Trash and linen chutes

p. Interior features (e.g. stair rails, light fixtures, decorative elements) thought to be historically or architecturally significant and to be preserved.

q. Lead-lined and radio-frequency shielded partitions

r. Fire and smoke rated partitions

s. Fire extinguisher cabinets

t. Bathroom & Bathing room floor drains with floors sloped to drain

u. Fixed Equipment

v. Wheelchair accessible facilities 5 Wall thickness and chase walls 6 Handrail locations and dimensions (where required) 7 Program net area/designated net area 8 Exterior building elevations:

a. Significant materials including colors

b. Massing

c. Fenestrations

d. Relationship to adjacent structures

e. Finish grades

f. Floor-to-floor heights

g. Floor elevations

h. Canopies at entrances and loading docks (minimum clearances)

i. Materials and elements (if any) identified for preservation, rehabilitation or restoration; see item 15

j. Future expansion

k. Expansion and control joints

l. Roof top equipment and architectural screens

m. Areaways and below grade openings

NO. ARCHITECTURAL – DESIGN DEVELOPMENT ITEM

n. Downspouts and gutters

o. Canopies at entrances and loading docks (minimum clearances) 9 Building sections (same scale as floor plans):

a. Finish floor elevations

b. Relationship of finish ground floor to finish grade at major entrances

c. Floor elevation alignment if building abuts existing structure

d. Floor to floor heights

e. Pipe basements and roof mechanical equipment

f. Section through elevator shaft

g. Section through stairways

10 Wall sections showing construction, building materials and systems, and proposed sill and head heights of openings

11 Finish schedule 12 Specification Section 09 06 00 for materials and products for interior design

13 Coordinate all drawings with other technical disciplines 14 Compliance with VA NCS Application Guide and applicable NCS

15 Compliance with applicable requirements of any Record of Decision or

16 Slip resistance of flooring material in Bathroom & Bathing rooms is a minimum of 0.7.

17 Equipment activation list

NO.

ARCHITECTURAL – CONSTRUCTION DOCUMENTS /

FINAL BID DOCUMENT ITEM

COMMENTS/

YES/NO/NA

2 Incorporate all of the revisions required from DD2 Review

a. Room names and numbers

b. Interior dimensions

c. Exterior dimensions and match lines

d. Column grid lines

e. Expansion joints between new and existing

f. Floor drains and pitch (all accessible Bathroom & Bathing room floors slope to drain)

g. Corner guards, handrails, bumper guards, and grab bars

h. Water coolers (near waiting rooms and along corridors)

i. Air-lock vestibules at main entrance

j. Elevator lobbies (min 12 feet deep)

k. Ducts and utility shafts that pass-through floors

l. Transformer rooms with curbs and no overhead pipes or ducts

m. Roof slope is minimum 1/4" per foot

n. Roof-top equipment with screens

o. Access doors to roof

p. Walkways on roof

q. Lightning protection

r. Door symbols

s. Lead-lines partitions and "universal floor T's"

t. Location and details of Dedication Plaque

u. Floor slab depressions identified and coordinated with structural drawings

CONSTRUCTION DOCUMENTS /

FINAL BID DOCUMENT

NO.

ARCHITECTURAL – CONSTRUCTION DOCUMENTS /

FINAL BID DOCUMENT ITEM

COMMENTS/

YES/NO/NA

v. Areaways with rails or gratings 4 Demolition Plans with existing finish schedule and notes 5 Reflected Ceiling Plan 6 Equipment Plans with elevations and details 7 Building sections, wall sections, and exterior elevations showing:

a. Finish floor elevations

b. All building systems

c. Materials

d. Future expansion 8 Fire Protection Plan:

a. Details of stairwell sign

b. Door and window schedule with fire rating and fire rated glazing

c. Location of main annunciator panel

d. Height and configuration of storage racks and shelving

e. Exit calculations 9 Graphics and Signage Plan 10 Interior details, elevations, and sections 11 Finish schedule 12 Architectural specifications edited and marked in pencil 13 Drafting symbols, abbreviations, general notes, and schedules 14 Coordinate all drawings with other technical disciplines 15 Compliance with VA NCS Application Guide and applicable NCS

16 Compliance with applicable requirements of any Record of Decision or