EXHIBIT A - SEALED BID CHECKLIST.pdf
PDF 176 KB Posted
- Attached to
- Repair CT Parking Apron Federal contract opportunity
- Solicitation number
- W50S8S25BA002
- Issued by
- Department of the Army National Guard
About this file
This document is a detailed checklist for bidders to avoid common errors and irregularities in federal contract bids. The comprehensive 20-point list covers critical bid submission requirements, including proper acknowledgment of amendments, accurate pricing, bond documentation, signatures, and representations and certifications. Key compliance points include ensuring the Bid Bond is on the correct Standard Form 24, having all prices and computations checked, verifying the bid is signed by an authorized representative, and completing all required forms such as the Plant and Equipment Schedule.
The checklist emphasizes the potential for a bid to be considered nonresponsive if specific requirements are not met, such as failing to complete the Certificate of Procurement Integrity for bids over $100,000 or not properly executing the Bid Bond. The document concludes with a caution that bids qualified by the bidder may be deemed nonresponsive, underscoring the importance of precise adherence to all bidding instructions and requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W50S8S25BA002 - CT Parking Apron - 1419 abstract construction.pdf | ||
| Solicitation Amendment - W50S8S25BA0020001.pdf | ||
| Reps and Certs Acknowledgements.docx | DOCX document | |
| RFI Responses 8-27-2025.pdf | ||
| Solicitation Amendment W50S8S25BA0020001 SF 30.pdf | ||
| ATTACHMENT 1 - SOW REV 1.pdf | ||
| W50S8S25BA002 - Repair CT Parking Apron Pre-Bid Conference-slides.pdf | ||
| PreBid SiteVisit Sign In 8-20-2025.pdf | ||
| EXHIBIT B-CHECKLIST FOR BID BONDS.pdf | ||
| ATTACHMENT 1 - SOW.pdf | ||
| ATTACHMENT 3 - DRAWINGS.pdf | ||
| Solicitation - W50S8S25BA002.pdf | ||
| ATTACHMENT 2 - UCF SPECIFICATIONS.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The following list should be used by bidders to avoid irregularities which have occurred in past bids.
1. Have amendments to the invitation been acknowledged on the< bid form in the spaces provided? If not, acknowledgment must be made by separate letter or telegram prior to opening of bids.
2. Have prices been inserted for all bid items of the Bidding Schedule?
3. Do prices inserted include subcontractors' and suppliers' quotations, indirect costs, and profit?
4. Does the total bid amount include the costs of obtaining performance and payment bonds?
5. Have all prices and computations been checked?
6. Is the bid submitted on the latest bid schedule?
7. Have changes been made to the Bidding Schedule if required by amendment?
8. Are decimal points in the bid prices in the proper places?
9. Have you checked for transposition of figures in prices inserted on the Bidding Schedule?
10. Is the bid form signed, and if so, is the bid form signed by a person legally authorized to bind the bidder?
Is the bidder's address included?
11. If the bid is signed by an agent, is legal evidence of agent's authority to sign included with the bid?
12. Is the Bid Bond on STANDARD FORM 24 (rev. 8/2016) or authorized form as directed in the BID GUARANTEE clause of this solicitation? If not, YOUR BID WILL BE CONSIDERED NONRESPONSIVE.
13. Is the Bid Bond completely and properly executed, dated not later than the bid opening date, signed by Principal and Surety, corporate certificates executed, and seals affixed, all as contained in "Instructions" on STANDARD FORM 24 BACK (REV 8-2016)? Power of Attorney is also required to accompany the bonds. Is the penal sum marked in? If an individual surety (or sureties) is (are) guaranteeing the bid bond, have the requirements of the PLEDGES OF ASSETS clause of this solicitation been satisfied and are the supporting documents included with the bond?
14. Has the Plant and Equipment Schedule been completed and included?
15. When applicable, has the form entitled, "Work to be Performed with Contractor's Own Organization" been completed? Does the work or percentage listed meet the requirements of the invitation?
16. Have the appropriate boxes been checked in all paragraphs of the REPRESENTATIONS AND
CERTIFICATIONS?
17. Has the certification contained in the provision REQUIREMENT FOR CERTIFICATE OF PROCUREMENT INTEGRITY been completed and signed? If not, and your bid is in excess of $100,000, your bid will be NONRESPONSIVE.
18. Have all representations and certifications been submitted with the bid?
19. If required by the invitation, is literature, date, catalogs, etc., specified by the invitation included with the bid?
20. Have requirements of the LATE SUBMISSIONS, MODIFICATIONS AND WITHDRAWALS OF BIDS provision of this solicitation been met?
CAUTION: BIDS WHICH ARE QUALIFIED BY THE BIDDER MAY BE CONSIDERED NONRESPONSIVE.