The document is a Draft Past Performance Questionnaire for the All Domain Common Platform (ADCP) Security Cloud Engineering Network Development (ASCEND) solicitation, issued by the Air Force Life Cycle Management Center/Kessel Run at Hanscom AFB, Massachusetts. The questionnaire is designed to collect detailed performance evaluation information from previous government/client contractors, covering multiple assessment areas including quality, schedule/timeliness, customer satisfaction, management/personnel, cost/financial management, safety/security, and overall contractor performance. The form provides a comprehensive rating system ranging from Exceptional to Unsatisfactory across various performance dimensions, allowing past clients to provide nuanced feedback on a contractor's capabilities, compliance, and effectiveness in executing government contracts.
The questionnaire includes sections for capturing specific contract details such as contract number, period of performance, role of the offeror, contract type, and complexity of work. Evaluators are asked to rate the contractor's performance across categories like quality of deliverables, ability to meet technical standards, timeliness, resource utilization, customer satisfaction, management effectiveness, cost control, security compliance, and responsiveness to emergencies. The document is part of a draft Request for Information (RFI) process, with feedback requested by Wednesday, 30 April 2025 at 5 PM Eastern, using an online submission form. The draft RFP emphasizes that submissions are voluntary, will not guarantee future participation, and are intended to help the government refine its solicitation requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DRAFT Solicitation - FA873025RB007.pdf | ||
| Attachment 5 - Draft Transmittal Letter Draft.pdf | ||
| Attachment 2 - DRAFT Task Order 0001 PWS.pdf | ||
| Exhibit A - Draft CDRLs.pdf | ||
| DRAFT SECTION M ASCEND.pdf | ||
| Attachment 3 - DRAFT Past Performance Information .pdf | ||
| Attachment 4 -Draft Client Authorization Letter.pdf | ||
| Attachment 7 - Cross Reference Matrix Sample.pdf | ||
| Attachment 1 - DRAFT ASCEND IDIQ PWS.pdf | ||
| Attachment 6 - Draft Consent Letter.pdf | ||
| DRAFT SECTION L ASCEND.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit B - Past Performance Questionnaire
Past Performance Questionnaire for
All Domain Common Platform (ADCP) Security Cloud Engineering Network Development (ASCEND)
Air Force Life Cycle Management Center/Kessel Run
(AFLCMC/C3C)
11 Barksdale Street
Building 1614 Hanscom AFB, MA 01731-1700
OFFEROR INFORMATION
Company Name Street Address
Point of Contact
(POC)
City
POC Phone Number State
CAGE Code
Zip Code
Contract Period of Performance (start to finish)
Description of Work
Role of Offeror on this project/program
�Prime �Sub �Other
Percentage of work performed if other than prime
CONTRACT INFORMATION
Contract Number Delivery/Task Order Number (if applicable) Contract Type (FFP, Cost, Other (please explain)
Award Date Contract Completion Date Original Contract Award Amount Final Contract Price Explain Difference Complexity of Work �High
�Medium �Routine
How is this project/program relevant to this acquisition?
See Relevancy table
INSTRUCTIONS TO PAST PERFORMANCE REFERENCE CONTACT:
The offeror named above is submitting a proposal for a Department of the Air Force (DAF) contract and has sent this form to you as a past performance reference contact. PLEASE complete the following pages in full. Once completed, PLEASE send the form directly to the Government contact provided below. If you have any questions regarding this request, PLEASE contact BOTH Government contacts provided below:
Name: Michelle Landry Title: Procurement Contracting Officer Email: michelle.landry@us.af.mil
Name: Rosa Krauss Title: Contract Specialist Email: rosa.krauss.3@us.af.mil
Please return the completed form as soon as possible, but no later than 1700 on XX XX 2025.
GOVERNMENT AGENCY/CLIENT INFORMATION
Government Agency/Client Point of Contact (POC) Title Phone Number Email
ADJECTIVAL RATINGS & DEFINITIONS
Rating Definition Notes
Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
Very Good Performance meets contractual requirements and exceeds some to the
A Very Good rating is appropriate when the mailto:michelle.landry@us.af.mil
Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
Not Applicable No information or did not apply to your contract.
Rating will be neither positive nor negative.
TO BE COMPLETED BY THE GOVERNMENT AGENCY/CLIENT
PLEASE CHECK THE ADJECTIVAL RATING WHICH BEST REFLECTS YOUR
EVALUATION OF THE CONTRACTOR’S PERFORMANCE
QUALITY:
Quality of deliverables/technical data/report preparation efforts
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory �Marginal
Ability to meet quality standards specified for technical performance
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory �Marginal
Timeliness/effectiveness of identified quality issue resolution
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory �Marginal
Adequate/effectiveness of quality control program
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory �Marginal
SCHEDULE/TIMELINESS OF PERFORMANCE:
Compliance with contract delivery/completion schedules including any significant intermediate milestones
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory �Marginal
Rate the contractor’s use of available resources to accomplish tasks identified in the contract
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory
CUSTOMER SATISFACTION:
To what extent were the end users satisfied with the project/program?
�Satisfactory �Marginal �Unsatisfactory
Overall customer satisfaction
�Satisfactory �Marginal �Unsatisfactory �Marginal
MANAGEMENT/PERSONNEL/LABOR:
Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
�Satisfactory �Marginal �Unsatisfactory �Marginal
Ability to hire, apply, and retain a qualified workforce to this effort
�Satisfactory �Marginal �Unsatisfactory
Government property control
�Satisfactory �Marginal �Unsatisfactory �Marginal
Knowledge/expertise demonstrated by contractor personnel
�Satisfactory �Marginal �Unsatisfactory �Marginal
Utilization of Small Business concerns.
Consider if the offeror complied with FAR 52.219-8, Utilization of Small Business Concerns and FAR 52.219-9, Small Business
�Exceptional �Very Good �Satisfactory
�Unsatisfactory
Subcontracting Plan (when applicable). Please include information in the notes regarding compliance.
�Marginal
Ability to simultaneously manage multiple projects with multiple disciplines
�Satisfactory �Marginal �Unsatisfactory �Marginal
Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
�Satisfactory �Marginal �Unsatisfactory �Marginal
Effectiveness of overall management (including ability to effectively lead, manage and control the program)
�Satisfactory �Marginal �Unsatisfactory �Marginal
COST/FINANCIAL MANAGEMENT:
Ability to meet the terms and conditions within the contractually agreed price(s)?
�Satisfactory �Marginal �Unsatisfactory �Marginal
Contractor proposed innovative alternative methods/processes that reduced cost, improved performance or other factors that benefited the client
�Satisfactory �Marginal �Unsatisfactory �Marginal
If this is/was a Government cost type contract, please rate the contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or over runs)
�Exceptional �Very Good �Satisfactory �Marginal �Unsatisfactory �Marginal
If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are
�Yes �No there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
SAFETY/SECURITY:
Contractor complied with all security requirements for the project and personnel security requirements.
�Satisfactory �Marginal �Unsatisfactory �Marginal
GENERAL:
Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
�Satisfactory �Marginal �Unsatisfactory
Compliance with contractual terms/provisions
�Satisfactory �Marginal �Unsatisfactory
Would you hire or work with this firm again?
�Yes �No
In summary, provide an overall rating for the work performed by this contractor.
�Satisfactory �Marginal �Unsatisfactory
ADDITIONAL COMMENTS:
File details come from the government source that posted it. Updated .