This document contains two Contract Data Requirements Lists (CDRLs) for a federal contract. The CDRLs require the contractor to submit a monthly Software Version Description and a Software User Manual with each major release under Contract Number W56KGY-24-R-0001 for the PM IS&A Intel Apps Weather Operational Effects application. The Software Version Description is due monthly within 15 days of each security patch delivery. The Software User Manual is due as required but no more than 140 days after award for the initial submission. Both documents must be complete, stand-alone, and address requirements in the Statement of Work. The contractor must submit the CDRLs electronically in Microsoft Office formats to the Army Contracting Command at Aberdeen Proving Ground and Space and Naval Warfare Systems Command.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
A001 A TDP TM OTHER IPSC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Weather Operational Effects Intel Application
W56KGY-24-R-0001 TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001 Software Version Description (SVD)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-IPSC-81442A SOW Paras: 3.1.3, 3.1.6, 3.2.3, 3.2.6, 3.4.1.1, 3.5.1.1, 3.9.2, 3.10.2
SFAE-IEW-DC
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
LT MTHLY 15 DAYS XDADO b. COPIES
8. APP CODE D 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
N/A N/A 30 DAYS XDARC Reg Repr o
BLOCK 4: In addition to the requirement of DI-IPSC-81442A, the contractor shall include all the information required by the SOW. Contractor format acceptable.
BLOCK 9: Distribution authorized to U.S. Government Agencies only.
BLOCK 10: A software version description (SVD) shall be submitted monthly with each monthly security patch/release delivery.
BLOCK 12:
Deliverables shall be complete, stand-alone, and address all the concerns in SOW paragraphs shown in Block 5. Deliverables shall be submitted and exchanged electronically, in Microsoft ® Office product suite or in searchable digital formats.
SFAE-IEW-DC
ACC-APG (CCAP-CCC)
*ELECTRONIC SUBMITTAL
15. TOTAL 3
G. PREPARED BY
Andrew E. Kim PM IS&A – Intel Apps APM
H. DATE
10 Oct 2023
I. APPROVED BY J. DATE
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
A002 A TDP TM OTHERIPSC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Weather Operational Effects Application W56KGY-24-R-0001 TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A002 Software User Manual
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-IPSC-81443A SOW Para 3.2.3, 3.4.1.1, 3.5.1.1, 3.9.2 SFAE-IEW-DC
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
LT ASREQ 140 DAYS XDADO b. COPIES
8. APP CODE D 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
N/A N/A AS REQ Reg Repr o
16. REMARKS:
BLOCK 4: In addition to the requirement of DI-IPSC 81443A, the contractor shall include all the information required by the SOW. Contractor format acceptable.
BLOCK 12:
Deliverables shall be complete, stand-alone, and address all the concerns in PWS paragraphs shown in Block 5. Deliverables shall be submitted and exchanged electronically, in Microsoft ® Office product suite or in searchable digital formats.
BLOCK 13: The contractor shall deliver documents with each major release.
SFAE-IEW-DC
ACC-APG (CCAP-CCC)
*ELECTRONIC SUBMITTAL
15. TOTAL 3
G. PREPARED BY
Andrew E. Kim PM IS&A – Intel Apps APM
H. DATE
10 Oct 2023
I. APPROVED BY J. DATE