Exhibit A to Draft Contract - SOW BSA_VD_CRP-SST_V8.2.pdf

PDF 782 KB Posted

Attached to
472077 RFP - DUNE VD CRP-SST
Solicitation number
472077
Issued by

About this file

This is a Statement of Work (SOW) for the procurement of sixteen (16) charge readout plane support superstructures (CRP-SSTs) for the Deep Underground Neutrino Experiment (DUNE) Vertical Drift detector, managed by Brookhaven Science Associates (BSA). The contractor is responsible for designing, manufacturing, inspecting, testing, and delivering two frame types: small and large SST frames. The large SST frame consists of three subassemblies (East/Center/West), and the contract requires delivery of twelve (12) large frames and four (4) small frames, with optional quantities of up to two (2) additional frames of each type.

Key technical requirements include providing engineering packages with 3D models, fabrication drawings, and structural finite element analysis (FEA) calculations for BSA approval; fabricating and delivering a first-article large SST frame to CERN within sixteen (16) weeks of drawing approval, followed by a small SST first article to the South Dakota Warehouse Facility (SDWF) within eight (8) weeks of drawing approval; and completing serial production of remaining frames within approximately forty-eight (48) weeks of technical performance approval. All materials must be compatible with liquid argon cryogenic environments, with fasteners specified as A4-70 stainless steel. The contractor must maintain comprehensive quality assurance per ISO 9001 or equivalent standards, submit detailed manufacturing/inspection/test plans, and provide complete end-item documentation packages for each shipment including material certifications, weld reports, dimensional survey results, and nonconformance reports. Factory acceptance testing requires dimensional verification with the frame on a flat metrology table and witness inspections by BSA representatives, with minimum two-week notice required (six weeks if contractor is outside the USA). Bi-weekly progress meetings with BSA are required during engineering phases. All documentation packages and quality records must be submitted and approved by BSA prior to shipment, with records retained for a minimum of three (3) years after contract completion.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BROOKHAVEN NATIONAL LABORATORY

BROOKHAVEN SCIENCE ASSOCIATES

UPTON, LONG ISLAND, N.Y. 11973

PROJECT:

BSA VD CRP-SST – Statement of Work

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

Document Number Date

BSA VD CRP-SST

Statement of Work

Prepared by

Nicholas Joniak / Engineer, Physics

Date

Approved by Nicholas Joniak / Technical Representative, Physics Date

Approved by Manhong Zhao / Engineer, Physics

Approved by James Stewart / DUNE Installation Coordinator, Physics

Approved by Gizandra Mussi / Quality Representative, Physics Date

This information is controlled by the U.S.

Department of Commerce Export Administration Regulations 15 CFR Parts 730-774 as EAR99 Technology.

03/10/26

03/10/26

03/11/2026

03/12/2026

03/12/2026

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

VERSION CONTROL SHEET

VERSION DESCRIPTION DATE AUTHOR APPROVED BY

1 Initial Draft April 01, 2025 N. Joniak N. Joniak

Revised per

Reviewer Comments

April 22, 2025 N. Joniak N. Joniak

Updated

Deliverables and Schedule Sections

May 27, 2025 N. Joniak N. Joniak

Updated

Requirements Section

June 13, 2025 N. Joniak N. Joniak

5 Updated Section 2 File Names July 11, 2025 N. Joniak N. Joniak

Revised per

Reviewer Comments

Aug. 5, 2025 N. Joniak N. Joniak

Revised per PRR

Reviewer Comments

Oct. 30, 2025 N. Joniak N. Joniak

Revised per

Reviewer Comments

Jan. 14, 2025 N. Joniak N. Joniak

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

Table of Contents

ACRONYMS

1 INTRODUCTION

1.1 Overview

2 APPLICABLE DOCUMENTS

3 REQUIREMENTS

3.1 Contractor Requirements

3.1.1 Technical Performance

3.1.2 Tooling/Fixtures/Test Equipment

3.1.3 Factory Acceptance Testing

3.1.4 SST Frame Serial Production

3.2 Finished Material Submittals and BSA Approval

3.2.1 End-Item Documentation Package

3.2.2 Sample Documentation Package for both US and EU Standards

3.3 Records

3.4 Serial Numbers

3.5 Storage, Packaging for Shipment, and Delivery

3.5.1 Protection of Equipment

3.5.2 Shipping Supports

3.5.3 Crating

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

3.5.4 Shipping

3.5.5 Marking of Outer Package and Hoisting & Rigging Services

4 QUALITY ASSURANCE

4.1 Quality System and Facility Access

4.2 Special Processes

4.2.1 Qualification of Procedures, Facilities, Equipment and Personnel

4.3 Responsibility for Conformance

4.4 Measuring and Test Equipment (M&TE) Calibration

4.5 Inspections and Test Requirements

4.6 Manufacturing/Inspection/Test Plan

4.7 Test and Inspection Procedures

4.8 Test Records

4.9 Failure Reporting, Analysis, and Corrective Action

4.10 Rework and Repairs

4.11 Notification of Change to Design, Methods, or Processes

4.12 Contractor’s Article Uniformity

4.13 Material Traceability

5 DELIVERABLES

5.1 Schedule of Deliverables

5.2 Summary of Equipment Items to Be Delivered (Requires BSA Technical

Representative Approval)

6 OPTIONS

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

Acronyms AWS American Welding Society BSA Brookhaven Science Associates CERN Conseil Européen pour la Recherche Nucléaire DUNE Deep Underground Neutrino Experiment CRP Charge Readout Plane CRP-SST Charge Readout Plane Support Superstructure FDC Far Detector & Cryostat FEA Finite Element Analysis PO Purchase Order QA Quality Assurance QC Quality Control SDWF South Dakota Warehouse Facility SOW Statement of Work SST Support Superstructure SURF Sanford Underground Research Facility VD Vertical Drift

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

1 Introduction This Statement of Work (hereafter SOW) will be the basis for the procurement of sixteen (16) charge readout plane support superstructures (CRP-SSTs) for the Deep Underground Neutrino Experiment (DUNE) Vertical Drift (VD) detector. This document outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.

1.1 Overview

DUNE will feature two (2) “Far Site” liquid Argon cryostats, and these structures will be constructed in the Sanford Underground Research Facility (SURF) in South Dakota. Due to the different technologies used in the design of these experiments, each cryostat will require unique tooling and installation procedures for the assembly of all internal components.

Within the VD cryostat, two (2) of the main component systems are the central cathode plane and the upper/lower anode planes. The anode planes are integrated into charge readout planes (CRPs), and these components are mounted underneath the CRP-SSTs. At the horizontal midplane of the detector is an array of cathode modules suspended with Dyneema ropes from the CRP-SST frames. These frames are a critical structural component within this detector and require precision fabrication with strict tolerances.

2 Applicable Documents The document herein defines the statement of work requirements for the BSA VD CRP-SSTs. This document shall be read in conjunction with Brookhaven Science Associates (BSA) document BSA_VD_CRP-SST_SPC- 001 and technical specification drawings “2874228-01_-_FD2_CRP-SST-01_10-30-2025” & “2874228-02_- _FD2_CRP-SST-01_10-30-2025”. Also provided are preliminary design level 3D models of both the small and large SST frames.

DOCUMENT TYPE DOCUMENT NUMBER

Technical Specification BSA_VD_CRP-SST_SPC-001 Technical Specification Drawings 2874228-01_-_FD2_CRP-SST-01_10-30-2025

2874228-02_-_FD2_CRP-SST-01_10-30-2025

3D Models FD2-superstr-Middle_set.stp

CRP-SST_Small_Module_V2.0.stp

3 Requirements In accordance with the applicable specifications, referenced documents, drawings, and instructions as defined in this Statement of Work (SOW), the Contractor shall be responsible for designing, manufacturing, inspection, testing, and delivering the CRP-SST frames as set forth herein.

Contractor shall provide timely updates on the status of the design, material procurements, fabrication, and delivery schedule as per milestones specified in the contract.

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

3.1 Contractor Requirements

3.1.1 Technical Performance

The Contractor is responsible for the structural engineering analysis of both the large and small SST frames in compliance with the BSA technical Specification BSA_VD_CRP-SST_SPC-001. The Contractor shall ensure that the design and fabricated parts conform to the approved production drawing package and approved 3D models.

3.1.1.1 Large SST Engineering Package

• Contractor shall provide an engineering package to BSA for the design of the large SST by the date provided in the table in Section 5.1. This submittal shall include a 3D model of the large SST with all proposed modifications, fabrication drawings, and an accompanying engineering note. The engineering note document shall include comprehensive structural engineering calculations utilizing finite element analysis (FEA) verifying the design performance of the large SST frame. Detailed requirements of the engineering note are listed in BSA technical specification BSA_VD_CRP-SST_SPC-001. BSA shall have four (4) weeks to review and provide comments on the engineering package. If the Contractor-supplied engineering package (3D models, fabrication drawings, and/or structural calculation) does not pass review, BSA will specify what modifications are required. The Contractor shall be responsible for incorporating all agreed-to changes in the final design package. Fabrication activities shall not commence until written BSA approval on the engineering package is received.

o During the engineering phase of the large SST, BSA and the Contractor shall have frequent update meetings to measure progress and ensure design compliance. The meetings shall occur on a bi-weekly basis, unless otherwise approved by the BSA Technical Representative.

o Contractor-generated fabrication drawings must feature tolerances that meet or exceed those presented in the bid technical specification drawings provided at the time of solicitation.

3.1.1.2 Small SST Engineering Package

• After the shipment of the large SST first article to CERN has been sent, the Contractor shall begin work on the design for the small SST frame. The Contractor shall provide an engineering package to BSA for the design of the small SST by the date provided in the table in Section 5.1. This submittal shall include a 3D model of the small SST with all proposed modifications, fabrication drawings, and an accompanying engineering note. The engineering note document shall include comprehensive structural engineering calculations utilizing finite element analysis (FEA) verifying the design performance of the small SST frame. Detailed requirements of the engineering note are listed in the BSA technical specification BSA_VD_CRP-SST_SPC-001. BSA shall have four (4) weeks to review and provide comments on the engineering package. If the Contractor-supplied engineering package (3D models, fabrication drawings, and/or structural calculation) does not pass review, BSA will specify what modifications are required. The Contractor shall be responsible for incorporating all agreed-to changes in the final design package.

Fabrication activities shall not commence until written BSA approval on the engineering package is received.

o During the engineering phase of the small SST, BSA and the Contractor shall have frequent update meetings to measure progress and ensure design compliance. The meetings shall occur on a bi-weekly basis, unless otherwise approved by the BSA Technical Representative.

o Contractor-generated fabrication drawings must feature tolerances that meet or exceed those presented in the bid technical specification drawings provided at the time of solicitation.

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

3.1.2 Tooling/Fixtures/Test Equipment

The Contractor shall be responsible for supplying all materials, including (but not limited to) the construction of all tools, jigs, fixtures, and test equipment required to complete the engineering, manufacturing, assembly, inspecting, testing, shipment, and delivery of the SST frames.

3.1.3 Factory Acceptance Testing

3.1.3.1 Large SST Factory Acceptance Testing

• The Contractor shall procure all materials, fabricate, assemble, qualify, package, and deliver the complete individual components for one (1) large SST as a first article. When the fabrication of the first article large SST frame is completed, the Contractor will verify all dimensions and conduct a test assembly prior to shipment to CERN (per Section 3.5.4). BSA will conduct a site visit for inspection (and witness of test assembly & survey) prior to shipment and Contractor must provide a minimum of two (2) weeks’ notice (or six (6) weeks’ notice if Contractor is located outside of the USA) of the inspection, test assembly, and survey.

o The first article large SST inspection by BSA is intended to verify the Contractor’s fabrication process and measure the final tolerances achieved prior to proceeding with serial fabrication.

o Fasteners need to be specified through the engineering validation process with preliminary engineering design bolt selections being presented in the BSA technical specification documents. Due to component operation in cryogenic temperatures while being submerged in liquid Argon, all indicated hardware (bolts and washers) must be A4-70 stainless steel. Carbon steel hex nuts are specified to prevent galling during all assembly tests and will be replaced after delivery with silver-plated hex nuts by BSA.

The procurement and installation of the final silver-plated hex nuts are not the responsibility of the

Contractor.

o All materials (excluding carbon steel hex nuts) must be compatible with a liquid Argon cryogenic environment.

o Serial production of the large SST shall not commence until written approval by BSA confirming frame performance is given to the Contractor.

After receiving BSA approval for the first article, all of the remaining units required by the

PO/contract must be produced by the Contractor and the Contractor’s suppliers using the same design, materials, processes, methods and tooling that were used to manufacture the approved first article(s). Any changes must have prior written approval from BSA.

• After serial production of the large SST frames has commenced, each finished frame shall be inspected, test assembled, and surveyed by the Contractor as specified in the BSA-approved factory acceptance testing plan. All end-item documentation must be completed and sent to BSA for approval prior to shipment as stated in Section 3.2.1.

• For all large SST acceptance tests (including the first article):

o All fabrication dimensions and tolerance measurements should be verified with the SST frame laying on a flat metrology table or other flat surface.

No load should be applied to the structure during these checks.

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

3.1.3.2 Small SST Factory Acceptance Testing

• The Contractor shall procure all materials, fabricate, assemble, qualify, package, and deliver the complete individual components for one (1) small SST as a first article. When the fabrication of the first article small SST frame is completed, the Contractor will verify all dimensions and conduct a survey prior to shipment to the South Dakota Warehouse Facility (SDWF) (per Section 3.5.43.1). BSA will conduct a site visit for inspection (and witness of survey) prior to shipment and Contractor must provide a minimum of two (2) weeks’ notice (or six (6) weeks’ notice if Contractor is located outside of the USA) of the inspection, test assembly, and survey.

o The first article small SST inspection by BSA is intended to verify the Contractor’s fabrication process and measure the final tolerances achieved prior to proceeding with serial fabrication.

o Please note that only the large SST first article will be sent to CERN for testing and not the small SST.

o All materials must be compatible with a liquid Argon cryogenic environment.

o Serial production of the small SST shall not commence until written approval by BSA confirming frame performance is given to the Contractor.

After receiving BSA approval for the first article, all of the remaining units required by the

PO/contract must be produced by the Contractor and the Contractor’s suppliers using the same design, materials, processes, methods and tooling that were used to manufacture the approved first article(s). Any changes must have prior written approval from BSA.

• After serial production of the small SST frames has commenced, each finished frame shall be inspected and surveyed by the Contractor as specified in the BSA-approved factory acceptance testing plan. All end-item documentation must be completed and sent to BSA for approval prior to shipment as stated in Section 3.2.1.

• For all small SST acceptance tests (including the first article):

o All fabrication dimensions and tolerance measurements should be verified with the SST frame laying on a flat metrology table or other flat surface.

No load should be applied to the structure during these checks.

3.1.4 SST Frame Serial Production

• After written approval has been received from BSA confirming the technical performance of each respective SST frame type, the Contractor shall proceed with serial production of the approved frame type. The Contractor shall procure all materials, fabricate, assemble, qualify, package, and deliver all complete individual components for three (3) small SST and eleven (11) large SST frames. If any contract options as noted in Section 6 are added to the contract, the total frame quantity previously noted must reflect all additional frames purchased. At this time the Contractor must update the fabrication schedule and notify BSA.

3.2 Finished Material Submittals and BSA Approval

3.2.1 End-Item Documentation Package

The Contractor must provide a documentation package for each shipment of completed SST frames, which consists of objective evidence of compliance with PO requirements. This documentation package must be complete, legible, indexed, and traceable to the item supplied. Three (3) copies of the documentation package must be included with each shipment. The documentation package for each SST frame must be approved by BSA prior to shipment. An example of a complete set of documentation provided for both US and EU codes is

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025 provided below in Section 3.2.2. Additionally, the following must be included with each end-item documentation package:

1) Copies of reports of all required or necessary inspections, examinations and tests, properly validated by the

Contractor’s authorized personnel.

a. These shall include test results verifying the dimensional tolerances per the QA/QC plan cited in the

Pre-Award Submittal, weld test results/weld material certifications, and final survey reports as detailed in the BSA technical specification drawing package.

2) A listing of the as-built configuration of each delivered item; this may be defined by the use of drawing numbers and revisions, unique parts lists or other such means of positive identification.

3) Copies of nonconformance reports dispositioned as “rework/repair” or “use-as-is.”

4) Copies of material test certificates for specified materials showing physical and chemical properties.

Material certificates, welder qualifications, weld inspection reports according to the standards listed (please reference Section 3.2.2 for an example set of either US or EU standards), and all dimensional measurements and survey information must be submitted to BSA prior to shipment of material. BSA must receive and approve all documentation before shipment can be authorized. Shipment of the frames to either delivery location may only begin once written BSA approval is given to the Contractor.

3.2.2 Sample Documentation Package for both US and EU Standards

COMPLIANCE OFFICE QA/QC REQUIREMENTS EXAMPLE – US STANDARDS

• The documentation provided by the appointed firm(s) shall demonstrate that the assembly complies with the requirements prescribed in:

- AISC 360 – Specifications for the design of steel structures

- AWS D1.1/D1.1M - Structural Welding Code

- RCSC Specification for Structural Joints Using High-Strength Bolts

- AISC Code of Standard Practice for Steel Buildings and Bridges

• Copies of materials test report for the main structural steel elements according to section A3.1 of AISC 360;

• Copies of manufacturer’s certifications for the fasteners according to section A3.3 of AISC 360;

• Copies of manufacture’s certification for the welding consumables according to section A3.5 of AISC 360;

• Manufacturer’s product data sheets or catalog data for welding filler metals and fluxes to be used. The data sheets shall describe the product, limitations of use, recommended or typical welding parameters, and storage and exposure requirements, including baking, if applicable.;

• Welding procedure specifications (WPS);

• Procedure qualification records (PQR) for WPS that are not prequalified in accordance with Structural Welding

Code—Steel AWS D1.1/D1.1M, or Structural Welding Code—Sheet Steel AWS D1.3/D1.3M , as applicable.;

• Welding personnel performance qualification records (WPQR) and continuity records;

• Fabricator’s or erector’s, as applicable, written QC manual that shall include, as a minimum:

- Material control procedures

- Inspection procedures

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

- Nonconformance procedures

• Fabricator’s or erector’s, as applicable, QCI (Quality Control Inspector) qualifications;

• Fabricator NDT personnel qualifications, if NDT is performed by the fabricator;

• Dimensional inspection of the Structure: report demonstrating compliance with the tolerances indicated on the drawings shall be provided;

• Non-conformities impacting the Compliance Office validation (dimensional, material properties, etc...): In case of non-conformities unresolved accepted by the Project, the non-conformity documentation, justification of acceptance and eventually technical compensatory measures implemented should be provided to Compliance Office for analysis and approbation.

COMPLIANCE OFFICE QA/QC REQUIREMENTS EXAMPLE – EU STANDARDS

• The documentation provided by the appointed firm(s) shall demonstrate that the assembly complies with the execution class 2 (EXC2) of the EN1090 or equivalent;

• Certificates according to EN 10204 type 3.1 for all the materials constituting the structure.

• Dimensional inspection of the structure: report demonstrating compliance with the tolerances indicated on the drawings shall be provided;

• Documentation demonstrating compliance with the following requirements shall be provided for the welding connections:

- All welds shall be inspected for imperfections according to level C of ISO 5817;

- 100% of the welds shall be controlled by visual inspection according to EN ISO 3452-1;

- Non-destructive tests of the welds shall be performed according to the extent specified in the EN 1090 for the EXC2. The method to be used for the test shall be selected from those given in EN ISO 17635;

- The welders shall be qualified according to ISO 9606-1;

- Welding procedure specification (WPS) and welding procedure qualification record (WPQR) shall be provided according to EN ISO 15614-1;

- NDT personnel shall be qualified according to EN ISO 9712.

• Cleaning certificate issued by the Contractor regarding the regarding the operations performed during manufacturing/ before welding and after welding;

• Labelling of the structure guaranteeing the full traceability of the components;

• Evidence (inspection, report, pictures) that each structure is installed in the transport box as specified before each transport phase.

• Visual inspection reports of the transport box and structure after each transport phase

• Non-conformities impacting the Compliance Office validation (dimensional, material properties, etc...): In case of non-conformities unresolved accepted by the Project, the non-conformity documentation, justification of acceptance and eventually technical compensatory measures implemented should be provided to the Compliance Office for analysis and approved;

3.3 Records

The Contractor shall retain evidence, including records of the inspections and tests performed during manufacturing, testing, inspecting, packaging, and preparation for shipment of procured items. These records shall be made available to BSA for review upon request. These records shall be maintained for a minimum of three (3)

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025 years, unless otherwise specified in the procurement documentation, after the completion of the Purchase Order (PO)/Contract.

3.4 Serial Numbers

The Contractor must assign/mark a separate and distinct serial number to each end-item in accordance with the procurement documentation. A record of the serial number, for each part number, must be maintained by the Contractor. The serial numbers must comply with the BSA-provided serialization number scheme as seen below in Table 1, and must be included in the bill of lading when shipping.

1) Please note that three (3) subassemblies will be used to form a complete large SST frame. Each subassembly end-item (East/Center/West) will require a unique serial number. In addition, each of the three (3) subassemblies that are tested and surveyed together will need to be marked with the serial number of the large SST frame that they are assigned to.

Table 1 Sample SST Frame Serialization Numbering

3.5 Storage, Packaging for Shipment, and Delivery

3.5.1 Protection of Equipment

Contractor shall assume the responsibility to design and fabricate protective packaging with adequate performance to ensure protection against natural and induced environments during delivery and storage of the SST frames. The Contractor shall employ procedures which ensure adequate protection of material and equipment during shipment and while in storage.

In preparation for shipping, the SST frames shall be covered or wrapped for protection against weather elements, road salt, dust, and damage to projections, shock loads, impacts, and rubbing. The SST frames shall be properly braced and cushioned within the packing so that it will not shift during handling and shipment.

3.5.2 Shipping Supports

Any internal or external transport or shipping supports that have been engineered during the design phase shall be implemented and documented with a traveler that these supports have been appropriately installed.

3.5.3 Crating

All small parts shall be crated into one or more smaller crates for shipping. All pieces of equipment shall be sufficiently protected when shipped on an open bed truck. All individual items in a crate or box shall be listed separately to clearly indicate the contents of each box or crate.

3.5.4 Shipping

There are two (2) specified delivery locations: CERN for the first article large SST frame only, and the Far Detector & Cryogenics (FDC) South Dakota Warehouse Facility (SDWF) location for all other frames. Copies of the data required in accordance with the procurement documentation must accompany each shipment. An additional copy of the data must be mailed to BSA at time of shipment for record purposes. All required freight

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025 forwarding processes required for components shipped overseas will be the responsibility of the Contractor. For all ground-based travel, the Contractor shall ship all deliverable items on an “air-ride” boxed truck/semi-trailer. If the components are oversized and a non-boxed truck is used, then the equipment shall have enough crating or protection to prevent damage from debris during transport. Shipping shall be on a dedicated truck to ensure timely delivery and protection of items.

All components to be delivered to the FDC SDWF location according to the schedule agreed upon at the time the contract is signed. Component delivery in batches to be approved by BSA Technical Representative prior to shipment.

a. CERN Address:

i. CERN Site De Meyrin

185/R-001, Route De Meyrin, Entrée D, Geneve 23 Switzerland, CH-1211

b. SDWF Address:

i. Dakota Warehouse

1313 E Saint Patrick St.

Rapid City, SD 57701

3.5.5 Marking of Outer Package and Hoisting & Rigging Services Each shipping container (transport package) with a gross weight equal to or greater than 400 pounds (180 kilograms) shall be marked with the center of gravity and gross weight on at least one side, and one end panel in addition to meeting the requirements of the latest revision of ASTM Standard D 3951-98, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BSA or other locations cited in the purchase order or contract. Advance notice shall be given to BSA if the packaging is unusually long (greater than 20 ft) or wide. A list of overall dimensions shall be submitted electronically to BSA Technical Representative at least 1 week in advance of shipment.

4 Quality Assurance

4.1 Quality System and Facility Access

The Contractor shall maintain a documented quality assurance system, which provides the processes to ensure that each component produced for acceptance conforms to the requirements of this document and the applicable technical documentation.

The Contractor’s responsibility includes ensuring adequate QC services are provided for work accomplished on-and off-site by their organization, suppliers, sub-tier subcontractors, technical laboratories, and consultants. The work activities included submittal management, testing and inspection, and all other functions related to the requirement for quality manufacturing. The Contractor shall implement a QC program and designate a quality responsible person(s) to achieve these goals.

The Contractor must submit its Company QA Program along with its proposal and written BSA approval is required before contract execution. The quality program shall meet an applicable nationally recognized standard such as ISO 9001, ASME, etc. The Contractor’s welding program shall meet applicable nationally recognized

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025 standards such as ASME, AWS, etc., and utilize qualified welders, Weld Procedure Specifications, and Weld Qualification Records. Please reference Section 3.2.2 for an example set of required QA/QC documents for both US and EU standards.

• The welding process and quality documentation must conform to the standards chosen above. Only one

(1) set of standards must be chosen (European or US) for design/fabrication. No mixing of US and EU standards is permissible.

BSA representatives shall have access to the Contractor’s facility during agreed upon fabrication, inspection, and testing processes. Contractor must provide a minimum of two (2) weeks’ notice (or six (6) weeks’ notice if Contractor is located outside of the USA) in advance of the agreed upon witness points.

4.2 Special Processes

Processes (e.g., welding, brazing, bonding, plating, chemical machining, chemical coating, chemical cleaning, precision cleaning, heat treating, or waste processing) that either cannot be verified non-destructively or require a unique (special) non-destructive test/inspection (e.g., radiographic inspection, ultrasonic testing, pressure leak testing) must be performed in accordance with detailed written procedures. These procedures must specifically describe the exact manner in which the processes are to be performed. Additionally, the following requirements apply as selected:

1) Copies of special process procedures must be made available on request by BSA.

2) At least sixty (60) calendar days prior to the use on items deliverable to BSA, the Contractor must submit to

BSA copies of all applicable process procedures for review and approval. Revisions or changes to BSA-approved special process procedures must be submitted to BSA for review and approval prior to implementation.

4.2.1 Qualification of Procedures, Facilities, Equipment and Personnel The Contractor must, prior to use, qualify the procedures/specifications, facilities, equipment and personnel that will be used for the performance of special processes. Only those personnel who have been qualified to perform a specific special process must be used to perform that process. Records of such qualification must be available to BSA upon request.

4.3 Responsibility for Conformance

The Contractor is responsible for providing items which conform to the requirements of the PO/Contract regardless of any assessments, surveillances, inspections and/or tests by BSA or its representatives at either the Contractor’s or BSA’s facility. The Contractor is responsible for notifying the BSA contractual representative of any recalls or alerts associated with this PO/Contract.

4.4 Measuring and Test Equipment (M&TE) Calibration

The Contractor shall calibrate any M&TE used in the fulfillment of the PO/Contract requirements against certified standards that are traceable to national standards such as the National Institute of Standards and Technology (NIST), or an international standard, or a physical constant. The Contractor shall notify BSA of any condition found during the calibration, servicing or repair of measuring and test equipment that can affect the end item requirements.

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

4.5 Inspections and Test Requirements

BSA reserves the right to perform any of the inspections and/or tests set forth in this document or referenced specifications where deemed necessary to ensure that supplies and services conform to prescribed requirements at no cost to the contract/BSA. BSA and/or their representative shall have the option to witness all the tests defined in this SOW.

4.6 Manufacturing/Inspection/Test Plan

Sixty (60) calendar days prior to performance of work, the Contractor must submit for BSA approval a Manufacturing/Inspection/Test Plan for the SST frames (both large and small frames). Once approved, changes/revisions must be approved by BSA prior to implementation. This shall include the following:

1) Identification of parts and subassemblies showing integrated flow into end item(s). This includes ensuring that the three (3) subassemblies comprising a single large SST frame are test assembled and surveyed together, and that they are marked per Section 3.4, so each subassembly can be easily traced to their final large SST frame assembly.

2) Identification of critical manufacturing operations, as well as inspection and test checkpoints.

3) The plan may be a single document, or may make use of existing “travelers,” or other suitable planning and control documents.

4.7 Test and Inspection Procedures

Test and inspection procedures required to demonstrate satisfactory completion of requirements shall be prepared by the Contractor and submitted to BSA for approval sixty calendar (60) days prior to the use of such procedures.

BSA reserves the right to modify the tests or to require any additional test procedures or details deemed necessary to determine compliance with the requirements of this SOW. The test details, such as fixture design, length of cycle, use of limited life material, etc., shall be part of the test procedures to be submitted. Once approved, changes/revisions shall be approved by the BSA technical representative prior to implementation.

4.8 Test Records

Test records shall be prepared and maintained for all tests herein. Records shall show test dates, test conditions, test equipment/instrumentation/gages identification (name, model/part number, serial number), test pressures, test durations, leakage rates, and other system characteristics. Test records shall be well organized and shall clearly and uniquely identify each test record to the specific item tested, and its final installed location. For this reason, drawings shall be included in test records.

Records shall include, but are not limited to the following:

1. Inspection and sign-off of raw material certifications.

2. Periodic inspection and sign-off of processes performed throughout fabrication.

3. Inspection and sign-off of dimensional tolerance checks with measured values.

4. Inspection and sign-off of adherence to BSA specifications.

5. Final dimensional survey according to BSA technical specification drawings.

6. Date, time, and signature for all inspections.

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

7. A report(s) must be submitted that indicates the complete inspection of welds or brazes from the initial fit-up stage through final inspection. Inspection reports must be accompanied by all radiographic films, filler metal reports etc. The reports must contain the signature or stamp, and title of an authorized Supplier representative.

4.9 Failure Reporting, Analysis, and Corrective Action

The Contractor shall maintain a failure reporting, analysis, and corrective action system that must, at a minimum, evaluate, analyze and correct failures occurring during qualification, first article and end-item acceptance testing and inspection. The results of all failure evaluations and analyses must be documented and available for review by BSA.

4.10 Rework and Repairs

If a non-conformance occurs or repairs are required to an assembly or any component during manufacturing or testing that affects form, fit, function, reliability, safety, or interchangeability, the process shall stop and BSA shall be immediately notified. BSA at their discretion may ask for retesting, additional review, and evaluation to determine root causes, analyses of failure modes(s), and corrective action plan. Corrective action plans for repair shall include adequate information for evaluating the repair, testing the effectiveness of repair, and methods to prevent damage to the existing work. No repair shall be initiated without approval of the BSA technical representative. All repairs shall be at the expense of the Contractor.

4.11 Notification of Change to Design, Methods, or Processes

The Contractor must immediately notify BSA of any significant changes (those that may affect form, fit, function, reliability, safety, or interchangeability) in product design, fabrication methods, materials, or processing from those used by the Contractor at time of Contractor’s quotation or offer to BSA, which resulted in the PO.

4.12 Contractor’s Article Uniformity

The Contractor shall establish those controls and processes necessary to ensure uniformity of all deliverable articles. All controls, inspections, processes, tests and quality assurance provisions established during development and preproduction tests shall be indicated on the applicable drawing and shall be performed on each deliverable article.

4.13 Material Traceability

Materials used must be identified by material type, applicable specification and revision number, and be traceable to their lot and/or heat number(s). Traceability records must be available for review by the BSA representative.

5 Deliverables

5.1 Schedule of Deliverables

The Contractor shall supply the following items. The scheduled due dates are for planning purposes only, and requirements set forth in the contract will govern.

Version

BSA_VD_CRP-

SST_SOW-001 Jan. 14, 2025

Deliverable Due BSA Approval

Engineering package for large SST (includes 3D model, fabrication drawings, and structural engineering calculations)

Eight (8) weeks after ARO (after receipt of order).

Yes

Manufacturing/Inspection/Test plan As detailed in Section 4. Yes List of documentation required prior to fabrication/production (including material certifications and specifications)

Two (2) weeks prior to start of fabrication activities.

Yes

Large CRP-SST first article (w/ test assembly & survey)

Sixteen (16) weeks after BSA approval of fabrication drawing package.

Yes

Engineering package for small SST (includes 3D model, fabrication drawings, and structural engineering calculations)

Eight (8) weeks after shipment of first article large SST frame to CERN.

Yes

Small CRP-SST first article (w/ test assembly & survey)

Eight (8) weeks after BSA approval of fabrication drawing package.

Yes

Serial SST frame production Estimate forty eight (48) weeks after BSA approval of large and small SST technical performance.

Yes

End item documentations As set forth in contract. Yes

5.2 Summary of Equipment Items to Be Delivered (Requires BSA Technical Representative Approval)

1) Four (4) Small CPR-SST frames.

2) Twelve (12) Large CRP-SST frames.

6 Options This section describes optional items the BSA may elect to exercise during the period of performance.

1. Up to two (2) additional small CRP-SST frames.

2. Up to two (2) additional large CRP-SST frames.

3. Cost of cleaning/degreasing the frames prior to shipment.

Acronyms
1 Introduction
1.1 Overview
2 Applicable Documents
3 Requirements
3.1 Contractor Requirements
3.1.1 Technical Performance
3.1.1.1 Large SST Engineering Package
3.1.1.2 Small SST Engineering Package
3.1.2 Tooling/Fixtures/Test Equipment
3.1.3 Factory Acceptance Testing
3.1.3.1 Large SST Factory Acceptance Testing
3.1.3.2 Small SST Factory Acceptance Testing

3.1.4 SST Frame Serial Production

3.2 Finished Material Submittals and BSA Approval
3.2.1 End-Item Documentation Package
3.2.2 Sample Documentation Package for both US and EU Standards
3.3 Records
3.4 Serial Numbers
3.5 Storage, Packaging for Shipment, and Delivery
3.5.1 Protection of Equipment
3.5.2 Shipping Supports
3.5.3 Crating
3.5.4 Shipping
3.5.5 Marking of Outer Package and Hoisting & Rigging Services
4 Quality Assurance
4.1 Quality System and Facility Access
4.2 Special Processes
4.2.1 Qualification of Procedures, Facilities, Equipment and Personnel
4.3 Responsibility for Conformance
4.4 Measuring and Test Equipment (M&TE) Calibration
4.5 Inspections and Test Requirements
4.6 Manufacturing/Inspection/Test Plan
4.7 Test and Inspection Procedures
4.8 Test Records
4.9 Failure Reporting, Analysis, and Corrective Action
4.10 Rework and Repairs
4.11 Notification of Change to Design, Methods, or Processes
4.12 Contractor’s Article Uniformity
4.13 Material Traceability
5 Deliverables
5.1 Schedule of Deliverables
5.2 Summary of Equipment Items to Be Delivered (Requires BSA Technical Representative Approval)

6 Options