This is a Past and Present Performance Questionnaire (Exhibit B) used for evaluating contractors bidding on a Department of Veterans Affairs contract for Building 55 Accessibility Ramp project (Project No. 667-24-255, Contract 36C25625R0002). The form serves as a reference evaluation tool where contractors provide their company information and project details to reference contacts, who then complete performance ratings and submit them directly to the VA contracting office.
The questionnaire requires reference contacts to rate contractor performance on 24 specific criteria using a 6-point scale ranging from unsatisfactory to exceptional, covering areas such as management capabilities, quality control, schedule adherence, problem-solving, subcontractor payments, and overall performance. Reference contacts must also indicate whether the contractor received cure or show cause notices, if they would award another contract to the contractor, and if the contractor is rated in CPARS (Contractor Performance Assessment Reporting System). Completed forms must be submitted to Tammy Tynes at the Gulf Coast Veterans Health Care System contracting office in Biloxi, MS, no later than the proposal receipt deadline. The form is marked as source selection sensitive information and requires narrative explanations for any ratings of 1 or 2 in the remarks section.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25625R0125_1 08-06-2025.docx | DOCX document | |
| EXHIBIT A.docx | DOCX document | |
| EXHIBIT D.docx | DOCX document | |
| S02 Wage Determination 667-24-255 -01-03-2025.pdf | ||
| S02 SOW 10-03-2024.pdf | ||
| S02 B55 Ramp-Existing Drawing.pdf | ||
| EXHIBIT E.docx | DOCX document | |
| EXHIBIT C.docx | DOCX document | |
| S02 2016-03-21 Utilities Drawing.pdf | ||
| EXHIBIT F.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
Source Selection Sensitive Information—See FAR 2.101 & 3.104 Project No. 667-24-255 Bldg. 55 Accessibility Ramp 36C25625R0002
EXHIBIT B
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE
INSTRUCTIONS TO CONTRACTOR
Complete the CONTRACTOR INFORMATION section, below (type answers into light blue shaded boxes). Save the document. Send an electronic or hard copy print of the form to each of your reference contacts, asking them to please complete the form and submit it according to the instructions, below.
INSTRUCTIONS TO REFERENCE CONTACT
The contractor named below is submitting an offer for a United States Department of Veterans Affairs contract requirement, and has sent this form to you, in your role as a past performance reference contact. Please complete this form in full (all areas shaded in light yellow, below). Once completed, please send the form to the Contract Specialist via postal mail or email, directly to:
Department of Veterans Affairs NCO 16 Contracting Office Gulf Coast Veterans Health Care System ATTN: Tammy Tynes REF: 36C25625R0002 400 Veterans Avenue (NCO 16) Biloxi, MS 39531-2410 Email Address (preferred): Tammy.Tynes@va.gov
Please return the completed form no later than the time set for receipt of proposals. If you have any questions, please contact Tammy Saxon via email. Thank you for your assistance in this matter.
GENERAL INFORMATION [completed by Contractor]
Contractor Company Name
Street Address
Contractor Point of Contact Name
City
Point of Contact Phone Number
State
Reference Project Title
Zip Code
Contract Period of Performance (start to finish):
Contract Number
Contract Dollar Value
Description of Work
Role of Contractor on This Project (check appropriate box) ☐ Prime Contractor ☐ Sub-contractor ☐ Key Personnel
RESPONDENT INFORMATION [completed by Reference Contact]
Company Name
Street Address
POC Name
City
Phone Number
State
Fax Number
Zip Code
PERFORMANCE INFORMATION: Choose the number on the scale of 1 to 6 that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF 1 OR 2 in the Remarks section, below (text box will expand to whatever extent is necessary).
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| UNSATISFACTORY |
| MARGINAL |
| SATISFACTORY |
| VERY GOOD |
| EXCEPTIONAL |
| NEUTRAL |
| Performance did not meet most contractual requirements. There were serious problems and the contractor’s corrective actions were ineffective. |
| Performance did not meet some contractual requirements. There were problems, some of a serious nature, for which corrective action was only marginally effective. |
| Performance met contractual requirements. There were some minor problems and corrective actions taken by the contractor were satisfactory. |
| Performance met all contract requirements and exceeded some to the government’s benefit. There were a few minor problems, which the contractor resolved in a timely, effective manner. |
| Performance met all contract requirements and exceeded many to the government’s benefit. Problems, if any, were negligible and were resolved in a timely, highly effective manner. |
| No record of past performance or the record is inconclusive.[endnoteRef:1] [1: ] |
| The Contractor … |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 1. |
| Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 2. | |||||
| Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 3. | |||||
| Delegated authority to project managers and supervisors commensurate with contract requirements. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 4. | |||||
| Home office participated in solving significant local problems. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 5. | |||||
| Followed approved quality control plan. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 6. | |||||
| Provided effective quality control and/or inspection procedures to meet contract requirements. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 7. | |||||
| Corrected deficiencies in timely manner and pursuant to their quality control procedures. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 8. | |||||
| Provided timely resolution of contract discrepancies |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 9. | |||||
| Identified problems as they occurred. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 10. | |||||
| Suggested alternative approaches to problems. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 11. | |||||
| Displayed initiative to solve problems. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 12. | |||||
| Developed realistic progress schedules. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 13. | |||||
| Met established project schedules. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 14. | |||||
| Provided timely resolution of warranty defects. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 15. | |||||
| Was responsive to contract changes. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 16. | |||||
| Provided adequate project supervision. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 17. | |||||
| Obtained consent of surety for increases in bonding as work-in-progress increased. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 18. | |||||
| Paid subcontractors/suppliers in a timely manner. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 19. | |||||
| Provided accurate and complete line item cost proposals including all aspects of work required for each task. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 20. | |||||
| Cooperated with Government personnel after award. | |||||
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 21. | |||||
| How would you rate the contractor's overall performance? | |||||
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 22. | |||||
| Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.” | |||||
| ☐ | YES | ||||
| ☐ | NO |
| 23 | |
| Would you award another contract to this contractor? If not, please explain in “remarks.” | |
| ☐ | YES |
| ☐ | NO |
| 24 | |
| To the best of your knowledge, is the contractor rated in CPARS? | |
| ☐ | YES |
| ☐ | NO |
REMARKS (Please use as much space as is needed – the box will expand as you type).