Exhibit D _ Precon Cost and Expenses.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- GGC J-449-DB, Building B-Roof Replacement
- Solicitation number
- PE-47200-RFQ-2027-000000152
- Issued by
- Gwinnett County, Georgia
About this file
Exhibit D is a preconstruction costs and expenses breakdown template for the Design-Build Services project at Georgia Gwinnett College in Lawrenceville, Georgia. The document provides a standardized format for bidders to detail preconstruction costs organized into two primary categories: Preconstruction Supervision and Management, and Preconstruction Miscellaneous expenses. The supervision and management section includes line items for personnel such as Senior Project Manager, Project Manager, Preconstruction Manager, Project Superintendent, Cost Control, Scheduling, Secretary, and Consultant positions, all measured in months. The miscellaneous expenses section covers items including office supplies, postage and shipping, blueprint and photostat reproduction, phone charges (local and long distance), courier service, and travel expenses. The template is structured with columns for quantity, unit, labor costs, materials costs, subcontractor costs, and respective subtotals, allowing bidders to itemize their anticipated preconstruction expenditures.
The template currently displays all cost entries as zero dollars, indicating this is a blank form to be completed by bidders during the proposal submission process. The document includes notation fields for special conditions, such as "By Arch." for blueprint costs and "Incl." for long distance phone charges, allowing bidders to reference how certain costs may be addressed or included elsewhere. The total preconstruction costs and expenses line at the bottom of the form will aggregate all itemized costs once completed. This exhibit serves as a mandatory disclosure document for the Design-Build project, requiring full transparency regarding all preconstruction management and administrative expenses that bidders anticipate incurring prior to the start of construction activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document | |
| Exhibit E _ General Conditions Breakdown.xlsx | XLSX spreadsheet | |
| _GGC J_449 DB RFQ_RFP.pdf | ||
| Egnyte Upload Instructions_6.pdf | ||
| Exhibit C _ DB Fee Proposal.docx | DOCX document | |
| Exhibit F _ Project Cost Matrix.xlsx | XLSX spreadsheet | |
| Exhibit A _ Certification Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attach. A - Precon Cost & Exp.
EXHIBIT D
| PRECONSTRUCTION COSTS AND EXPENSES BREAKDOWN | Beers | ||||||||||||||||||||
| Description | Qty | Unit | Labor* | Mat'l** | Sub | Labor Subtotal | Mat'l Subtotal | Sub Subtotal | Total | Notes | Qty | Unit | Labor* | Mat'l** | Sub | Labor Subtotal | Mat'l Subtotal | Sub Subtotal | Total | Notes | |
| A. | Preconstruction - Supervision & Management: | ||||||||||||||||||||
| 1 | Senior Project Mgr. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 2 | Project Mgr. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 3 | Preconstruction Manager | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 4 | Project Supt. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 5 | Cost Control | mos | $0 | $0 | $0 | $0 | 0 | $30,000 | |||||||||||||
| 6 | Scheduling | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 7 | Secretary | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 8 | Consultant | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 9 | Other (Identify) | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| Subtotal | $0 |
| B. | Preconstruction - Miscellaneous | |||||||||
| 10 | Office Supplies | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 |
| 11 | Postage & Shipping | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 |
| 12 | Blueprint/Photostat. | ls | $0 | $0 | $0 | $0 | By Arch. | |||
| 13 | Phone Charges | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 |
| 14 | Phone Charges-Long Dist. | mos | $0 | $0 | $0 | $0 | Incl. | |||
| 15 | Courier Service | mos | $0 | $0 | $0 | $0 | ||||
| 16 | Travel Expenses | mos | $0 | $0 | $0 | $0 | ||||
| 17 | Other (Identify) | mos | $0 | $0 | $0 | $0 | ||||
| Subtotal | $0 |
TOTAL ALL PRECONSTRUCTION COST AND EXPENSES $0