Exhibit K Contract Submittal Schedule.pdf

PDF 175 KB Posted

Attached to
Huntsville, Alabama Women's Health Clinic Lease
Solicitation number
36C24426R0054
Issued by

About this file

Contract Submittal Schedule Summary

This document is a Contract Submittal Schedule template for GSA Real Property Lease (RLP) procurement actions. It contains two separate schedules for tracking contractor submittals across lease solicitation and execution phases, identified by RLP and lease numbers (RLP NO. 36C24426R0054/LEASE NO. 36C24426L0008 and RLP NO. 36C24425R0095/LEASE NO. 36C24425L0016).

The first schedule covers the RLP submittal phase and requires 31 line items including GSA Forms 1364, 1217, and 12000; proof of ownership and flood plain documentation; space concept drawings and narratives addressing design, technical capability, parking, and emergency preparedness; zoning and SAM registration verification; subcontracting plans if applicable; energy compliance documentation including LEED-NC Silver certification; building security pricing; asbestos management plans; floor plans; and tenant improvement cost summaries. Each submittal row tracks the date received in contracting, date to civil engineer, return suspense date, submittal numbers, contractor notification date, contractor resubmittal status, final approval status (approved/disapproved), and remarks.

The second schedule addresses the lease submittal phase and requires 18 items including building occupancy permit, HVAC balance and water testing reports, executed GSA Form L100 lease document, firm commitment of funds, state licensing/certification, reused building material plans, green lease submittals, MSDS sheets, DIDs, tenant improvement price proposals, construction schedules, as-built drawings, color boards for finishes, meter verification documentation, periodic services schedules due within 60 days post-occupancy, interior signage requirements, and a commissioning plan prior to DID completion. This template provides the tracking framework for government project engineers to monitor contractor compliance with all required submittals throughout the lease lifecycle.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT K

CONTRACT SUBMITTAL SCHEDULE

PROJECT NUMBER

PROJECT TITLE

SOLICITATION/CONTRACT NUMBER

RLP NO. 36C24426R0054

LEASE NO. 36C24426L0008

TO BE COMPLETED BY PROJECT ENGINEER

LI

N

E N

U M

B

ER

DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

D A

TE

R

EC

EI

VE

IN

C O

N

TR

A C

TI

G

TE

T O

C

IV

IL

EN

IN

EE

R

ET

U R

N S

U

SP

SE

TE

SU

M

IT

TA

L

N U

M B

S

DATE CONTRACTOR

NOTIFIED

C O

N

TR

A C

TO

ES

U

B M

IT

TA

L

FI

A L

A

PP

R O

VA

REMARKS

APPROVED

DIS-APPROVED

RLP SUBMITTALS

1 GSA Form 1364, Proposal to Lease Space (Exhibit F)

2 GSA Form 1217, Lessor’s Annual Cost Statement (Exhibit G)

3 GSA Form 12000, Pre-lease Fire Protection and Life Safety Evaluation for an Office Building (Part A&B) (See Section 3 for applicable requirements) (Exhibit H)

4 Proof of ownership (Reference RLP Section 3.04)

5 Documentation evidencing proof that offered space/property/building is outside of the 100 Year Flood Plain (Reference RLP Section 2.02 & 3.02)

6 Evidence of at least Conditional Commitment of Funds (Reference RLP Section 3.02 & 3.04)

7 Space Concept Drawing/First Generation Plans (Reference RLP Sections 2.01, 3.02, 3.04 & 4.05)

8 Building Location Narrative (Reference RLP Section 3.02 & 4.05)

9 Design Concept Narrative (Reference RLP Section 4.05)

10 Technical Capability Narrative

11 Time required to Occupy Space Narrative (Reference RLP 4.05)

12 Parking Narrative (Reference RLP Section 3.03)

13 Site Plan (Reference RLP Section 3.04)

14 Legal Description of Property and tax ID number associated with the property (Reference RLP Section

15 Proof of Status/Preferences or Statement (Reference RLP Section 2.05, 3.02, and 3.04)

16 Representation Regarding Certain Telecommunication and Video Surveillance Services or Equipment (Exhibit U)

17 Proof of Signing authority (See RLP

18 SAM Active Registration (See RLP

19 Proper Zoning (See RLP Section

20 Subcontracting Plan (if applicable)

21 Program Management & Response Plan (Reference RLP Section 4.05)

22 Emergency Preparedness Plans

23 Past Performance References

24 Proposed Milestone Plan or Critical Path of Build Out Phase (Reference RLP Section 4.05)

25 Compliance with Energy Star Requirements (Reference RLP

26 LEED-NC Silver Scorecard & Statement Requirements (Reference RLP Section 3.04)

27 Any deviations from the Government’s Stated Requirement (Reference RLP Section 3.04)

28 Building Security Unit Price List (Exhibit I)

29 Asbestos Certification or Management Plan (Exhibit S)

30 Floor Plan(s) (Exhibit L)

31 Tenant Improvements Cost Summary (Exhibit U)

CONTRACT SUBMITTAL SCHEDULE

PROJECT NUMBER

PROJECT TITLE

SOLICITATION/CONTRACT NUMBER

RLP NO. 36C24425R0095

LEASE NO. 36C24425L0016

TO BE COMPLETED BY PROJECT ENGINEER

LI

E N

U M

DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

TE

R

EC

EI

VE

IN

C

O N

TR

A

C

TI

TE

T O

C

IV

IL

IN

EE

ET

U R

N S

U

SP

SE

TE

SU

M

IT

TA

L

N U

M B

S

DATE CONTRACTOR

NOTIFIED

C O

N

TR

A C

TO

ES

U

B M

IT

TA

FI

A L

A

PP

R O

VA

REMARKS

APPROVED

DIS-APPROVED

LEASE SUBMITTALS

1 BUILDING OCCUPANCY PERMIT

2 HVAC BALANCE REPORT

3 WATER TESTING REPORT

4 EXECUTED LEASE DOCUMENT

(GSA FORM L100)

5 FIRM COMMITMENT OF FUNDS

SUFFICIENT TO PERFORM WORK

6 LICENSE OR CERTIFICATION TO

PRACTICE IN THE STATE

7 REUSED BUILDING MATERIAL

“REUSE PLAN”

8 GREEN LEASE SUBMITTALS

9 MSDS SHEETS

10 DIDS

11 TI PRICE PROPOSAL

12 CONSTRUCTION SCHEDULE

13 AS-BUILT DRAWINGS

14 COLOR BOARD FOR FINISHES

15 Section 1.03 a record of the meter numbers and verification that the meters measure Government usage only

16 Within 60 days after occupancy by the Government, the Lessor shall provide the LCO with a detailed written schedule of all periodic services and maintenance to be performed other than daily, weekly, or monthly.

17 Interior Signage Requirement

18 Commissioning Plan prior to completion of DIDs