Exhibit M10 - Final Copy_PV Service Schedule.pdf

PDF 77 KB Posted

Attached to
Full Maintenance Services for Corpus Christi and Victoria, TX
Solicitation number
47PH0221R0001
Issued by

View the file

Other files

File Type Posted
Amendment 0002 BL8_ PM Schedule Report.xlsx XLSX spreadsheet
Amendment 0002 Questions and Answers.pdf PDF
Amendment 0002 Corpus Christi Victoria OM FM Spec 2 4 21.pdf PDF
Amendment 0002 Attachment 3_ Flag Policy.pdf PDF
Amendment 0002 Fire Inspection Reports.pdf PDF
Amendment 0002 Site Visit Sign-In Sheets.pdf PDF
Amendment 0002 Preproposal Meeting Roster .pdf PDF
Amendment 0002 Preproposal Conference Slides.pdf PDF
Amendment 0002 47PH0221R0001 SF30.pdf PDF
Corpus Christi Victoria OM FM Spec 1 20 21 Amendment 0001.pdf PDF
47PH0221R0001 Amendment 0001.pdf PDF
Figure B-3 Pricing of Services Amendment 0001.xlsx XLSX spreadsheet
47PH0221R0001 Corpus Christi Victoria OM_FM Spec 1 13 21.pdf PDF
Figure L-1 Management Plan Worksheet.xlsx XLSX spreadsheet
Exhibit M2 - Green Purchasing Report.pdf PDF
Attachment 2 - Service Contract Act (SCA) Wage Determination.pdf PDF
Figure L-2 Past Performance Questionnaire.pdf PDF
Figure B-3 Pricing of Services_.xlsx XLSX spreadsheet
Exhibit M9 - 2018 GSA PM Guide FINAL.pdf PDF
Exhibit C5 - Erosion and Sediment Control.pdf PDF
BL6_ Work Order History.xlsx XLSX spreadsheet
FIGURE B-2 SCA_DOL Combination Wage Adjustment Spreadsheet.xlsx XLSX spreadsheet
Exhibit M5 - Smart Buildings.pdf PDF
BL5_ Roof Information.pdf PDF
Exhibit M3 - Environmental Sustainable Products.pdf PDF
BL2_ Inventory to Include Fire Alarm Devices.xlsx XLSX spreadsheet
Figure B-1 Contractors Staffing Declaration.xlsx XLSX spreadsheet
Exhibit M8 - Misc Best Practices Shave Energy.pdf PDF
Attachment 1 - Collective Bargaining Agreement (CBA) with Wage Determination.pdf PDF
BL4_ Elevator Information.pdf PDF
Exhibit C7 - PBS Waste Audits.pdf PDF
Exhibit M7 - Qualificaiton of Electrical Testing Technicians.pdf PDF
Exhibit C1 Building Information Sheets.pdf PDF
Exhibit M6 Water Treatment.pdf PDF
Exhibit C6 - Recycle Solid Water Trash Report.pdf PDF
BL7 Energy___Water_Monthly_Report_template.docx DOCX document
BL3_ Building Location Info.pdf PDF
Exhibit C4 - Building Exterior and Hardscape Plan.pdf PDF
Exhibit C8 - GSA Form 3638 Pest Control Work and Inspection Report.pdf PDF
Exhibit M4 - Bldg Op Plan Template.pdf PDF
BL1_ Extinguisher Report.pdf PDF
Exhibit C2 and M1 Quality Assurance Surveillance Plan.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit M10

Item

PV Service Description

Frequency/ Response

Time

Visual inspection of Solar Facility’s general site conditions, PV arrays, electrical equipment, mounting structure, fence, shading, trackers, vegetation, animal damage, erosion, corrosion, and discolored panels.

Every 6 months

Visual inspection and correction of Solar Facility for loose electrical connections and ground connections.

String-level open-circuit voltage, DC operating current tests, and I-V curve traces on 100% of all strings.

1x per year

4 All switches and disconnects tested to ensure they are not jammed.

Infrared scans on 100% combiner and re-combiner boxes; tighten connections to manufacturer's torque specification; report broken terminal blocks.

100% check calibration expiration on sensors and meters, including pyranometers, and anemometers and perform other service such as cleaning and replacement of any desiccant.

Turn off and on logging and communications to ensure they are communicating and ensure battery backups are working.

Inverter preventive maintenance for 100% of all inverters per manufacturer’s operating guidelines

See 9-12

9 Clean inverter cabinet air vents.

10 Clean and change inverter air filters, if present, per manufacturer’s warranty requirements.

11 Clean/remove dust from inverter heat sinks per manufacturer’s warranty requirements.

12 Check torque marks and re-tightening appropriate wiring connections to design specification torque force per manufacturer’s guidelines.

13 Inspect roof penetrations to ensure sealant is applied properly and not degrading.

14 PV array module maintenance for all modules See 15-16

Wash all panels with water with no chemicals in a method approved by the

Owner.

16 Perform infrared scan of 100% of modules for two types of circuitry connections: cells on the front and junction boxes on the back.