Exhibit C _ DB Fee Proposal.docx
DOCX document 25 KB Posted
- Attached to
- GCSU J-461-DB Arts & Sciences Renovation
- Solicitation number
- PE-47200-RFQ-2026-000000115
- Issued by
- Barrow County, Georgia
About this file
This is a Design Builder (DB) Fee Proposal document for Project No. J-461, Arts and Sciences Renovation at Georgia College and State University in Milledgeville, Georgia. The proposal establishes the fee structure and compensation framework for the design-build services contract, which encompasses design consultants' services, pre-construction consulting services, and construction services. The document outlines the contractual compensation structure that will be paid to the selected design builder upon satisfactory completion of all contract requirements within established time limits.
The compensation structure consists of three fixed-fee components: a Design Consultants Fee for basic design services and construction administration; a Pre-Construction Fee representing gross profit for pre-construction consulting services; and a Construction Fee representing gross profit for construction services. Additionally, the design builder may be reimbursed for pre-construction costs and expenses and construction overhead costs, with maximum amounts specified in separate attachments. All fees and overhead costs are presented as fixed amounts to be established through the bidding process, with specific dollar values to be filled in by proposing firms. The proposal requires signature authorization from a DB officer and includes provisions for potential multi-site project breakdown if applicable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| GCSU J_461 Arts and Sciences Renovation DB RF.pdf | ||
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document | |
| Egnyte Upload Instructions.pdf | ||
| Exhibit D _ Precon Cost and Expenses.xlsx | XLSX spreadsheet | |
| Exhibit A _ Certification Form.docx | DOCX document | |
| Exhibit F _ Project Cost Matrix.xlsx | XLSX spreadsheet | |
| Exhibit E _ General Conditions Breakdown.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15 of Exhibit C
Project No. J-461, Arts and Sciences Renovation Georgia College and State University
DESIGN BUILDER (DB) FEE PROPOSAL
1. DB’S FEE:
Basis of Fee. The DB’s fee is the amount, established by and agreed to by both parties, which is the full amount of compensation due to the DB as gross profit, and for any and all expenses of the Project not included and identified as a Cost of the Work, provided that the DB performs all the requirements of the Contract Documents within the time limits established. (See Article 4.1.1 of the General Requirements.) If applicable, the fees and costs should be broken down by each site within a multi-site project.
A. DESIGN CONSULTANTS FEE:
Design Consultants Fee. Representing the fee amount for basic design services and construction administration services provided by DB. Owner shall pay to DB a Design Consultants Fee:
TOTAL
Design Fee (fixed fee)
B. PRECONSTRUCTION FEE:
Pre-Construction Fee. Representing the gross profit for the pre-construction consulting services provided by DB as set forth in Section 2, Parts 1 and 2 of the General Requirements, and as described in Paragraph 4.1.1.1(a), Owner shall pay to DB a Preconstruction Fee:
TOTAL
Pre-Construction Fee (fixed fee)
C. CONSTRUCTION FEE:
Construction Fee. Representing the gross profit for the construction services provided by DB as set forth in Section 3, Part 1 of the General Requirements, and as described in Paragraph 4.1.1.1(b) Owner shall pay to DB a Construction Fee.
TOTAL
Construction Fee (fixed fee)
2. DB’S PRECONSTRUCTION & CONSTRUCTION OVERHEAD COSTS and EXPENSES:
The DB’s Overhead Costs. The maximum amount for the DB’s Pre-Construction Costs and Expenses and Construction Overhead Costs are inclusive of all direct and incidental expenses are as described in Paragraph 4.1.1.2 .
AMOUNT
A. Maximum Pre-construction Costs & Expenses (From Attachment A. Do not include the Pre-Construction Fee in this amount)
B. Maximum Construction Overhead Costs (From Attachment B. Do not include the Construction Fee in this amount)
Total Maximum Overhead Cost (Sum of A & B)
DB Firm Name
By:__________________________________________________________ Signature of DB Officer
Title of DB Officer