Exhibit_A3_E_Living_Unit_DRAFT_FOR_REVIEW.pdf

PDF 568 KB Posted

Attached to
RECS RFP Repair, Replace, and Upgrade Fire Suppres
Solicitation number
2000015536
Issued by
Stearns County, St. Cloud City, Minnesota

About this file

This document is a request for proposal (RFP) from RECS Project #78SC0086 for mechanical and electrical engineering services to repair, replace, and upgrade the existing fire suppression system at the MCF-St. Cloud facility in St. Cloud, Minnesota. The project involves full design services to bring the existing fire suppression system up to current code requirements. Proposals are requested from qualified firms to provide these services, with the RFP providing details on the scope of work, response requirements, and procurement process. The scope includes hydraulic calculations, shop drawing preparation, and coordination with authorities having jurisdiction. Proposals are due by a specified date, and the selected firm will be awarded a contract for the design services.

The RFP does not provide specific details on pricing, funding sources, set-asides, or incumbent firms. It indicates the project will be funded through state and local government sources, but does not include any additional financial information. The RFP is focused on soliciting qualified engineering firms to provide the required design services for the fire suppression system upgrade project at the MCF-St. Cloud facility.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 01

SUMMARY OF WORK AND SPECIAL REQUIREMENTS

Section 01 01 00 Page 1 of 5 E Living Unit Fire Suppression at MCF St Cloud EEA Proj. No. 6426 RECS Proj. No. 78SC0055

PART 1 - GENERAL

01.01 APPLICABLE DOCUMENTS

A. Bidding requirements, Conditions of the Contract and pertinent portions of sections in Division One of these specifications apply to the work of this section.

01.02 SUMMARY

A. In general, the Work under this Contract includes, but is not limited to providing fire sprinklers and standpipe hose connections, along with fire alarm system annunciation for the ‘E’ Hall Living Unit at MCF Saint Cloud. This will be an extension of existing systems in the building complex.

01.03 WORK BY OWNER OR SEPARATE CONTRACT

A. The Owner reserves the right to let other future separate contracts for the project, or perform work with his own forces. The Owner and their selected contractors are performing additional electrical work in the data center.

01.04 SITE MANAGEMENT

A. Contractor shall assume site management within seven days after Notice to Proceed and shall carry responsibility for all site management until final completion of his Contract. From the time the Contractor for this project commences work at the site until his Contract is completed, the Contractor is responsible for the care of the site and Project to the extent his work, acts, operations or use of the site affects the site and Project.

B. Site management and maintenance shall include, but not be limited to: providing and maintaining temporary facilities as specified; protection of adjacent structures, overall fire safety management, general security of the Project; and similar overall or general management of the site and adjacent other property to fulfill the obligations of this Contract.

C. Contractor shall confine his apparatus, materials, equipment, and operations of workers to the site and construction limits indicated on drawings or otherwise imposed by the Owner. The site and Project shall not be unreasonably encumbered with materials and equipment. Neat and orderly stockpiling and other operations shall be maintained and debris shall be regularly removed from the site.

D. All improvements on or about the site and adjacent property which are not shown to be altered, removed or otherwise changed shall be restored to the conditions which existed previous to starting work. All existing buildings, structures, or other features shall be protected from damage by any operation in connection with the Project. Contractor shall replace or repair, at his own expense (and to the satisfaction of the Owner), all damage to existing buildings, and other property resulting from work of his Contract, from whatever cause.

E. Contractor shall install and maintain temporary board or plank protection at all sides of openings in finished or exposed construction where materials may be moved, including (but not limited to) sills and jambs of door, window or similar openings through which material may be passed. Any damaged surfaces shall be removed and replaced as directed.

F. The existing buildings will be occupied by the Owner during construction. Except as required in the performance of contract work, Contractor's personnel shall not occupy, use, or otherwise enter existing buildings.

Section 01 01 00 Page 2 of 5 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

G. Contractor shall conduct his operations so as to permit access to existing buildings. Walks, driveways, entrances and hallways to be used by the Owner shall be maintained in a safe condition and shall be kept free and clear of the Contractor's equipment, materials and debris.

H. Contractor shall cooperate with the Owner in the scheduling and execution of the work and use of the site, and he shall notify the Owner as far as possible in advance of the commencement of any work or operation which would interfere with the use of the existing buildings.

01.05 CHARACTER OF WORK, MATERIALS AND INSTALLATION

A. The Work shall conform in all respects with requirements of all Contract Documents, and workmanship shall be first quality, the best obtainable at the present state of the crafts. Incompetent or careless workmanship shall not be permitted by the Contractor and will not be accepted by the Owner.

B. If, in opinion of the Contractor (or any Subcontractor) any Work is indicated on drawings or specified in such manner as to make it impossible to produce Work of highest quality, within space shown, or which may be considered improper for use and conditions, including the effects of expansion and Contraction, or should discrepancies appear between drawings, or drawings and specifications, the Contractor shall refer same to the Engineer before proceeding. If the Contractor does not request such interpretation, no excuse will be entertained thereafter for failure to carry out and guarantee the Work in a satisfactory manner. Elements of the Work intended to protect against weather shall be guaranteed weather and water tight.

C. Proper performance of the Contract shall imply, among other things, correct and proper placement, proper or published results for products and equipment, fitting and operation of fixed or movable and operating parts of the Work, including all systems and equipment. All materials and equipment shall be complete in every respect, with all parts, connections, anchors, devices, backing, fittings and other necessary items, and shall be completely installed, anchored, fitted and placed in operating condition.

Before buying, constructing or installing work, the Contractor shall notify the Engineer of any conditions which may exist in the Contract Documents which may affect proper operation or first quality installation.

01.06 CUTTING, REMOVAL AND PATCHING

A. This article covers cutting, patching and restoration of existing work as necessary to accomplish and complete all work under the Contract, including relocation or reuse of existing materials, equipment, systems or other work, as well as the disposal of salvaged materials or debris.

B. Each trade shall perform all cutting and patching necessary in order to perform his work. However, special permission shall be obtained from the Engineer before cutting structural members or finished material. All patching shall be performed in such manner as to leave no visible trace and to return the part affected to the condition of undisturbed work. Patching work shall be performed by men experienced, skilled and licensed for the particular type of work involved. Inferior work will not be accepted. All holes in masonry shall be drilled with rotary drills. Impact tools shall not be used.

C. Fencing, pavements, sidewalks, roads and curbs shall be cut, patched, repaired or replaced as required to permit the installation of the work of each trade. Such cutting, patching, repairing and replacing shall be the responsibility of and paid for by the trade requiring the work.

D. Each trade shall bear the expense of all cutting, patching, repairing or replacing of the work of other trades required because of his fault, error or tardiness or because of any damage done by him.

Section 01 01 00 Page 3 of 5 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

E. Patch disturbed existing construction as indicated on the drawings, or as otherwise required to restore the work and surfaces. Where existing construction is removed, cut exposed or otherwise disturbed by Work of the Project, patch defective and incomplete surfaces.

F. Patching work shall be done by skilled mechanics experienced in the particular type of work involved.

Patching work shall conform to the standards of the Specifications where applicable, and where not specified, work shall conform to the highest standards of the trade.

G. Thoroughly clean and prepare all surfaces to receive new finish or covering. Completely remove dirt, dust, grease, oil, paint, loose materials and soil. Clean, etch where necessary, and place surfaces in most suitable condition for the finish, as approved by Engineer.

01.07 ANCHORAGE, SUPPORTS AND SLEEVING

A. The requirements of technical sections of the specifications or as shown on drawings, which are more specific or in excess of the general requirements herein, shall take precedence over these general requirements.

B. Contractor and his Subcontractors shall furnish and install proper anchorage devices to securely and in the best manner, fasten, hang, mount, anchor, support all work in a neat and substantial way.

Unless otherwise specified, Subcontractors shall furnish all devices for fastening their work together and for fastening to the structure.

C. Contractor and each Subcontractor shall furnish and install all their own sleeves, anchors, inserts and other devices as work progresses to accommodate their own materials or work. Methods and devices, as well as location, may be subject to the Engineer's approval and shall not impair, violate or alter structure, or aesthetic value of the Work.

D. In general, provide bolts and shields for anchorage to solid materials, toggle bolts into hollow construction or through bolts and washers where necessary, unless otherwise shown or specified.

Wood plugs into solid materials, toggle bolting to vertical lath and plaster, or bolting into shields at hollow units, will not be acceptable. Contractor shall provide adequate backing for all fastenings and supports to prevent pull-out, deflection or undue stresses. For concrete, anchorage devices shall generally be cast-in, not drilled in later, unless otherwise specified.

E. At concrete, shot or drilled-in anchor devices will be permitted where casting-in may be difficult to coordinate, provided they will not damage the concrete or cause any spalling around the anchor.

Drilled-in expansion anchors, which have the same hole size as the bolt size, such as "Kwik-bolt" or "Wej-it" will be permitted provided there is no spalling around the holes, the holes are neatly drilled and approved test reports indicate adequate shear and pullout strength with ample safety factor.

01.08 HOLES THROUGH MASONRY AND CONCRETE

A. Each trade shall provide all holes and openings required for his work unless such holes and openings are shown to be provided on the architectural or structural drawings. Pay particular attention to openings required in precast, pre-stressed or post-tensioned slabs.

B. Holes made in the field shall be core-drilled large enough to allow all pipe insulation to continue uninterrupted. Holes in floors or exterior walls above grade shall include a steel pipe sleeve grouted water-tight.

1. The above method shall be employed whenever holes are made on the job, including holes required by change orders or because of omissions made inadvertently by the trade.

Section 01 01 00 Page 4 of 5 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

C. Pipe openings in exterior walls below grade between earth areas and interior spaces shall include a steel pipe sleeve and a mechanical seal.

D. Each trade shall be responsible for providing and disposing of water he uses in the core drilling operation. Such work shall be scheduled and other trades coordinated so that damage will not result from the use of water.

1. Special attention shall be given to core drilling operations which occur in areas adjacent to or over finished spaces which could be damaged by water. Each trade shall provide collection pans or alternate method of water control.

E. Each trade shall be responsible for grouting air-tight any openings adjacent to his work to seal against the passage of air, smoke or vapors.

01.09 GENERAL PROTECTION

A. Contractor and all Subcontractors shall provide protection for all his own equipment, hoist, and other facilities, used in the prosecution of the work to prevent operation by unauthorized personnel.

01.10 SAFETY AND HEALTH

A. Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. All of the Work shall be performed in a safe manner.

B. Contractor shall comply with all applicable codes, laws, ordinances, rules, regulations and lawful orders of any public authority, having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss. They shall erect and maintain, as required by existing conditions and progress of the Work, all reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying users of adjacent spaces.

C. Contractor shall designate a responsible member of his organization at the site whose duty shall be the prevention of accidents and other safety or protection measures. This person shall be the Contractor's superintendent unless otherwise designated in writing by the Contractor to the Owner.

D. When the use or storage of hazardous materials or equipment is necessary for the execution of the

Work, the Contractor shall exercise the utmost care and shall carry on such activities under the supervision of properly qualified personnel.

E. Contractor shall provide and maintain adequate fire extinguishers or other firefighting systems or devices in and around the construction area, available to all workmen, but shall not use the Owner's extinguishers.

F. Contractor shall not load or permit any loading which will endanger the safety of or in any way damage the Project, the Work, or any existing or adjacent facilities.

01.11 HAZARDOUS MATERIALS

A. The services provided by the Engineer do not include responsibility for the discovery, presence, handling, removal or disposal of or exposure of persons to hazardous materials in any form at the project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB), lead paint, or other toxic substances.

B. The services provided by the Contractor do not include responsibility for the discovery, presence, handling, removal or disposal of or exposure of persons to hazardous materials in any form at the

Section 01 01 00 Page 5 of 5 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055 project site, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB) or other toxic substances.

C. The Owner has complete responsibility for injuries or damages arising out of the presence, removal, transportation and disposal of hazardous materials. Statutes of Federal and State and other regulatory bodies require an asbestos building survey prior to construction work where the Owner, an employer or Contractor has or should have reason to believe there are asbestos-containing materials present in the building or its environment where construction is to take place.

D. The Owner has indicated hazardous materials investigation and abatement services have been provided by others prior to the work of this Project.

E. If hazardous materials are encountered by the Contractor, work should stop immediately and the

Owner's representative should be contacted.

01.12 FIRE SAFETY PRECAUTIONS

A. Contractor shall exercise extreme care to maintain and exercise adequate fire safety precautions throughout the work. This shall include providing sufficient firefighting devices, watchmen, standby helpers or other precautions during construction, in use of temporary heat, welding, brazing, seating, testing or other phases of work.

B. All welding, brazing, cutting and sweating operations performed in vicinity of or accessible to combustible materials shall be adequately protected to make certain that sparks or hot slag does not reach the combustible material and start a fire.

01.13 PERIODIC CLEAN-UP

A. Refer to General Conditions and Section 01 70 00, “Project Close-out.” It is the intent the site and building areas be maintained in clean, neat and free of debris at all times.

B. Contractor shall be responsible for installed work, stored materials, tools, equipment, scaffolding, and they shall be kept clean and in good order and workmanlike condition. Contractor shall also be responsible for keeping the premises free at all times from accumulation of rubbish, waste and excess materials, unused tools and equipment, and the like connected with or caused by his operations, employees or Subcontractors. Contractor shall periodically remove and lawfully dispose of all such rubbish, etc., off the Owner's premises.

C. Contractor is responsible to keep clean and orderly areas where his is working, storing materials and equipment or using to gain access. In the event Contractors fail to maintain the building and site clean and free of debris, the Owner will have it done by others and assess the cost to the Contractor.

PART 2 - PRODUCTS

Not used.

PART 3 - EXECUTION

END OF SECTION

CHANGES TO THE WORK

Section 01 10 00 Page 1 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426

01.01 RELATED DOCUMENTS

A. The Drawings, the provisions of the Contract including the General and Supplementary

Conditions and the General Requirements apply to the work of this Section.

01.02 SUMMARY

A. This Section defines administrative procedures for executing changes to the work.

Not applicable.

03.01 PRODUCT SUBSTITUTION

A. Pre-Bid Acceptance of Alternate Manufacturer.

1. Submit requests for substitution to Engineer no later than 10 days prior to bid date.

Include complete information including manufacturer’s literature, references on similar projects, test data, samples if appropriate or requested, and a letter detailing how the proposed product differs from that specified.

2. Requests for substitution will be evaluated based on proven equivalent performance and/or appearance, availability, durability, cost of maintenance and service, and long-term value to the Owner. The Engineer’s judgment in these matters is final.

3. Approvals will be made for alternative manufacturers, not specific products, based upon the Engineer’s determination that manufacturer is capable of furnishing acceptable products. Final product evaluation will be made during the shop drawing review process.

4. Approvals of substitute manufacturers will be published by Addendum to the Contract

Documents.

B. Post-Bid Acceptance of Substitute Products.

1. Post-bid requests for substitution will normally only be reviewed if there is a demonstrated benefit to the Owner, either in cost, schedule or quality. Contractor’s failure to order materials in a timely fashion will not be sufficient cause for product substitution.

2. Submit requests for substitution as required for pre-bid submittals. Approval of substitute products will be made by Supplemental Agreement, if a change in contract sum or time is involved, or by Supplemental Instruction if no such change is required.

Section 01 10 00 Page 2 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

3. If review of post-bid requests for substitution is lengthy or involved, Engineer may require payment of fees by Contractor for required architectural or engineering services. Such fees will be agreed to in writing prior to product review, and be charged at the same hourly rate specified in the Owner-Engineer Agreement.

C. Execution of Product Substitutions.

1. If a particular color or finish is specified, substitute product shall match exactly whether or not the specified color or finish is standard with the substitute manufacturer.

2. If a substitute product is accepted, Contractor shall coordinate and pay for any necessary changes in other related work required to incorporate the substitute product.

03.02 INTERPRETATION OF CONTRACT DOCUMENTS

A. Request for Information.

1. Questions related to interpretation of the Contract Documents or discovery of site conditions shall be addressed in writing by Request for Information (RFI) sent by email to the office of the Engineer.

2. The Engineer’s response will be written on the RFI form and returned to the Contractor by email. Clarifying drawings or sketches may be attached to the RFI

3. If the Contractor concludes that the Engineer’s response requires additional cost or time, he may submit a Request for Change Order within seven (7) days. Proceeding with the work constitutes the Contractor’s agreement that no change in cost or time is required.

B. Architect’s Supplemental Instruction.

1. If a clarification of or change to the Contract Documents is required, which in the

Engineer’s judgment does not involve a change in Contract Sum or Time, the Engineer will issue an Architect’s Supplemental Instruction (A.S.I.) on AIA Form G710.

2. If the Contractor concludes that the A.S.I. requires additional cost or time, he may submit a Request for Change Order within seven (7) days. Proceeding with the work shall constitute Contractor’s agreement that no change in cost or time is required.

03.03 CHANGES IN PROJECT SCOPE

A. Proposal Request.

1. If a change to the Contract Documents is required which involves a change in the scope of the project, the Engineer will issue a Proposal Request (PR) on AIA Form G709.

2. In response to the PR, the Contractor shall submit a Request for Change Order indicating

Contractor’s proposal for changes in the Contract Sum or Time. Include an itemized breakdown of labor, materials, overhead and profit, including work by subcontractors or suppliers.

3. If the Contractor’s proposal is acceptable to the Owner, Engineer will prepare a State of

Minnesota Developing Encumbrance. Do not proceed with the work until approved Developing Encumbrance has been executed by the Owner and forwarded to the Contractor.

Section 01 10 00 Page 3 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

4. The Engineer will prepare a State of Minnesota supplemental agreement, Admin Form 908, based upon a developing Encumbrance. Upon receipt of a signed Supplemental Agreement, the Contractor may include the cost of the work in his monthly Application for Payment.

PROJECT COORDINATION AND SCHEDULING

Section 01 20 00 Page 1 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426

A. Bidding requirements, Conditions of the Contract and pertinent portions of sections in Division One of these specifications apply to the work of this section.

01.02 SUMMARY

A. This Section defines procedures for:

1. Project Meetings.

2. Project Scheduling.

3. Project Phasing.

PART 2 PRODUCTS

03.01 PROJECT MEETINGS

A. Pre-Construction Meeting.

1. Scheduled: By Owner or Engineer upon award of Contract.

2. Location: To be determined.

3. Attendance: Owner’s Project Manager, Owner’s Site Representative, Engineer, Contractor, and other major subcontractors and suppliers.

4. Agenda.

a. Pre-Construction submittals.

b. Critical work sequencing.

c. Project coordination.

d. Administrative procedures.

e. Use of site.

f. Temporary facilities.

g. Housekeeping.

h. Safety and security.

i. Contract payments.

j. Project close-out.

5. Minutes: By Engineer, distributed by Contractor to Contractor’s personnel and subcontractors.

Section 01 20 00 Page 2 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

B. Construction Progress Meetings.

1. Frequency: Mutually scheduled, weekly, or more frequently if job progress and needs warrant.

2. Location: To be determined.

3. Attendance: Same as Pre-Construction Conference.

4. Agenda.

a. Previous minutes.

b. Work progress.

c. Schedule.

d Field observations, problems, conflicts.

e. Submittals.

f. Coordination of work.

g. Changes to the work.

h. Safety and security.

5. Minutes: By Engineer, distributed by Contractor to Contractor’s personnel and subcontractors.

C. Construction Coordination Meetings.

1. Schedule by Contractor, at least weekly.

2. Location: Contractor’s field office.

3. Attendance: Contractor, subcontractors, material suppliers.

4. Agenda: Project coordination.

5. Minutes: by Contractor.

03.02 PROJECT SCHEDULING

A. Start submittals and materials acquisition immediately upon Notification to Proceed, and achieve

Substantial Completion no later than the date listed on the bid form.

B. Within ten (10) working days of receipt of Notice to Proceed, submit a detailed schedule as specified in Section 01 30 00. Schedule shall show dates of all planned power outages and system shutdowns.

C. Keep Engineer and Owner fully informed about progress of the work, performance of the work, and potential problems.

D. The existing building will remain occupied and in operation throughout the remodeling work.

1. Coordinate on-site activities with the Owner’s Representative. Provide specified notice of service shutdowns, or other interference with Owner’s activities.

2. Coordinate all construction activities to ensure timely completion of the project, maintain safety and security, and to minimize disruption to the Owner’s use of the premises.

Section 01 20 00 Page 3 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426

3. Coordinate all building service outages with the Owner at least two (2) weeks in advance.

03.03 PROJECT COORDINATION

A. For all work requiring an outage to any building services, the Contractor shall plan work effort and review and get consent from building Owner prior to commencement of the work.

B. Contractor is responsible for the means and methods of providing all work in these drawings and specifications; however, due to critical nature of systems in this project, the Owner must be made aware of all work being done and its possible effects on building systems and may require backup procedure in the event of unexpected outages.

SUBMITTALS

Section 01 30 00 Page 1 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426

01.01 APPLICABLE DOCUMENTS

A. Bidding requirements, Conditions of the Contract and pertinent portions of sections in Division

One of these specifications apply to the work of this section.

01.02 SUMMARY

A. This Section defines procedure for the following pre-construction submittals required by the

Contract Drawings.

B. Refer to Section 01 70 00, "Project Closeout," for project close-out submittals.

PART 2 - REQUIRED SUBMITTALS

02.01 SHOP DRAWINGS, EQUIPMENT BROCHURES, AND PRODUCT DATA

A. Required submittals of shop, fabrication, or erection drawings, equipment brochures and product data, composite systems (including those by one or more Subcontractors or suppliers) and similar information shall be submitted in accord with this Article.

B. "Shop Drawings" shall mean all similar types of product data, including specially prepared drawings, standard prints, brochures and other descriptive data.

C. Contractor shall submit Shop Drawings to the Engineer with such promptness as to cause no delay in his work or the work of any Subcontractor on the Project. Adequate time shall be allowed for review by the Engineer.

D. Refer to General Conditions, Supplemental General Conditions, and Section 01 01 00 for coordination of work. Shop drawings shall be provided or exchanged as necessary or beneficial to the coordination effort.

E. Drawings submitted shall be marked with name of Project, Contractor, Engineer, whether

"preliminary" or "final" in nature, and shall bear stamp of approval of the Contractor, as evidence that drawings have been checked (including field dimensions) by the Contractor. The Contractor shall field verify or otherwise determine interferences or conflicts between various materials and resolve dimensions or methods resulting therefrom as approved by the Engineer. Any drawings submitted to the Engineer without the Contractor's approval and including evidence of field review and notations will not be considered reviewed and will be returned to the Contractor for prior review and re-submittal.

F. Prepared Shop Drawings shall be submitted in the form of clear, sharp, electronic PDF files acceptable to the Engineer. Shop drawings returned reviewed as "Noted" shall be printed by the Contractor in quantity required for his use. When shop drawings are returned "revise" and "resubmit", the Contractor shall correct the drawing and resubmit a new PDF file of the corrected original until final acceptance is obtained. The final Shop Drawings shall show field verified dimensions.

G. Checking and acceptance of Shop Drawings by the Engineer is for general conformance with design intent and Contract requirements and does not relieve the Contractor of responsibility to

Section 01 30 00 Page 2 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055 verify accuracy of dimensions, obtain field dimensions, coordinate dimensions with work of others and prevent interference with other equipment and other features of the work. If a drawing submitted is in accordance with Contract requirements, or specifically indicates deviation from Contract requirements which Engineer finds to be in interest of the Owner and to be so minor as not to involve a change in Contract price or time for performance, Engineer will accept drawings.

H. Acceptance of Shop Drawings and setting drawings will be general and, except as otherwise provided in preceding paragraph, shall not be construed as: (1) permitting any departure form Contract requirements, (2) relieving Contractor of responsibility from errors in details, dimensions or otherwise that may exist, (3) accepting departures from additional details or instructions previously furnished by Engineer, and (4) confirming clearances or lack of interference.

I. Review and acceptance by Engineer shall not relieve Contractor of responsibility for deviations from drawings and specifications unless such deviation is specifically called to Engineer's attention by a specific indication of "note deviation" or similar clear and bold indication at time of submission, nor shall it relieve him of responsibility for errors or omissions in Shop Drawings.

02.02 TEST REPORTS

A. Reports of tests required shall be submitted in duplicate to the Engineer. Submit one additional copy of reports of inspections, test and approvals of engineering items to the appropriate Engineering Consultant.

02.03 LIST OF MATERIALS

A. Within ten (10) days after the award of the Contract, the Contractor shall submit to the Engineer for acceptance, five (5) copies of a complete list of all materials, products and equipment proposed to be used in construction.

B. Where two or more manufacturer or models or items are named in the specifications (or additional names are called for in an addendum), the Contractor shall state which particular manufacturer or model of each item he proposed to provide. If the Contractor fails to state a preference, the Owner shall have the right to select any of the manufacturers or models named without change in price.

C. This list shall be submitted in the form prescribed by the Engineer and arranged in order of specification sections. The items listed shall fully conform to Project requirements and specifications. All materials are subject to the Engineer's acceptance. After acceptance there shall be no changes or substitutions. Each and all materials, products and equipment shall be specifically named on list "as specified".

02.04 LIST OF SUBCONTRACTORS

A. Within ten (10) calendar days after the award of the Contract, the Contractor shall submit 5 copies of a complete list of all Subcontractors (and major material suppliers) he proposed to use in performance of the Contract, to the Engineer for review and acceptance by the Engineer and Owner. The list shall be in the form prescribed by the Engineer. When appropriate, or when requested by the Engineer, the list shall include proposed Sub-subcontractors. No subcontracts shall be executed until the proposed listed subcontractors are accepted.

B. The proposed subcontractors or sub-subcontractors shall be established, reputable firms or recognized standing with a record of successful and satisfactory past performance with the type work and items proposed to be provided or installed by them. Only those subcontractors that the Owner approves will be used on the work.

Section 01 30 00 Page 3 of 3 E Living Unit Fire Suppression

C. The right to reject any Subcontractor or Sub-subcontractor is reserved by the Owner. The right to reject will be exercised by the Engineer or Owner as specified in the General Conditions.

02.05 CONSTRUCTION PROGRESS SCHEDULE

A. Within ten (10) days after the award of the contract or 3 days prior to the date of a pre-construction conference, the Contractor will submit to the Engineer an estimated progress schedule in bar graph format. The schedule shall denote a "Critical Path" of construction, showing pertinent dates for all sections of work described in this project manual and the drawings. The schedule will indicate the phase of construction where timely coordination of trades will be required or when major items will be started, completed and closed in. The schedule will leave spaces for individual subcontractors and suppliers to indicate their critical times. The construction progress schedule will be a minimum size of 11 x 17 and be located in the field office in a permanent, conspicuous space available to all trades. The schedule will be brought to all construction progress meetings and will be revised and reposted as construction continues and submitted along with each Application for Payment.

02.07 PROJECT CLOSE-OUT SUBMITTALS

A. Final approved copies of all submittals will be required in addition to the Owner's manual requirements of Section 01 70 00, "Project Closeout."

TEMPORARY FACILITIES

Section 01 50 00 Page 1 of 2 E Living Unit Fire Suppression

EEA Proj. No. 6426

01.01 TEMPORARY ENCLOSURES

A. Provide protective coverings and enclosures necessary to prevent damage to existing spaces and materials to remain.

B. Provide temporary support during demolition, cutting, remodeling and related new construction as necessary for the execution of the work and the protection of persons and property. Perform all work with appropriate supports, protection and methods to prevent collapse, settling or damage to property or persons. Provide adequate supports for the loads to be carried, with loads properly distributed, including to lower levels if necessary.

01.02 CONSTRUCTION LIGHT AND POWER

A. Existing Buildings. The Owner will operate and maintain the existing system during the project.

The Contractor may use electricity if measures are taken to avoid overloading or waste.

01.03 CONSTRUCTION WATER

A. Water for construction purposes may be obtained free of charge from the existing Campus distribution system. Coordinate connections with Campus representative.

Install temporary piping and a temporary hose bib as necessary. Remove temporary work when no longer required.

Take care that use of water will not damage existing building. All water shall be disposed of after use.

01.04 TELEPHONES

A. Contractor may not use the Facility’s phone or data network. Make provisions for separate service if needed.

B. Cellular phones or pagers are not permitted within the Facility.

01.05 SANITARY FACILITIES

A. With permission by the Owner, the Contractor may use selected building toilets during construction but must endeavor to keep them clean. Toilets shall be maintained in a clean and sanitary condition.

01.06 FIELD OFFICE AND TEMPORARY BUILDINGS

A. Contractor shall provide and maintain a field office. The field office shall be weather-tight, securely locked and adequately heated, ventilated and lighted. Provide secure, orderly storage for field office documents, such as plan specifications updated with addenda and change authorizations, complete set of approved shop drawings (installation, instructions, procedures, etc.), referenced standards and safety data. Coordinate field office location with Owner.

B. Temporary Buildings and Sheds. Each subcontractor shall provide and maintain such trailers, sheds and other temporary buildings on the site as he may require for the storage of his

TEMPORARY FACILITIES

Section 01 50 00 Page 2 of 2 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055 materials, tools and equipment, as directed by the Contractor and approved by the Owner. All temporary storage facilities must be kept securely locked.

C. Remove all temporary buildings when no longer required.

01.07 TEMPORARY SIGNS

A. Contractor shall provide and maintain temporary warning signs and other temporary signs required for the safe and proper execution of the work.

B. No billboards, advertisements or similar signs shall be erected on the site.

01.09 PARKING

A. Contractor parking is limited to spaces allowed by the Owner.

B. Keep vehicles locked at all times.

SECURITY PROCEDURES

Section 01 56 00 Page 1 of 1 E Living Unit Fire Suppression

EEA Proj. No. 6426

01.01 SECTION INCLUDES

A. Security requirements related to working at MCF St. Cloud

01.02 SECURITY PROGRAM

A. Coordinate the work with the Facility's established security program.

B. Notify subcontractors, suppliers, and other entities that visit the site of security requirements, and ensure compliance.

C. The facility reserves the right to modify or make changes to security procedures at any time.

01.03 SECURITY CLEARANCE

A. A criminal history check will be performed on all workers entering the Facility. The Contractor shall be responsible for performing this check prior to the worker working at the Facility. Include the cost of these checks in the project bid.

B. Upon completion of security clearance checks, the Contractor will provide this information to the

Facility. Identification badges will be required for this project.

C. Prior to start of work, the contractor shall furnish the Facility a complete list, including names of all workers. The list shall be subject to the approval of the Facility. The schedule and list of workers is to be updated on a bi-weekly basis.

01.04 GENERAL SECURITY PROCEDURES

A. No firearms, weapons, explosives, alcoholic, beverages, tobacco, or controlled substances are allowed on the grounds or within the Facility. Any workers who need to use tobacco must leave the Facility property.

01.05 SITE SECURITY PROCEDURES

A. Contractor parking is available in the designated parking, as identified on the Site Plan.

B. Construction trailers for field offices for the contractor may be located within the designated parking/staging area. They must be able to be secured when unattended.

C. Demolition dumpsters will be allowed in the construction area. Moving of dumpsters must be approved by staff prior to the move.

D. A representative of the contractor or vendor must accept any and all material deliveries at the work area. Facility staff will not accept any contractor or vendor deliveries.

E. Anyone entering the site will be required to wear a photo ID.

PROJECT CLOSE OUT

Section 01 70 00 Page 1 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426

01.01 GENERAL REQUIREMENTS

A. As applicable, the specified requirements shall apply to substantial completion as described in the

General Conditions, Supplemental Conditions and the General Requirements of Division 1. Where appropriate or possible, the specified requirements shall be accomplished at the date of substantial completion.

B. The Contractor's letter stating he has inspected the work and is ready for the Substantial Completion

Inspection and an attached list and status report of any incomplete items must be received by the Engineer at least seven (7) days prior to the requested Inspection date. After substantial completion, the Contractor shall continue to diligently complete all remaining work in an organized, efficient manner. In addition, the Contractor's letter of Request for Final Inspection shall certify each substantial completion punch list item conforms to the requirements of the Contract Documents.

C. Contractor shall reimburse the engineer for time and expenses to re-inspect uncompleted work.

D. As may be appropriate, the requirements of this section apply to, and shall be accomplished for, any individual area, floor, spaces or other parts of the total project the Owner may take over and assume beneficial occupancy or use.

03.01 REQUIREMENTS SPECIFIED ELSEWHERE

A. Change Orders. All Change Orders shall be resolved prior to final payment.

B. Guarantees & Warranties. Refer to General Conditions for the General Guarantee Requirements. In addition to the general guarantee, provide all written guarantees specified in the technical Sections of the specifications. Where the guarantee terms are included in the specifications a specific guarantee is referenced, submit guarantee in the specified form. The Contractor shall provide a check list of required guarantees, by specification Section numbers and submit guarantees prior to final payment.

C. Test Reports and Certificates. Provide all test reports and certificates required in the technical

Sections, prior to final payment. The Contractor shall provide a check list of required reports and certificates, by specification Section numbers.

D. Identification of Equipment. Prior to substantial completion, the Contractor shall provide the identification tags or plates, or other identification means, as specified under the technical Sections of the specifications, such as at valves, panelboards and similar items. Plates with directions, circuit data and similar information shall also be affixed.

E. Final Payment. Refer to Supplemental General Conditions for procedure to follow in completing the contract.

Section 01 70 00 Page 2 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

03.02 INSTRUCTIONS TO THE OWNER

A. Requirements herein supplement any specific requirements provided under individual specification section. The intent is that the Contractor thoroughly and properly instruct the Owner in the use, operation, care and maintenance of the Project, especially the various systems and equipment installed under the Contract. The instructions shall be methodically given, cover the various phases of the work and be in sufficient detail so the Owner fully understands the building's various equipment and systems.

B. As construction progresses, and particularly in the later stages, the Contractor shall permit and shall assist designated representatives of the Owner to become familiar with the locations, methods, materials, uses and intended operation of the systems and equipment, as well as any specialized materials installations installed under his Contract. The explanations and instructions shall be provided by qualified representatives of the Contractor or his specialty subcontractors.

C. Prior to substantial completion of the work, submit three (3) copies of operating and maintenance manuals for the equipment to the Engineer in duplicate, unless otherwise specified. The manuals shall be neatly edited with similar equipment grouped, pages tabbed and indexed. All material shall be printed or typewritten, and individual pages shall be set into plastic page covers bound in a 3-ring notebook. An electronic copy in PDF format on CD shall be provided in each manual. The manuals shall contain the following information:

1. Complete operating instructions and recommendations as to fuel and other materials to be used in or with the item.

2. Manufacturer's complete data sheets.

3. Complete cleaning instructions including recommended cleaning materials.

4. Maintenance data, repair and adjustment data including manufacturer's instructions.

5. Parts list with numbers, recommended parts to stock and nearest parts depot and service organization.

6. Assembly drawings, wiring diagrams, mechanical diagrams and installation diagrams and instructions.

D. Attachments to the Owner's maintenance manuals shall include, in duplicate as appropriate:

1. All guarantees and warranties.

2. As-built drawings, which are bid documents revised to show addenda, change orders and no charge changes by the Contractor.

3. Product literature describing all products used and for all approved product substitutions.

4. One approved copy of shop drawings per each specification section are to be turned over to the Owner.

5. Salvage materials stipulated for return to the Owner.

6. Excess supply quantities of materials as required by the Documents.

Section 01 70 00 Page 3 of 3 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

03.03 SYSTEMS AND EQUIPMENT TESTING

A. Contractor is responsible for testing all equipment and systems of the Contract and demonstrating that they are correctly installed and operating properly, in the intended and planned manner. The Contractor shall operate and test each system and provide a written record of the tests and the results.

03.04 CLEAN-UP

A. Refer to General Conditions and Section 01 01 00 for General Requirements of cleaning during construction.

B. Contractor shall thoroughly clean the materials, equipment or other items of his Contract. Cleaning shall be done by appropriate methods (scrubbing, washing, damp mopping, dusting, vacuuming) to leave surfaces, areas, space and interiors free from stains, discolorations, oil, grease, dirt, dust or other soil and to leave the work in a clean and streak-free condition. All labels shall be removed, except those labels, plates or tags that are necessary to leave for the proper use of the equipment or item or have data and characteristics that are necessary to leave.

03.05 CLOSEOUT SUBMITTALS

A. When the Engineer has determined that the Work is acceptable under the Contract Documents and the Contract fully performed, the Contractor shall prepare and submit his final Application for Payment to the Engineer together with the following:

1. Contractor's Affidavit of Payment of Debts and Claims, AIA Document G706.

2. Contractor's Affidavit of Release of Liens, AIA Document G706A.

a. Contractor's lien waiver in the full amount of the Contract Sum.

b. Lien waivers from all Subcontractors, sub-subcontractors and major suppliers who have furnished material for the work under contract with the Contractor or a Subcontractor. The lien waivers shall be in the full amount of the contract involved.

3. Consent of surety to final payment on Consent of Surety Company to Final Payment, AIA

Document G707.

4. Final Settlement of Contract With State of Minnesota: Submit From IC-134, Affidavit for Obtaining Final Settlement of Contract With the State of Minnesota and its Political or Governmental Subdivisions. Form IC-134 is a certificate of compliance with Minnesota Statutes 290.92 and 290.97.

5. Evidence of compliance with requirements of governing authorities:

a. Certificates of Inspection from all required agencies and departments.

b. Certificate of Occupancy.

6. Construction Record Drawings.

7. Operating and Maintenance Data, Instructions to Owner's Personnel.

8. Warranties and Bonds.

DIVISION 21

GENERAL REQUIREMENTS OF

FIRE SUPPRESSION SYSTEMS

Section 21 01 00 Page 1 of 12 E Living Unit Fire Suppression

EEA Proj. No. 6426

01.01 CONDITIONS

A. Each contractor involved in the work of any section of Division 21 for this project shall be governed by Section 21 01 00, "General Requirements for Fire Suppression Systems," in its entirety.

B. The General Conditions, Supplementary General Conditions, and Division 01 General

Requirements apply to Division 21.

01.02 SUMMARY OF WORK

A. In general, the work of this Division consists of extending an existing wet-pipe fire suppression system to serve the E Living Unit.

B. Work to be accomplished under this Specification and the accompanying drawings includes the furnishing of all labor, materials, equipment, and services necessary for the proper completion of all of the work. The extent of fire suppression systems work is indicated on drawings and by requirements of this Section and other Division 21 sections. The omission of express reference to any equipment, materials, or services necessary for or reasonably incidental to a complete installation shall not be construed as releasing the Contractor from providing such equipment, materials, or services.

C. Attempts have been made to specify all fire suppression systems equipment in accordance with applicable and governing codes and regulations. The Contractor shall endeavor to follow such regulations and notify the Architect/Engineer of any deviations from these regulations in a timely manner.

01.03 INSPECTION OF SITE

A. Before submitting a proposal on the work contemplated in this Specification and accompanying drawings, each bidder shall examine the site, check as to the means of making connections to services, and shall become familiar with all the existing conditions and limitations. No extras will be allowed because of the bidder’s misunderstanding as to the amount of work involved or his lack of knowledge of any site conditions which may affect his work. Any apparent variance of the plan or specification from existing conditions at the site shall be called to the attention of the Engineer during the bid period so clarification can be made by addendum.

B. Existence of any wires, conduits, pipes, or other facilities are shown in a general way only. It will be the duty of the bidding contractors to visit the site and make the exact determination of the existence of any such facilities prior to the submission of bids. It is understood that the bidders will be responsible for making the exact determination of the location and condition of such facilities.

01.04 FEES, PERMITS, AND INSPECTIONS

A. All required fees, permits, and inspections shall be secured and paid by the Contractor, under the section of the Specifications for which they are required.

Section 21 01 00 Page 2 of 12 E Living Unit Fire Suppression

EEA Proj. No. 6426 RECS Proj. No. 78SC0055

B. Regular inspections shall be requested and arranged by the Contractor as required by regulations. Charges from regulating agencies for inspections of installations or review of drawings and specifications shall be paid by the Contractor.

C. Certificate of Final Inspection. Under each applicable section of the Specifications, the

Contractor shall, upon completion of the work under that section, furnish a Certificate of Final Inspection to the Owner from the inspection department having jurisdiction.

D. State and Local Sales Tax. The Contractor shall include all State and local sales tax in the bid.