About this file

This is a Design Builder Fee Proposal form for Project No. J-449 at Georgia Gwinnett College in Lawrenceville, Georgia. The document outlines the compensation structure for the design-builder selected to provide design-build services for the Building B-Roof Replacement project. The fee proposal consists of three primary components: a Design Consultants Fee for basic design services and construction administration, a Preconstruction Fee representing gross profit for pre-construction consulting services, and a Construction Fee representing gross profit for construction services. Each fee category is designated as a fixed fee amount to be specified by the bidder.

The proposal requires bidders to identify maximum overhead costs and expenses, separated into two categories: Pre-Construction Costs and Expenses (excluding the pre-construction fee) and Construction Overhead Costs (excluding the construction fee). The document includes designated line items for both the Design Consultants Fee, Preconstruction Fee, and Construction Fee, along with supporting attachments (Attachment A and Attachment B) that detail the overhead cost breakdowns. Bidders must complete the form with specific dollar amounts for each fee category and provide the total maximum overhead cost, along with signature authorization from the design-builder firm's officer.

View the file

Other files

File Type Posted
Exhibit B _ Contractor Affidavit.docx DOCX document
Exhibit G _ Proposer_s Disclosure Statement.doc DOC document
Exhibit E _ General Conditions Breakdown.xlsx XLSX spreadsheet
Egnyte Upload Instructions_6.pdf PDF
Exhibit D _ Precon Cost and Expenses.xlsx XLSX spreadsheet
_GGC J_449 DB RFQ_RFP.pdf PDF
Exhibit F _ Project Cost Matrix.xlsx XLSX spreadsheet
Exhibit A _ Certification Form.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15 of Exhibit C Project No. J-449 Georgia Gwinnett College, Lawrenceville, Georgia

DESIGN BUILDER (DB) FEE PROPOSAL

1. DB’S FEE:

Basis of Fee. The DB’s fee is the amount, established by and agreed to by both parties, which is the full amount of compensation due to the DB as gross profit, and for any and all expenses of the Project not included and identified as a Cost of the Work, provided that the DB performs all the requirements of the Contract Documents within the time limits established. (See Article 4.1.1 of the General Requirements.) If applicable, the fees and costs should be broken down by each site within a multi-site project.

A. DESIGN CONSULTANTS FEE:

Design Consultants Fee. Representing the fee amount for basic design services and construction administration services provided by DB. Owner shall pay to DB a Design Consultants Fee:

TOTAL

Design Fee (fixed fee)

B. PRECONSTRUCTION FEE:

Pre-Construction Fee. Representing the gross profit for the pre-construction consulting services provided by DB as set forth in Section 2, Parts 1 and 2 of the General Requirements, and as described in Paragraph 4.1.1.1(a), Owner shall pay to DB a Preconstruction Fee:

TOTAL

Pre-Construction Fee (fixed fee)

C. CONSTRUCTION FEE:

Construction Fee. Representing the gross profit for the construction services provided by DB as set forth in Section 3, Part 1 of the General Requirements, and as described in Paragraph 4.1.1.1(b) Owner shall pay to DB a Construction Fee.

TOTAL

Construction Fee (fixed fee)

2. DB’S PRECONSTRUCTION & CONSTRUCTION OVERHEAD COSTS and EXPENSES:

The DB’s Overhead Costs. The maximum amount for the DB’s Pre-Construction Costs and Expenses and Construction Overhead Costs are inclusive of all direct and incidental expenses are as described in Paragraph 4.1.1.2 .

AMOUNT

A. Maximum Pre-construction Costs & Expenses (From Attachment A. Do not include the Pre-Construction Fee in this amount)

B. Maximum Construction Overhead Costs (From Attachment B. Do not include the Construction Fee in this amount)

Total Maximum Overhead Cost (Sum of A & B)

DB Firm Name

By:__________________________________________________________ Signature of DB Officer