This Statement of Work (SOW) details a kitchen grease trap replacement project at Fermi National Accelerator Laboratory (Fermilab) in Batavia, Illinois. The project involves removing existing grease traps and installing two new pump-out grease interceptors in the Wilson Hall kitchen, with work to be performed during the winter break from December 22, 2025, through January 4, 2026. The subcontractor will be responsible for procurement of materials, pre-installation assessment, demolition of existing traps, installation of new interceptors, concrete replacement, leak testing, and providing operational training to Fermi Forward Discovery Group (FFDG) personnel. The project objectives include improving wastewater management, ensuring compliance with plumbing regulations, and providing a long-term solution for grease and solids capture, with an estimated project timeline of 30 days and a construction dumpster to be provided by FFDG.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW DATE: 10/3/2025
PROJECT TITLE: WHL KITCHEN GREASE TRAP REPLACEMENT
COUNTY THAT WORK WILL BE COMPLETED IN: DuPage☒ Kane☐ Fermilab County Line
INTRODUCTION
This project aims to enhance wastewater management in the Wilson Hall kitchen by replacing the existing grease traps with two (2) new pump-out grease interceptors. Wilson Hall is a high-rise building situated on the grounds of Fermi National Accelerator Laboratory (Fermilab) in Batavia, Illinois. The Fermilab site encompasses 6,800 acres and is owned by the U.S. Department of Energy (DOE), with operations overseen by the Fermi Forward Discovery Group
(FFDG).
The subcontractor shall provide all labor, materials, equipment, and supervision necessary to perform the work as described in the drawings, technical specifications and the scope of work below. An FFDG Task Manager or Construction Coordinator (TM/CC) will be assigned to provide oversight of the project.
OBJECTIVE
1. Improve kitchen wastewater management by replacing outdated grease traps.
2. Ensure compliance with all local, state, and federal plumbing and sanitation regulations.
3. Provide a reliable, long-term solution for grease and solids capture with easy pump-out access.
SCOPE OF WORK
The Subcontractor shall provide all work as shown on the drawings and technical specifications to provide two (2) new pump out grease interceptors, to include (but not limited to) the following:
1. Procure necessary materials and verify with FFDG personnel that they meet the specifications outlined.
2. Conduct a pre-installation assessment to confirm sizing, location, and existing plumbing connections.
3. Ensure that the work site is set up to minimize contamination to other areas of the kitchen. Use tarps, tenting, etc. as necessary to achieve this.
4. Perform demolition of existing grease traps as indicated on the drawings.
5. Dispose of concrete debris in dumpsters provided by FFDG.
6. Disconnect, remove, and properly dispose of existing grease traps in compliance with environmental regulations.
7. Furnish and install new pump-out interceptors sized appropriately to meet current code requirements and kitchen capacity, as indicated on the drawings.
8. Coordinate installation to minimize kitchen downtime, including after-hours work if required.
9. Perform start-up, leak testing, and operational verification of installed interceptors.
10. Replace concrete, as necessary once installation of interceptors is complete, as shown on the drawings to include:
a. Top cover of new interceptor should be flush with finished floor.
b. All exposed edges of finished concrete shall have a ¾” champer.
c. Replaced concrete shall be finished to match the surrounding floor.
11. Provide overview of new equipment to FFDG personnel on the proper operation and function of the interceptors.
Statement of Work https://fermipoint.fnal.gov/org/os/FESS/web_docs/Shared%20Documents/Fermilab%20-%20with%20County%20Lines-compressed.pdf
12. Submit as-built drawings and all manuals and operation guides upon completion.
13. Ensure worksite is cleaned and free of debris. Dispose of all waste materials in FFDG supplied dumpster.
14. Perform close out of project with the TM/CC.
DELIVERABLES
The Subcontractor shall execute all construction activities as required to fulfill the scope of work in accordance with the approved drawings and specifications. Prior to commencing construction, the Subcontractor shall submit all relevant submittals and shop drawings to Fermilab for review and comment, detailing the proposed equipment and layout.
SCHEDULE
• Milestone 0: Day 0 – Notice to Proceed (NTP) issued
• Milestone 1: Days 1–12 – Mobilization period
• Milestone 2: Days 13–26 – Execution of work as defined in the Scope of Work (SOW)
• Milestone 3: Day 30 – Project completion, including all final tasks and deliverables
The NTP establishes the official start date of the project timeline. The Project Completion milestone signifies the conclusion of all work, including resolution of punch list items, site clean-up, and acceptance of as-built drawings and any required submittals.
GOVERNMENT FURNISHED PROPERTY
Construction dumpster only by FFDG. All other supplies will be provided by the Subcontractor.
PLACE OF PERFORMANCE
Fermi National Accelerator Laboratory (Fermilab) Wilson Hall ground floor Kitchen Batavia, IL 60510.)
ESTIMATED SCHEDULE/PERIOD OF PERFORMANCE
The expectation is to do this work during the winter break from the kitchen will be closed from December 22, 2025, through January 4, 2026
EST START DATE: 12/15/2025 EST END DATE: 1/26/2026