Exhibit E

28 KB Posted

Attached to
East Campus Streetscapes
Solicitation number
BR-30-2205-DB
Issued by
Fulton County, Georgia

About this file

Construction Overhead Cost Breakdown – East Campus Streetscapes, Georgia Institute of Technology

This is a Construction Overhead Cost Breakdown exhibit (Exhibit E) for the Design-Build Services project "East Campus Streetscapes" at Georgia Institute of Technology in Atlanta, Georgia. The document is a detailed cost template requiring bidders to populate all applicable construction overhead expenses across multiple categories including Site Supervision & Management, Site Office Expense, Safety & Security, Bonds & Insurance, and Miscellaneous costs. The breakdown is structured by line item with columns for Quantity, Unit, Labor, Materials, and Subcontractor costs, with explicit instructions that any attempts to recategorize items as "Fee," "Cost of Work," or "By Others" will result in a non-responsive proposal determination. All cost fields in the provided template are currently populated with $0 values, indicating this is a blank form awaiting bidder completion.

The document references a projected fee of $1,231,000 based on a $46 million Guaranteed Maximum Price (GMP), establishing the financial framework for the project. The template emphasizes strict categorization requirements for overhead costs, with various line items marked as "Included" in other categories, "By Architect," or "Not Applicable" to prevent cost duplication or misallocation. The construction overhead cost breakdown serves as a critical component of the overall bid package, requiring complete and accurate cost accounting from design-build contractors submitting proposals for this Georgia Tech campus improvement project.

Text of this file

Attach. B - Const. OH Cost)

EXHIBIT E
Fill-in all applicable costs, any attempts to recategorize any of these items as "Fee", "Cost of Work", or "By Others" will be treated as a non-responsive proposal.
CONSTRUCTION OVERHEAD COST BREAKDOWN
DescriptionQtyUnitLabor*Mat'l**SubLabor SubtotalMat'l SubtotalSub SubtotalTotalNotesQtyUnitLabor*Mat'l**SubLabor SubtotalMat'l SubtotalSub SubtotalTotalNotes
Site Supervision & Management:
1Senior Project Mgr.mos$0$0$0$0$0$00$0
2Project Mgr.mos$0$0$0$0$0$00$0
3Project Supt.mos$0$0$0$0$0$00$0
4Asst. Project Supt.mos$0$0$0$0$0$00$0
5Area Supt.mos$0$0$0$0NA
6Secretarymos$0$0$0$0$0$00$0
7Project Engineermos$0$0$0$0$0$00$0
8Engineer or Eng. Companymos$0$0$0$0$0$00$0
9Cost Controlmos$0$0$0$0$0$00$0
10Safety Engineermos$0$0$0$0$0$0
11Schedulingmos$0$0$0$0$0$0
12Purchasingmos$0$0$0$00$30,000
13Project Accountantmos$0$0$0$0$0$00$0
140$0
15Incl.
Subtotal$0$0$00$0
$30,000
Site Office Expense:
18Job Office Trailer Rentmos$0$0$0$0
19Office Jobsite Build Outls$0$0$0$0NA
20Office Jobsite Set-upls$0$0$0$0$0$00$0
21Temp. Const. Trailer/Storageea$0$0$0$0$0$00$0
22Office Furniturels$0$0$0$0NA
23Office Machines/Equip.mos$0$0$0$0Incl. Below
24Copy Machines/Maintenancemos$0$0$0$0$0$00$0
25Office Suppliesmos$0$0$0$0Incl. Above
26Janitor/San. Suppliesmos$0$0$0$0$0$00$0
27Postage & Shippingmos$0$0$0$0$0$0
28First Aid/Med. Treat.mos$0$0$0$0$0$00$0
29Telephone Systemls$0$0$0$0$0$0
30Phone Installationls$0$0$0$0$0$00$0
31Phone Chargesmos$0$0$0$00$0
32Phone Charges-Long Dist.mos$0$0$0$00$0
33Radio Communicationsea$0$0$0$0By Arch.
34Radio Maintenancels$0$0$0$0$0$00$0
35Computer-PCSmos$0$0$0$0Incl.
36Computersmos$0$0$0$0$0$00$0
37Softwareallow$0$0$0$0Incl.
38MIS Chargesmos$0$0$0$0
39Temp. Electric-Officemos$0$0$0$0
40Security-Officemos$0$0$0$0$0$00$0
41Water - Field Officemos$0$0$0$0
42
430$0
Subtotal$0
$0
Safety & Security:
43Safety Incentivesls$0$0$0$0
44Watchman/Guard Ser.ls$0$0$0$0NA
45Traffic Controlls$0$0$0$00$0
46Safety Equipmentls$0$0$0$0$0$00$0
47Rainwear/Hardhats, etc.ls$0$0$0$0$0$00$0
48Drug Testingea$0$0$0$00$0
49$0$0$0$0$0$00$0
50$0$0$0$00$0
Subtotal$0
$0
Bonds & Insurance:
51Perform. & Payment Bondsmos$0$0$0$00$0
52Workers Comp. Insurancemos$0$0$0$0Incl.
53Liability Insurancemos$0$0$0$0$0$00$0
54Fed. & State Unemploymentmos$0$0$0$0$00$0
55FICAmos$0$0$0$0
56Builders Risk Insurancemos$0$0$0$00$0
57
58
Subtotal$0
$0
Miscellaneous
59Off-Site Parkingmos$0$0$0$0
60Ceremony Expensels$0$0$0$0
61Vehicle for On-Site Project Managermos$0$0$0$0
62Vehicle for On-Site Superintendentmos$0$0$0$0
63Vehicle Repairs/Maintenancels$0$0$0$00$0
64Water - Coolersmos$0$0$0$0Incl.
65Water Barrelsmos$0$0$0$0$0$00$0
66Ice Machinemos$0$0$0$0NA
67Ice and/or Cupsls$0$0$0$0NA
68Temporary Toilets Installea$0$0$0$0NA
69Temporary Toiletsmos$0$0$0$0$00$0
70Cold Weather Protectionls$0$0$0$0Incl.
71Temp. Heat for Bldg.ls$0$0$0$0$00$0
72Job Signsea$0$0$0$0Incl.
73Progress Photosea$0$0$0$00$0
74Extra Plans & Specs.ea$0$0$0$00$0
75Blueprint/Photostat.allow$0$0$0$0Incl.
76Temp. Electric -Buildingmos$0$0$0$0$0$00$0
77Building Permitls$0$0$0$0Incl.
78Plan Check Feesls$0$0$0$0NA
79NA
80NA
Subtotal$0
TOTAL ALL CONSTRUCTION OVERHEAD COSTS:$0
108Projected Fee (Based on $46 Million GMP)
$1,231,000
109Grand Total GCs & Fee$0
ERROR:#REF!

&D &T &P

Sheet2

Sheet3

Other files

File Type Posted
Award Information —
Exhibit H —
Exhibit D —
Egnyte Upload Instructions —
Exhibit B —
GIT BR-30-2205 Addendum No. 1 —
GIT BR-30-2205 Addendum No. 2 —
Exhibit F —
GIT BR-30-2205 DB RFQ-RFP —
Exhibit A —
Exhibit C —
Exhibit I —
GIT BR-30-2205 Addendum No. 3 —
Exhibit G —
Show all 14

On GovTribe

Work with this file