This is a Statement of Work document prepared by the Oregon Department of Transportation (ODOT) for facility repairs at the Government Camp Maintenance Station located at 90300 US-26 in Government Camp, Oregon. The project encompasses multiple building repair tasks including fuel station concrete rehabilitation and rub rail replacement, sand shed roofing screw replacement and damaged panel repair (approximately 40 panels totaling 18 feet in length), lateral trim removal and flashing installation, gable flashing replacement, and maintenance building HVAC ductwork installation with supply and return registers. An additional alternate bid item includes replacement of approximately 241 linear feet of translucent siding panels (192 linear feet on the south side and 49 linear feet on the north side, each approximately 2 feet 6 inches in height). Substantial completion is required by December 20, 2026, with final completion no later than January 10, 2027. Work shall be performed on weekdays between 6 a.m. and 4 p.m., excluding weekends and state holidays. The ODOT Construction Project Manager is Jorge Ojeda (jorge.ojeda@odot.oregon.gov, 971-429-4075). Contractors are required to conduct a site visit and examine existing conditions prior to bidding, submit all construction materials for approval before work commences, and coordinate scheduling with ODOT at least ten business days before starting work.
The contractor is responsible for obtaining all required permits, providing temporary connections to existing water and electrical services, managing all cleanup and debris removal, and protecting materials from weather damage. ODOT will not provide disposal facilities or dumpsters, and the agency assumes no responsibility for contractor materials or equipment security on the premises. The contractor must maintain compliance with Oregon OSHA regulations, provide a one-year installation warranty on all workmanship, and supply manufacturer warranties for all equipment. Prior to final completion, the contractor must deliver marked-up record drawings showing as-built conditions and underground utilities, provide digital copies of operations and maintenance information, submit equipment details including manufacturer and serial numbers, and furnish signed certification that all subcontractors and suppliers have been paid in full. Water and electrical power are available from the premises without charge, and on-site sanitary facilities are accessible to contractor personnel.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00018009_Mandatory Pre-Bid Conference Sign-In Sheet.pdf | ||
| Exhibit 6 - Drawings (For Reference Only)~1.pdf | ||
| 00018009_RFCQ.docx | DOCX document | |
| 00018009_ESB Sample Contract~1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 5
STATEMENT OF WORK
9/24/2026 Oregon Department of Transportation
ESB – ODOT Government Camp MS Misc. Facility Repairs Project Location:
Government Camp Maintenance Station
90300 US-26
Government Camp, OR 97028
ODOT Contact:
The ODOT Construction Project Manager (CPM) for this project is Jorge Ojeda.
· E-mail: jorge.ojeda@odot.oregon.gov
· Cell: (971) 429-4075
· Address: 3700 SE 92nd Ave, Portland, OR 97266 The ODOT Project Manager may designate an additional ODOT contact person or engineer to support with inspections or questions in the field.
Project Background This project addresses some facility repairs and needs at the ODOT Government Camp Maintenance Station.
Project Description:
See detailed Outline of Work to be completed in the Exhibit 1-A at the end of this document.
General Construction Notes:
· The contractor shall make a site visit and examine existing conditions prior to providing a bid. Any discrepancies shall be brought to the attention of ODOT through a request for clarification as set forth in the bid documents.
· Clarifications shall be requested in writing prior to any installation. Incorrect installations shall be corrected at no additional cost to ODOT.
· All work shown is to be by the contractor unless specifically noted as being by ODOT or by others. All materials shown are to be provided by the contractor unless specifically noted as existing or provided by ODOT.
· Some building drawings are provided for component locations and scale reference. Drawings are schematic in nature, and major components are shown on the drawings only. The contractor shall supply and install all minor components and materials necessary to provide a complete and functional project whether all such components are noted in the construction documents.
· Match adjacent finishes unless otherwise indicated in the Specifications.
· All equipment and materials shall be installed in accordance with the manufacturer’s published installation instructions and recommendations.
· All work must comply with all applicable rules, laws, and ordinances.
· Replace means remove existing, furnish, and install.
· Clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
Submittals
The Contractor shall provide the following submittals at a minimum to the ODOT Project Manager. Submittals shall be approved by the ODOT Project Manager prior to the start of on-site construction.
· All construction materials.
Scheduling of Contract:
· Substantial completion of the Work shall be no later than December 20, 2026. Final completion shall be no later than January 10, 2027.
· After award of contract, the Contractor shall contact the ODOT Project Manager to schedule the Work at least ten (10) business days prior to the start of any work/demolition.
· The Work shall be accomplished on weekdays between the hours of 6 a.m. and 4 p.m. Work hours shall exclude weekends and State Holidays, unless specifically requested by the Contractor and approved by the ODOT Project Managers.
· Any permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Manager prior to the start of work. The Contractor shall be responsible for posting all permits on site in accordance with local jurisdiction requirements.
· The Contractor shall submit to the ODOT Project Managers a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all Subcontractors and their key representatives.
· The Contractor shall coordinate the efforts of all Suppliers and Subcontractors and shall maintain orderly progress of the Work, prevent duplication of effort, and ensure proper sequence of operations.
Clean-Up/Conditions of Site:
· The Contractor shall be responsible for keeping the ODOT Project Manager informed of all activity throughout the Work.
· Water and electrical power services are available from the premises without charge. The Contractor shall provide temporary connection to existing service as needed.
· It is acceptable for the contractor to use the sanitary facilities on site, located inside the maintenance building.
· The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the premises. The Contractor shall broom-clean their work area at the end of each workday and neatly stack materials and debris in an approved location. The contractor shall clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
· The Contractor shall protect materials subject to damage by temperature or other weather conditions.
· The location for storage of materials, debris, or dumpster on the Premises shall be approved in advance by the ODOT Project Manager. Disposal facilities, bins, or dumpsters shall not be provided by ODOT.
· The Contractor shall notify the ODOT Project Manager at least two (2) days in advance of any major deliveries.
· Contractor shall immediately notify the ODOT Project Manager of any damage done by the Contractor to the Premises, grounds, or adjacent State properties. Damage done by the Contractor to the Premises or surrounding area shall be repaired to existing conditions as found prior to the commencement of the Work.
· ODOT shall not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the Premises.
· It is the responsibility of the Contractor to ensure the Work is performed in accordance with Oregon OSHA rules and regulations.
· The Contractor shall immediately bring to the attention of the ODOT Project Manager any conflicts or issues between existing utilities and the Work.
Close Out:
· All special inspections must be complete prior to Substantial Completion.
· Inspection of the work by the ODOT Project Manager for establishment of Substantial Completion shall be made within five (5) business days after receipt of the Contractor’s email request. At this time, the ODOT Project Manager and the Contractor shall develop a punch list document of any incomplete or deficient work.
· Prior to Final Completion, the Contractor shall complete all items on the punch list.
· The Contractor shall provide final inspection reports for all permits applicable to this Contract signed by authorities having jurisdiction
· The Contractor shall maintain one set of the approved drawings for recording as-built conditions. Mark (in red) the actual location of all underground utilities and any changes. At the time of Final Completion, the Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Manager.
· Prior to Final Completion, the Contractor shall provide one (1) digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Manager.
· Prior to Final Completion, provide ODOT Project Manager with information for all equipment provided by the project, including but not limited to: Manufacturer, model, serial number, consumables, installation date, purchase date.
· Prior to Final Completion, and as prerequisite for final payment, provide ODOT Project Manager with signed certification that all subcontractors and suppliers have been paid in full and in compliance with all prompt payment requirements. All disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid, and, to the best of the Contractor's knowledge, there are no claims of any kind outstanding against the project.
· Prior to Final Completion, the Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems.
· Inspection of the work by the ODOT Project Manager for establishment of Final Completion shall be made within five (5) business days after receipt of the Contractor’s email request.
Warranty:
· Contractor shall provide a 1-year Installation warranty on all workmanship.
· Contractor shall provide all warranties for equipment applicable to this Contract.
EXHIBIT 5-A
Outline of Work
| Bid Item # |
| Building |
| Scope item description. Refer to pictures below. |
| 1 |
| Fuel Station |
| A. Remove the fuel‑station island rub rail, repair chipped concrete, and install a new rub rail with similar characteristics. |
The contractor is responsible for determining and proposing an appropriate method for removing the existing rub rail, installing a replacement rub rail of at least comparable characteristics, and rehabilitating the existing fuel‑island concrete as necessary.
| 2 |
| Sand Shed |
| B. Replace all existing roofing screws throughout the building and install new roofing screws in all locations where screws are missing. |
C. Inspect overall condition of roofing panels. Replace damaged roofing panels. For estimating purposes, include a total of approximately 40 non-contiguous panels on the eave side of both roof pitches. Coordinate with ODOT CPM to confirm which specific panels will be replaced. Panel length is approximately 18’, not including overlap.
D. Remove lateral trim on the west and east sides of the building and install flashing in its place.
E. Replace damaged gable flashing located on the northwest side of the building.
| 3 |
| Maintenance Building |
| F. Install flexible duct connections above ceiling to provide HVAC from the existing ductwork into Mechanics Office 113. Install one supply register and one return register, and perform air balancing upon completion. |
| Add. alternate #1 |
| Maintenance Building |
| G. Replace approximately 192 LF of translucent siding panels on the south side of the building and approximately 49 LF on the north side. Siding height is approximately 2'-6", not including overlap. For estimating purposes, siding panel overlap is 6 inches. |
Note: ⃝ symbol is used to indicate base bid items in the pictures below. ♢ symbol is used to indicate add-alternate bid items.
0. Government Camp Maintenance Station
Picture 1: Government Camp MS aerial view
1. Fuel Station Picture 2: East side
Picture 3: West side
Picture 4: North Side
2. Sand Shed Picture 5: East view
Picture 6: East view
Picture 7: West view
Picture 8: Northwest view
3. Maintenance Building Picture 9: Excerpt from building as-built drawings
Picture 10: Interior of Mechanic Office
Picture 11: South façade – west side
Picture 12: South façade – east side
Picture 13: North façade
Sand Shed
Maintenance Building
N
Fuel Station
Revision: 5/7/24
File details come from the government source that posted it. Updated .