Exhibit A - Scope of Services.pdf
PDF 79 KB Posted
- Attached to
- Ag. Science Annex Substation Transformer
- Solicitation number
- RFP202690000694
- Issued by
- Mingo County, West Virginia
About this file
This is a Scope of Services document from West Virginia University (WVU) detailing a procurement for one primary substation liquid-filled transformer to be installed at the Agricultural Science Annex Substation on the Evansdale Campus in Morgantown, West Virginia. WVU is soliciting proposals from qualified manufacturers or distributors for this equipment. The supplier selection is anticipated within one week of proposal receipt, with purchase order issuance expected within ten business days of receiving the selected supplier's required documentation. The transformer will be installed on an existing concrete pad in a fully operational, gated substation transformer farm; the existing non-operational pad-mounted transformer will be replaced while the concrete foundation remains in place.
The document does not specify pricing terms, set-asides, incumbent information, funding sources, or other financial details. No information regarding site visits, bidder conferences, specific response deadlines, or contract renewal options is included in this scope of services excerpt.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP202690000694.pdf | ||
| 1371408-event.pdf | ||
| Exhibit C - Similar Product Experience.pdf | ||
| Exhibit B - Cost Summary Sheet.pdf | ||
| Exhibit D - Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT A - SCOPE OF SERVICES
INTRODUCTION
West Virginia University (“WVU”) is requesting Proposals from qualified manufacturers or distributors to provide one (1) primary substation liquid filled transformer to the Agricultural Science Annex (“Ag. Science Annex”) Substation on the Evansdale Campus in Morgantown WV.
SCHEDULE
WVU anticipates the Supplier selection within one (1) week after receipt of Proposals and issuance of a purchase order within ten (10) business days after receipt of the selected Supplier’s required documents.
EXISTING CONDITIONS
The existing substation transformer farm is fully operational within a gated area. The existing transformer to be replaced is still pad mounted, but not operational. The existing concrete transformer pad will remain.