This is a Sample Public Improvement Contract from the State of Oregon, Department of Transportation (ODOT), for miscellaneous facility repairs at the Government Camp Maintenance Station. The project encompasses concrete rehabilitation, building siding and roofing panel replacement, HVAC ducting installation, and other related repairs at the facility located in Clackamas County (BOLI Region #2). The contract is structured with three base bid items covering work at the fuel station, sand shed, and maintenance building, plus one add alternate item for additional maintenance building work. The substantial completion date is December 20, 2026, with final completion required by December 10, 2027. ODOT's authorized representative is Jorge Ojeda (971.429.4075; jorge.ojeda@odot.oregon.gov).

The contract price is to be determined based on competitive quotes submitted by offerors. Liquidated damages are assessed at $500 per calendar day for each day beyond the substantial completion date. The contractor must provide performance and payment bonds each equal to the contract price and maintain commercial general liability insurance of $1,000,000 per occurrence/$2,000,000 annual aggregate, plus commercial automobile liability insurance of $1,000,000 per occurrence. The work is subject to Oregon prevailing wage rates and apprenticeship requirements effective September 3, 2026. Retainage is limited to 5 percent of progress payments and shall be withheld and released in accordance with ORS 279C.550 to 279C.580. The contractor must be licensed by the Construction Contractors Board or State Landscape Contractors Board before commencing work and must comply with discrimination prohibitions, wage equality requirements, and the Oregon False Claims Act. All subcontractors must maintain appropriate licensing and insurance coverage.

View the file

Other files

File Type Posted
00018009_Mandatory Pre-Bid Conference Sign-In Sheet.pdf PDF
Exhibit 5 - Statement of Work.doc DOC document
Exhibit 6 - Drawings (For Reference Only)~1.pdf PDF
00018009_RFCQ.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT B

SAMPLE PUBLIC IMPROVEMENT CONTRACT

OFFEROR INSTRUCTIONS: Do not submit this document with your Quote. If you are the successful Offeror, Owner will fill in the blanks within this form and request your signature, which will represent your agreement to enter into a contract. PLEASE NOTE: There are some terms in this document that you will be agreeing to should you be awarded a contract; for instance, completion dates and liquidated damages. Please make sure you have read and understand this document before you submit a Quote.

STATE OF OREGON PUBLIC IMPROVEMENT CONTRACT

for ESB - ODOT Government Camp Maintenance Station Miscellaneous Facility Repairs

Contract Number: PO-73000-00000000

Resulting from Request for Competitive Quotes No. S-73000-00018009

This Public Improvement Contract for ESB - ODOT Government Camp Maintenance Station Miscellaneous Facility Repairs (the "Contract"), made by and between the State of Oregon, acting by and through the Department of Transportation, hereinafter called Owner, and [insert contractor] hereinafter called Contractor (collectively the “Parties”), is effective on the date this Contract has been signed by all the Parties and all required State of Oregon governmental approvals have been obtained. Unless otherwise defined in the Request for Competitive Quotes (“RFCQ”) or in this Contract, the capitalized terms used herein are defined in Section A.1 of the State of Oregon General Conditions for Public Improvement Contracts.

1. Contract Price Contractor, in consideration of the sum of $[XX] (the “Contract Price”), to be paid to Contractor by Owner in the manner and at the time hereinafter provided, and subject to the terms and conditions provided for in the RFCQ, this Public Improvement Contract and other Contract Documents, all of which are incorporated herein by reference, hereby agrees to perform all Work described and reasonably inferred from the Contract Documents.

The Contract Price includes all items listed in the table below. All Work described in the Contract Documents but not specifically itemized in the table below is considered incidental to the Work, and Contractor agrees to furnish all necessary labor, equipment, accessories, materials, and permits, and perform all other incidental Work at no additional cost to Owner.

Item
Description
Est. Qty.
Unit

Price Total Price

1
Base bid item #1: Complete all work at the fuel station, described in the Outline of Work in the Exhibit 1 - Statement of Work, scope item A.
2
Base bid item #2: Complete all work at the sand shed, described in the Outline of Work in the Exhibit 1 - Statement of Work, scope item B through E.
3
Base bid item #3: Complete all work at the maintenance building, described in the Outline of Work in the Exhibit 1 - Statement of Work, scope item F.
4
Add Alt #1: Complete all work at the maintenance building, described in the Outline of Work in the Exhibit 1 - Statement of Work, scope item G.

2. Representatives Unless otherwise specified in the Contract Documents, the following individuals are named as the authorized representatives in the administration of this Contract. Owner’s Authorized Representative shall be the initial point of contact for matters relating to performance, payment, and authorization, and to carry out the responsibilities of Owner. Contractor’s authorized representative is authorized to act on its behalf.

Owner’s Contract Administrator:

Jorge Ojeda 3700 SE 92nd Avenue Portland, OR 97266 971.429.4075 jorge.ojeda@odot.oregon.gov

Contractor’s Contract Administrator:

Name Address City/State/Zip Phone Email

3. Contract Dates

SUBSTANTIAL COMPLETION:December 20, 2026
FINAL COMPLETION:December 10, 2027

4. Liquidated Damages Failure to complete the Project known as ESB – ODOT Government Camp Maintenance Station(“MS”) Miscellaneous Facility Repairs by the specified time will result in damage to the State of Oregon. Since actual damage will be difficult to determine, it is agreed that Contractor shall pay to the State of Oregon, not as a penalty but as liquidated damages, $500.00 per calendar day for each day elapsed in excess of the Substantial Completion date stated in Section 3 of this Contract.

5. Exhibits The following exhibits are incorporated into this Contract by this reference. Contractor must utilize and comply with these documents and requirements in its performance of this Contract. The versions of the exhibits set forth herein replace any versions included in or as attachments to the RFCQ.

EXHIBIT 1 RESERVED

EXHIBIT 2 RESERVED

EXHIBIT 3 RESERVED

EXHIBIT 4 STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS, SUPPLEMENTAL GENERAL CONDITIONS, CONTRACT CLOSEOUT COMPLIANCE CHECKLIST

EXHIBIT 5 STATEMENT OF WORK: Project Overview September 14, 2026 ESB - ODOT Government Camp MS Misc. Facility Repairs Specifications are available as separate upload on OregonBuys on the attachments tab for this Contract

EXHIBIT 6 PLANS: AS-BUILT DRAWING SET Plans are available as separate upload on OregonBuys on the attachments tab for this Contract

6. Prevailing Wage Rates This Contract is subject to the Oregon Bureau of Labor and Industries (“BOLI”) prevailing wage rates and apprenticeship rates (and any applicable amendments) in effect as of the date the Project was first advertised, which while not physically attached, are available in the following publications at the website listed below and incorporated herein by reference with the same force and effect as though fully set forth herein:

BOLI Prevailing Wage Rates for Public Works Contracts dated September 3, 2026

PWR Apprenticeship Rates effective September 3, 2026

These BOLI wage rates are available at: https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx.

The work will take place in Clackamas, BOLI Region #2.

7. Certifications

a. Reserved

b. Discrimination in Subcontracting Prohibited (ORS 279A.110). Contractor certifies that it has not discriminated and will not discriminate against any disadvantaged business enterprise, minority-owned business, women-owned business, emerging small business, or business that a veteran owns, in obtaining any required subcontracts. Failure to do so shall be grounds for disqualification.

c. Debt. Contractor certifies that Contractor has no undisclosed liquidated and delinquent debt owed to the State or any department or agency of the State.

d. Subcontracts. Contractor certifies that all Subcontractors performing Work subject to the licensing requirement in ORS Chapter 701 will be licensed with the Construction Contractors Board or licensed by the State Landscape Contractors Board (as applicable) before the Subcontractors commence Work under the Contract.

e. Contractor certifies that it is certified by the State of Oregon as an “Emerging Small Business” per the guidelines of the Certification Office for Business Inclusion and Diversity (“COBID”), that it will comply with all requirements of the Emerging Small Business Assistance Program under Oregon Revised Statute (ORS) 200.160 through ORS 200.200, and that it will perform at least 51 percent of the labor for the Work using Contractor's own workforce.

f. Use of Premises. Contractor certifies that each Contractor and subcontractor employee will comply with the prohibition on aerosolizing, smoking or vaporizing when performing Work under the Contract on Owner’s project premises per ORS 433.845.

8. Integration THE CONTRACT, WHICH INCLUDES THIS CONTRACT AND THE REMAINING CONTRACT DOCUMENTS, CONSTITUTES THE ENTIRE CONTRACT BETWEEN THE PARTIES. NO WAIVER, CONSENT, MODIFICATION, OR CHANGE OF TERMS OF THE CONTRACT SHALL BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT, MODIFICATION OR CHANGE, IF MADE, SHALL BE EFFECTIVE ONLY IN THE SPECIFIC INSTANCE AND FOR THE SPECIFIC PURPOSE GIVEN. THERE ARE NO OTHER UNDERSTANDINGS, AGREEMENTS, OR REPRESENTATIONS, ORAL OR WRITTEN, NOT SPECIFIED HEREIN REGARDING THE CONTRACT. CONTRACTOR, BY THE SIGNATURE BELOW OF ITS AUTHORIZED REPRESENTATIVE, HEREBY ACKNOWLEDGES THAT IT HAS READ THIS CONTRACT AND THE REST OF THE CONTRACT DOCUMENTS, UNDERSTANDS THEM, AND AGREES TO BE BOUND BY THE TERMS AND CONDITIONS OF THIS CONTRACT AND THE REMAINING CONTRACT DOCUMENTS.

Agreed to and Signed by:

CONTRACTOR:

[Insert business name] (Legal Business Name)

[Insert address] (Address)

[Insert CCB#][Insert expiration date]
(CCB#)(Expiration Date)
[Insert ESB#][Insert expiration date]
(ESB#)(Expiration Date)

(Authorized Representative Name) (Title)

(Authorized Representative Signature) (Date)

STATE OF OREGON

State of Oregon by and through its Department of Transportation

Procurement Authority:

(Authorized Representative Name) (Title)

(Authorized Representative Signature) (Date)

Expenditure Authority:

Kristen LaLondeFacilities Construction Program Manager
(Authorized Representative Name)(Title)

Expenditure Authority received via OregonBuys on 9/14/2026 (Authorized Representative Signature) (Date)

EXHIBIT 1 RESERVED

EXHIBIT 2 RESERVED

EXHIBIT 3 RESERVED

EXHIBIT 4

STATE OF OREGON GENERAL CONDITIONS, SUPPLEMENTAL GENERAL CONDITIONS, CONTRACT CLOSEOUT COMPLIANCE CHECKLIST

The STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS (“General Conditions”) dated January 1, 2012, which although not physically attached, are incorporated herein by reference with the same force and effect as though fully set forth herein. The General Conditions can be obtained on line at: http://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

Supplemental General Conditions

The following supplemental general conditions modify the General Conditions. Where a portion of the General Conditions is modified or deleted by these Supplemental General Conditions, the unaltered portions of the General Conditions shall remain in effect.

SGC-1 In Sections A.1 and A.3.1, change “State of Oregon Public Improvement Agreement Form” to “State of Oregon Public Improvement Contract.”

SGC-2 Delete the order of precedence list in Section A.3.1 and replace it with the following descending order of precedence list:

1. Contract amendments and Change Orders, with those of later date having precedence over those of an earlier date;

2. The State of Oregon Public Improvement Contract;

3. The Supplemental General Conditions;

4. The General Conditions

5. The Plans and Specifications;

6. The Solicitation Document and any addenda thereto;

7. The accepted Offer.

SGC-3 Add the following new Sections A.3.5 and A.3.6 after A.3.4 under INTERPRETATION OF CONTRACT DOCUMENTS:

A.3.5 Items not indicated in the Plans and Specifications that can be legitimately and reasonably inferred to complete the Work must be furnished by Contractor as though they were detailed in the Plans and Specifications.

A.3.6 The characterization of provisions of the Contract as material provisions or the failure to comply with certain provisions as a material breach of the Contract shall in no way be construed to mean that any other provisions of the Contract are not material or that failure to comply with any other provisions is not a material breach of the Contract.

A.3.7 Electronic Signatures. Contractor and Owner agree that signatures showing on PDF documents, including but not limited to PDF copies of the Contract, bonds, Change Orders and amendments, submitted or received via email, when submittal or receipt in that manner is required or allowed by Owner are “Electronic Signatures” under ORS Chapter 84 and bind the signing party and are intended to be and can be relied upon by the parties. Owner reserves the right at any time to require Contractor to deliver the hard copy originals of any documents.

SGC-4 Add the following after Section A.7 GOVERNMENT EMPLOYMENT STATUS:

A.8 TITLE VI NON-DISCRIMINATION PROVISIONS

During the performance of the Contract, Contractor, for itself, its assignees, and its successors in interest (hereinafter referred to as the “Contractor”) agrees as follows:

a. Compliance with Regulations: Contractor shall comply with the regulations relative to nondiscrimination in federally-assisted programs of the Department of Transportation Title 49, Code of Federal Regulations, Part 21, as they may be amended from time to time, (hereinafter referred to as the Regulations), which are herein incorporated by reference and made a part of the Contract.

b. Nondiscrimination: Contractor, with regard to the Work performed by it during the Contract, shall not discriminate on the grounds of race, color, sex, or national origin in the selection and retention of Subcontractors, including procurements of materials and leases of equipment. Contractor shall not participate either directly or indirectly in the discrimination prohibited by section 21.5 of the Regulations, including employment practices when the Contract covers a program set forth in Appendix B of the Regulations.

c. Solicitations for Subcontracts, Including Procurements of Materials and Equipment: In all solicitations either by competitive bidding or negotiation made by Contractor for work to be performed under a subcontract, including procurements of materials or leases of equipment, each potential Subcontractor or supplier shall be notified by Contractor of Contractor’s obligations under the Contract and the Regulations relative to nondiscrimination on the grounds of race, color, sex, or national origin.

d. Information and Reports: Contractor shall provide all information and reports required by the Regulations, or directives issued pursuant thereto, and shall permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by ODOT, FHWA or the Federal Transit Administration (“FTA”) as appropriate, to be pertinent to ascertain compliance with such Regulations, orders and instructions. Where any information required of Contractor is in the exclusive possession of another who fails or refuses to furnish this information, Contractor shall so certify to ODOT, FHWA or FTA as appropriate, and shall set forth what efforts it has made to obtain the information.

e. Sanctions for Noncompliance: In the event of Contractor’s noncompliance with the nondiscrimination provisions of the Contract, ODOT shall impose such Contract sanctions as ODOT, FHWA or FTA may determine to be appropriate, including, but not limited to:

(i) Withholding of payments to Contractor under the Contract until Contractor complies, and/or

(ii) Cancellation, termination or suspension of the Contract, in whole or in part.

f. Incorporation of Provisions: Contractor shall include the provisions of paragraphs (a) through (e) in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Regulations, or directives issued pursuant thereto. Contractor shall take such action with respect to any subcontract or procurement as ODOT of the federal government may direct as a means of enforcing such provisions including sanctions for non-compliance: Provided, however, that, in the event Contractor becomes involved in, or is threatened with, litigation with a Subcontractor or supplier as a result of such direction, Contractor may request ODOT, and, in addition, Contractor may request the United States to enter into such litigation to protect the interests of the United States.

SGC-5 Make the following revisions to Section B.5 COMPLIANCE WITH GOVERNMENT LAWS AND REGULATIONS:

· Add the following to the end of Section B.5.1:

As required by ORS 279C.520, Contractor must comply with the prohibitions set forth in ORS 652.220, and shall not discriminate against any of Contractor’s employees in the payment of wages or other compensation for work of comparable character, the performance of which requires comparable skills, or pay any employee at a rate less than another for comparable work, based on an employee’s membership in a “protected class.” For purposes of this provision, a “protected class” means a group of persons distinguished by race, color, religion, sex, sexual orientation, gender identity, national origin, marital status, veteran status, disability or age. Contractor’s failure to comply with these requirements is a breach of the Contract that entitles Owner to terminate the Contract for cause.

Compliance with ORS 279C.520 includes, but is not limited to, not prohibiting employees from discussing wages, salaries, benefits and other compensation, and compliance with the wage related prohibitions in ORS 652.220. Compliance with ORS 279C.520 and ORS 652.220 is a material element of the Contract, and Contractor’s failure to comply is a breach of the Contract that entitles Owner to terminate the Contract for cause.

All rights and remedies available to Owner under applicable federal, state and local laws are also incorporated by reference herein and are cumulative with all rights and remedies under the Contract.

· Section B.5.2(a) is deleted and replaced with the following:

(a) Pursuant to ORS 279A.110, Contractor shall not discriminate against a disadvantaged business enterprise, a minority-owned business, a woman-owned business, a veteran-owned business or an emerging small business, in the awarding of subcontracts.

· The following Section B.5.2(c) is added:

(c) Respecting certification as a disadvantaged business enterprise, minority-owned business, woman-owned business, business that a veteran-owned business or an emerging small business under ORS 200.055, as and when applicable, Contactor shall maintain the certification, and require in its subcontracts that Subcontractors maintain the certification required by ORS 279A.107. Owner may require Contractor to terminate a subcontract with a Subcontractor that fails to maintain its certification under ORS 200.055 throughout the term of the subcontract and any extensions.

· The following Section B.5.2(d) is added:

(d) It is a material term of the Contract that Contractor certifies by entering into the Contract that Contractor has a written policy and practice that meets the requirements described in ORS 279A.112 for preventing sexual harassment, sexual assault and discrimination against employees who are members of a protected class and that Contractor shall maintain the policy and practice in force during the entire term of the Contract

· Section B.5.6 is deleted and replaced with the following revised Section B.5.6 B.5.6 Contractor shall comply with all Oregon tax laws, consistent with Contractor’s certification of compliance with tax laws and Contractor’s warranty that Contractor has complied with the Oregon tax laws. Any violation of Contractor’s certification of compliance or warranty will constitute a material breach of the Contract.

· The following Section B.5.7 is added:

B.5.8 Failure to comply with any or all of the requirements of B.5.1 through B.5.6 shall be a material breach of Contract entitling Owner to pursue and recover any and all of its available remedies at law or in equity that arise from the breach, including, but not limited to, recovery of damages, the termination of the Contract, and the exercise of the right of setoff, garnishment if applicable and the withholding of amounts otherwise due and owing to Contractor without penalty. Damages or costs resulting from such non-compliance shall be the responsibility of Contractor.

SGC-6 The provisions in Section B.15 GOVERNING LAW are deleted and replaced with the following provisions:

This RFCQ and the resulting Contract shall be governed by, construed, and enforced in accordance with the laws of State of Oregon without regard to principles of conflicts of law.

SGC-7 Add the following section after Section D.3 CLAIMS REVIEW PROCESS:

D.4 FALSE CLAIMS (OREGON FALSE CLAIMS ACT)

D.4.1 Contractor understands and acknowledges it is subject to the Oregon False Claims Act (ORS 180.750 to 180.785) and to any liabilities or penalties associated with the making of a false claim under that Act. By its execution of the Contract, Contractor certifies the truthfulness, completeness, and accuracy of any statement or claim it has made, it makes, it may make, or cause to be made that pertains to the Contract or the Project for which the services are being performed, including but not limited to Contractor’s statement of proposal and any invoices, reports, or other deliverables.

D.4.2Contractor shall immediately disclose (in Writing) to Owner whenever, in connection with the award, performance or closeout of the Contract, or any subcontract thereunder, Contractor has credible evidence that a principal, employee, agent, or Subcontractor of Contractor has committed:
(i)A violation of the Oregon False Claims Act; or;
(ii)A violation of State or Federal criminal or civil law involving fraud, conflict of interest, bribery, gratuity or similar misconduct.

D.4.3 Contractor must include subsections D.4.1 and D.4.2 of this section in each subcontract Contractor may award in connection with the performance of the Contract. In doing so, Contractor may not modify the terms of those subsections, except to identify the Subcontractors or sub grantee that will be subject to those provisions.

SGC-8 Make the following revisions to Section E.2.4, related to Owner’s right to withhold payment:

· A new subsection is added to Section E.2.4 as subsection (i) and existing subsections (g) and (h) of Section E.2.4 are revised to read as follows:

(g) failure to carry out the Work in accordance with the Contract Documents;

(h) assessment of liquidated damages, when withholding is made for offset purposes; or

(i) Contractor having liquidated and delinquent debt owed to the State of Oregon or any department or agency of the State of Oregon.

SGC-9 Delete Section E.5 RETAINAGE in its entirety and replace with the following:

E.5 RETAINAGE

E.5.1 Retainage, if withheld, shall be withheld and released in accordance with ORS 279C.550 to 279C.580.

E.5.1.1 Owner reserves the right in its sole discretion to withhold or to not withhold retainage from progress payments or to begin withholding retainage at any time. If Owner withholds retainage from progress payments the amount to be retained will not exceed 5% of the payment. Upon written application by Contractor, including written approval of Contractor's surety, Owner may reduce the amount of the retainage and may eliminate retainage on any remaining progress payments after 50% of the Work under the Contract is completed if, in Owner's opinion, such Work is progressing satisfactorily. Upon receipt of written application by Contractor, Owner shall respond in Writing within a reasonable time. When the Work is 97.5% completed, Owner may, at its discretion and without application by Contractor, reduce the retained amount to 100% of the value of the Work remaining to be done.

E.5.1.2 If retainage is withheld and Contractor elects Owner shall deposit the retainage, as the retainage accumulates, in an interest-bearing account, established through the State Treasurer, as provided under ORS 279C.560(5). Owner may recover from Contractor any additional costs incurred through such election by reducing Contractor's final payment.

E.5.1.3 In accordance with the provisions of ORS 279C.560 and any applicable administrative rules, Contractor may submit and Owner shall accept the following alternative forms of retainage, unless Owner rejects in Writing the bonds, securities, or other instruments that Contractor submits under paragraph (a) or a surety bond that Contractor submits under paragraph (b), below, for good case based on unique project circumstances:

(a) bonds, securities or other instruments of equal value deposited with Owner or in a bank or other financial institution to be held in lieu of the cash retainage for the benefit of Owner. Interest or earnings on the bonds, securities or other instruments shall accrue to Contractor. To be permissible the bonds, securities and other instruments must be of a character approved by the Director of the Oregon Department of Administrative Services, including but not limited to:

(i) Bills, certificates, notes or bonds of the United States.

(ii) Other obligations of the United States or agencies of the United States.

(iii) Obligations of a corporation wholly owned by the federal government.

(iv) Indebtedness of the Federal National Mortgage Association.

(v) General obligation bonds of the State of Oregon or a political subdivision of the State of Oregon.

(vi) Irrevocable letters of credit issued by an insured institution, as defined in ORS 706.008; or

(b) a surety bond for the benefit of Owner, for all or a portion of funds retained, or to be retained, by Owner in substantially the form specified in ORS 701.435(4) (See ORS 279C.560(7); House Bill 4006, 82nd Oregon Legislative Assembly (2024)). A surety bond submitted under this paragraph must be executed by a surety bonding company that is authorized to transact surety business in this state and may not be a surety obligation of an individual. Such bond and any proceeds therefrom shall be made subject to all claims and liens in the manner and priority as set forth for retainage under ORS 279C.550 to ORS 279C.570 and ORS 279C.600 to ORS 279C.625. Owner shall reduce the moneys Owner holds as retainage in an amount equal to the value of the surety bond and pay the amount of the reduction to Contractor in accordance with ORS 279C.570 (House Bill 4006, 82nd Oregon Legislative Assembly (2024)).

E.5.1.3.1 Where Owner has accepted Contractor's election of option E.5.1.3 (a) or (b) above, Owner may recover from Contractor the additional costs incurred through such election by reducing Contractor's final payment.

E.5.1.3.2 Where Owner has agreed to Contractor's request to deposit a surety bond under option E.5.1.3 (b), Contractor shall accept surety bonds from Subcontractors and suppliers on the project from which Contractor has withheld retainage. At any time before final payment, a Subcontractor may submit a surety bond to Contractor and request that Contractor submit, in a manner provided under ORS 279C.560(7) (House Bill 4006, 82nd Oregon Legislative Assembly (2024)), a surety bond to Owner for the portion of Contractor’s retainage that pertains to the Subcontractor. When a Contractor at a Subcontractor’s request obtains and submits to Owner a surety bond under this subsection, Contractor may withhold from payments to the Subcontractor an amount equivalent to the portion of Contractor’s surety bond premium for which the Subcontractor is responsible. Contractor shall comply with all applicable requirements under ORS 279C.560(8), including subsection (b), regarding timely submission to Owner a surety bond after Subcontractor’s request, and subsection (e), regarding release of amounts held as retainage to Subcontractor after receipt of a surety bond (House Bill 4006, 82nd Oregon Legislative Assembly (2024)).

E.5.1.4 In accordance with the provisions of ORS 279C.560, if Owner accepts bonds, securities or other instruments deposited as provided in paragraph (a) of subsection E.5.1.3, Owner shall reduce the moneys held as retainage in an amount equal to the value of the bonds, securities and other instruments and pay the amount of the reduction to Contractor in accordance with ORS 279C.570.

E.5.1.5 The retainage held by Owner shall be included in and paid to Contractor as part of the final payment of the Contract Price. Owner shall pay to Contractor interest at the rate of 1.5% per month on the final payment due Contractor, interest to commence thirty (30) Days after the Work under the Contract has been completed and accepted and to run until the date Contractor shall notify Owner in Writing when Contractor considers the Work complete and Owner shall, within fifteen (15) Days after receiving the written notice, either accept the Work or notify Contractor of Work yet to be performed on the Contract. If Owner does not, within the time allowed, notify Contractor of Work yet to be performed to fulfill contractual obligations, the interest provided by this subsection shall commence to run thirty (30) Days after the end of the 15-Day period.

E.5.1.6 Contractor agrees that if Contractor elects to reserve retainage from any progress payment due to any Subcontractor or supplier, such retainage shall not exceed 5% of the payment, and such retainage withheld from Subcontractors and suppliers shall be subject to, and Contractor shall comply, with all applicable legal requirements, including but not limited to those in ORS Chapters 279C and 701.

E.5.2 As provided in Sections C.2.2 and C.2.3, additional withholding in the amount of 25% of amounts earned shall be withheld and released in accordance with ORS 279C.845(7) when Contractor fails to file certified statements as required by Section C.2.1.

SGC-10 Add the following at the end of Section E PAYMENTS:

E.7 REPORT OF SUBCONTRACTORS PAID: Following each payment to Contractor, including final payment and any progress payments, Contractor shall submit to Owner ODOT Form 734-2882, Paid Summary Report. Contractor shall complete and submit the form as specified in the form instructions, which are available online, along with the form at: http://www.oregon.gov/ODOT/Forms/2ODOT/2882.pdf

SGC-11 Add the following new sections at the end of Section F.2 PROTECTION OF WORKERS, PROPERTY AND THE PUBLIC:

F.2.7 Contractor shall comply with applicable State of Oregon Governor’s executive orders and Oregon Administrative Rules promulgated by the Department of Consumer and Business Services, Oregon Occupational Safety and Health Division. Additionally, Contractor shall regularly consult Oregon OSHA guidance publications regarding construction contractors and construction sites (found at https://osha.oregon.gov/pubs/Pages/index.aspx and utilize those resources and information to develop, update and enforce Contractor’s policies for safety planning and safety practices on the Project. Contractor shall also comply with all other federal, state and local government statutes, regulations, administrative rules, ordinances, executive orders, Owner policies and other laws/requirements applicable to the Project pertaining to workplace health and safety requirements.

F.2.8 UTILITIES AND UTILITY FACILITIES: Contractor shall be responsible for locating any and all public or private utilities or utility facilities on the Project site prior to commencement of site work, including all costs associated with obtaining such locates. This shall include both Public and Private Locating services.

This Project may be located within the Oregon Utility Notification Center area which is a notification system for notifying owners of utility facilities about Work being performed in the vicinity of their facilities. The utilities notification system telephone number is 811 (or 1 800 332 2344).

SGC-12 Add the following new sections to SECTION F: Job Site Conditions:

F.8 MATERIAL SALVAGE FOR DEMOLITION CONTRACTS: Pursuant to ORS 279C.510 Contractor and all Subcontractors involved in demolition work are required to salvage or recycle construction and demolition debris, if feasible and cost-effective.

F.9 ASBESTOS ABATEMENT LICENSING REQUIREMENTS: If the work under this Contract involves an asbestos abatement project, Contractor or Subcontractor must hold a license issued by the Department of Environmental Quality as required by ORS 468A.720. Contractor or Subcontractor carrying out an asbestos abatement project shall be responsible for the safe and proper handling and delivery of waste that includes asbestos-containing material to a landfill authorized to receive such waste.

SGC-13 Delete Section G.2.1 in its entirety and replace with the following:

G.2.1 Contractor shall furnish and maintain in effect at all times during the Contract Period, a performance bond in a sum equal to the Contract Price and a separate payment bond also in a sum equal to the Contract Price.

SGC-14 Delete Section G.3 INSURANCE in its entirety and replace with the following:

G.3 INSURANCE

G.3.1 Contractor: Contractor shall obtain the insurance specified below prior to the execution of the Contract. Contractor shall maintain the insurance in full force at Contractor’s expense throughout the duration of the Contract and all warranty periods that apply.

G.3.1.2 Subcontracting: If Contractor specifies prior to the execution of the Contract that a Subcontractor will satisfy an insurance requirement, that is permitted to be satisfied by a Subcontractor, Contractor shall obtain Owner approval of Subcontractor and Subcontractor’s insurance coverage(s), at least 35 Calendar Days prior to commencement of subcontracted work. After Contractor receives Owner approval of the Subcontractor, Contractor may contractually obligate the Subcontractor to obtain and maintain, at the Subcontractor's expense or at Contractor's expense, the insurance permitted.

G.3.1.3Contractor shall require that all Subcontractors carry insurance coverage that Contractor deems appropriate based on the risks of the subcontracted work. Contractor shall obtain proof of the required insurance coverages, as applicable, from any Subcontractor providing services related to the Contract.
G.3.1.4Neither the insurance provided by Subcontractor(s) nor any agreements Contractor or Subcontractor(s) may enter into shall place any limitation on the liability or indemnification obligations of Contractor under applicable law or the Contract.

G.3.1.5 Insurance Provisions: Contractor and Subcontractor(s), if any, shall obtain insurance from insurance companies or entities that are authorized to transact the business of insurance and issue coverage in the state of Oregon and that are acceptable to Owner. Insurance coverage shall be primary and noncontributory with any other insurance and self-insurance, with the exception of Workers’ Compensation/Employer’s Liability. Contractor, or appropriate Subcontractor, but not Owner, shall pay for all deductibles, self-insurance retentions and self-insurance, if any.

G.3.2 Workers' Compensation and Employer’s Liability:

G.3.2.1 All employers, including Contractor and Subcontractor(s), if any, that employ subject workers, as defined in ORS 656.027, shall comply with ORS 656.017 and shall provide Workers’ Compensation insurance coverage, unless such employers meet the requirement for an exemption under ORS 656.126(2). The coverage shall include Employer’s Liability insurance with coverage limits of not less than $500,000 for each accident. Contractors who perform the Work without the assistance or labor of any employee need not obtain such coverage if Contractor certifies so in Writing. Contractor shall ensure that each of its Subcontractors complies with these requirements. Contractor shall require proof of such Workers’ Compensation and Employer’s Liability by receiving and keeping on file a certificate of insurance from each Subcontractor or anyone else directly employed by either Contractor or its Subcontractors.

G.3.2.2 All employers, including Contractor and Subcontractor(s), if any, exempt under ORS 656.126(2) and subject to any other state’s Workers’ Compensation law, shall provide Workers’ Compensation insurance coverage as required by applicable Workers’ Compensation laws. The coverage shall also include Employer’s Liability insurance with limits not less than $500,000 each accident.

G.3.3 Liability Insurance:

G.3.3.1 Commercial General Liability: Contractor shall obtain, at Contractor's expense, and keep in effect during the term of this Contract, Commercial General Liability insurance written on an occurrence basis and covering bodily injury, property damage, personal and advertising injury, products and completed operations, and contractual liability.When Work to be performed includes operations or activity within 50 feet of any railroad property, bridge, trestle, track, roadbed, tunnel, underpass or crossing, Contractor shall provide the Contractual Liability – Railroads CG 24 17 endorsement, or equivalent, on the Commercial General Liability policy. Combined single limit per occurrence shall not be less than the dollar amount specified in the Contract. The annual aggregate limit shall not be less than the dollar amount specified in the Contract.
Per OccurrenceAnnual Aggregate
Commercial General Liability$1,000,000$2,000,000

G.3.3.2 Commercial Automobile Liability: Contractor shall obtain, at Contractor's expense, and keep in effect during the term of this Contract, Automobile Liability insurance covering owned, non-owned, and hired vehicles for bodily injury and property damage. Combined single limit per occurrence shall not be less than the dollar amount specified in the Contract.

Combined Single Limit

Per Occurrence
Commercial Automobile Liability$1,000,000

G.3.3.3 Extended Reporting: If any of the required liability insurance is permitted to be and is on a claims made basis, Contractor or Subcontractor who provided the insurance coverage, shall obtain an extended reporting period on the claims made policy or maintain the claims made policy for a duration of at least 24 months from the date the applicable work has been completed and accepted by Owner or the date of Final Completion. This extended reporting requirement shall be satisfied with documentation of one of the following:

oMaintaining the applicable continuous claims made policy with liability coverage;
oExtended Reporting Endorsement; or
oTail Coverage.

G.3.3.4 Excess/Umbrella Liability: A combination of primary and Excess/Umbrella Liability insurance may be used to meet the required limits of insurance. If any Excess/Umbrella Liability policies are in place, they must be provided on a true “following form” or broader coverage basis, with coverage at least as broad as provided on the underlying insurance. In addition, the limits of the underlying primary insurance must be sufficient to prevent any gap between such minimum limits and the attachment point of the coverage provided by the Excess/Umbrella Liability policy.

G.3.3.5 Additional Insured: The liability insurance coverages, except Professional Liability and Workers’ Compensation/Employer’s Liability, if included, shall include an Additional Insured Endorsement endorsing the “State of Oregon, the Oregon Transportation Commission, and the Oregon Department of Transportation, and their respective members, officers, agents, and employees” as Additional Insureds, but only with respect to Contractor's activities to be performed under this Contract. Coverage shall be primary and non-contributory with any other insurance and self-insurance. The liability coverages that are permitted by Owner to be obtained by an appropriate Subcontractor shall include all of the foregoing as Additional Insureds and shall also include Contractor and its officers and employees as Additional Insureds. Additional Insured Endorsements shall be submitted with the Certificate(s) of Insurance and must be acceptable to Owner.

G.3.3.6 Additional Insured – Commercial General Liability: Additional Insured Endorsements on the Commercial General Liability shall be written on ISO Form CG 20 10 07 04, or equivalent, with respect to liability arising out of ongoing operations and ISO Form CG 20 37 07 04, or equivalent, with respect to liability arising out of completed operations. Additional Insured Endorsements shall be submitted with the Certificate(s) of Insurance and must be acceptable to Owner.

G.3.3.7 Notice of Cancellation or Change: Contractor shall provide at least 30 Calendar Days written notice to Owner before cancellation of, material change to, potential exhaustion of aggregate limits, or non-renewal of the required insurance coverages. If a Subcontractor is providing insurance to meet the Contract requirements, Contractor shall provide at least 30 Calendar Days written notice to Owner before cancellation of, material change to, potential exhaustion of aggregate limits, or non-renewal of the required insurance coverage(s). Any failure to comply with the reporting provisions of this insurance shall not affect the coverage(s) provided to the State, Owner, County, City, or other applicable political jurisdiction or to Owner's governing body, board, or Commission and its members, and Owner's officers, agents, and employees.

G.3.3.8 Certificate(s) of Insurance: As evidence of the insurance coverages required by this Contract, Contractor shall furnish Certificate(s) of Insurance to Owner prior to execution of the Contract. As evidence of insurance coverages required by the Contract but permitted by Owner to be obtained by an appropriate Subcontractor, Contractor shall furnish Certificate(s) of Insurance to Owner for approval on such coverages at least 35 Calendar Days prior to commencement of subcontracted work. The Certificate(s) shall:

•List the “State of Oregon, the Oregon Transportation Commission, and the Oregon Department of Transportation, and their respective members, officers, agents and employees” as a Certificate Holder and endorse as an Additional Insured;
•Include all required endorsements or copies of the applicable policy language effecting coverage required by the Contract;
•Specify that all liability insurance coverages shall be primary and non-contributory with any other insurance and self-insurance, with exception of Professional Liability and Workers’ Compensation/Employer’s Liability; and
•Include a list of all policies that fall under the Excess/Umbrella Liability insurance if Excess/Umbrella Liability insurance is used to meet the minimum insurance requirement.

G.3.3.9 Owner Acceptance: All insurance and insurance providers are subject to Owner acceptance. In addition, all of the following are subject to Owner acceptance and, if requested by Owner, Contractor shall provide complete copies of the following to Owner’s representatives responsible for verification of the insurance coverages required by the Contract: insurance policies, endorsements, self-insurance documents and related insurance documents.

G.3.3.10 Insurance Requirement Review: Owner reserves the right to periodically access risks and the adequacy of insurance coverage and in its discretion to require additional insurance coverage or increased coverage limits on existing coverages, or both.

G.3.4 Builder’s Risk Insurance and Builder’s Risk Installation Floater (RESERVED – NOT REQUIRED FOR THIS PROJECT)

SGC-15 Section J.4, Owner’s Right to Terminate Contract:

· Delete subsection (f) of Section J.4.1 and replace with the following:

(f) If Contractor has liquidated and delinquent debt owed to the State of Oregon or any department or agency of the State of Oregon; or

· Add a new subsection (g) to Section J.4.1 to read as follows:

(g) If Contractor is otherwise in material breach of any part of the Contract.

SGC-16 Delete Section J.4, Owner’s Right to Terminate Contract in its entirety and replace with the following:

J.4.2 At any time that any of the above occurs, Owner may exercise all rights and remedies available to Owner at law or in equity, including, in the event of the conditions set forth in Section J.4.1(f) regarding Contractor’s liquidated and delinquent debt (including garnishing all monies due for any and all Work performed by Contractor, when appropriate) and otherwise recovering any liquidated and delinquent debt owed to the State of Oregon or any department or agency of the State of Oregon. In addition, Owner may take possession of the premises and of all materials and appliances and finish the Work by whatever method it may deem expedient. In such case, Contractor shall not be entitled to receive further payment until the Work is completed. If Owner's cost of finishing the Work exceeds the unpaid balance of the Contract Price, Contractor shall pay the difference to Owner.

SGC-17 Add the following Section J.4.3 to Section J.4 OWNER’S RIGHT TO TERMINATE CONTRACT:

If a termination under this Section J.4 is determined by a court of competent jurisdiction to be unjustified, the termination shall be deemed a termination for convenience. (See Section J.5 TERMINATION FOR CONVENIENCE.)

SGC-18 Add the following at the beginning of SECTION K CONTRACT CLOSEOUT:

As a condition of final payment, Contractor shall complete and sign the Contract Closeout Checklist form provided by Owner. If accepted by Owner, Contractor’s delivery of the certification as required in K.3 of the Checklist will be deemed to be compliance with the requirements of Section K.3 below and Contractor’s delivery of the information required in K.7 of the Checklist will be deemed to be compliance with the requirements of Section K.7 below.

SGC-19 Delete Section K.4 except for the title and replace it with the following:

K.4.1 Contractor shall provide Owner’s Authorized Representative a written request for notice of Substantial Completion. The request must state the date Contractor substantially completed the Project and include a Punchlist of any items that need to be completed or corrected. Upon receipt of the request for notice of Substantial Completion, Owner’s Authorized Representative will perform a final Project inspection. If Owner’s Authorized Representative finds that the project is substantially complete, a notice of Substantial Completion will be issued by Owner’s Authorized Representative which will include the final Project Punchlist. Once all Punchlist items have been completed to the satisfaction of Owner’s Authorized Representative, Owner’s Authorized Representative will provide Contractor with a Contract Closeout Checklist form. Contractor shall complete and sign the form and submit it to Owner’s Authorized Representative. Owner’s Authorized Representative will provide the final signature on the form upon which date Final Completion shall take effect.

K.4.2 Substantial Completion of a facility with operating systems (e.g., mechanical, electrical, HVAC) shall be that degree of completion that has provided a minimum of 30 continuous Days of successful, trouble-free operation, which period shall begin after all performance and acceptance testing has been successfully demonstrated to Owner's Authorized Representative. All equipment contained in the Work, plus all other components necessary to enable Owner to operate the facility in the manner that was intended, shall be complete on the Substantial Completion date.

Contract Closeout Compliance Checklist

Contract Number

Contract Name

Contractor

Owner’s Authorized Rep.

This checklist is intended to assist Owner and Contractor in complying with the Contract Closeout and Final Payment requirements in the General Conditions for Public Improvement Contracts, Sections K and E.6.

Owner will mark “NA” by any requirement that is not applicable to the Contract. Contractor’s and Owner’s Authorized Representatives shall place their initials by each requirement listed below that has not been marked “NA” by Owner, and provide a signature at the end of the checklist.

A copy of this signed checklist must be retained in the contract administration file.

Requirements
Mark NA if not applicable
Date completed
Contractor initials
Owner

initials

K.1 Record Documents submitted

K.2 O & M Manuals submitted

K.3 Certification/Release of Claims

By Contractor’s Signature below, Contractor certifies and agrees to the following:

All Subcontractors and suppliers have been paid in full or will be paid in full out of the final payment, and in compliance with all prompt payment requirements. All disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid, and, to the best of Contractor's knowledge, there are no claims of any kind outstanding against the project.

K.4 Completion notices

Request for notice of Substantial Completion submitted:

Date of substantial completion:

Date of final completion:

K.5 Training sessions scheduled

K.6 Extra materials provided (List individually):

K.7. Environmental Clean-up:

Contractor hereby notifies Owner that all environmental cleanup that was performed as a part of this contract has been disposed of in accordance with all applicable rules, regulations, laws, and statutes of all agencies having jurisdiction over such environmental pollution.

K.8 Certificate of Occupancy received by Owner

K.9 Other Contractor Responsibilities (List individually):

E.6 Contractor’s final payment request submitted

Final payment request approved by Owner

CONTRACTOR’S AUTHORIZED REPRESENTATIVE:

Printed Name Title

Signature Date

OWNER’S AUTHORIZED REPRESENTATIVE:

Printed Name Title

Signature Date

EXHIBIT 5

STATEMENT OF WORK

Project Overview ESB - ODOT Government Camp MS Misc. Facility Repairs Specifications

The above Specifications are incorporated herein and are found as separate upload on OregonBuys for this Project. Should any of the Specifications conflict with the General Conditions, as modified by the Supplemental General Conditions, the General Conditions shall prevail.

EXHIBIT 6

AS-BUILT DRAWING SET PLANS

The above Plans are incorporated herein and are available as separate upload on OregonBuys for this Project.

Contract Number – [00000000] ESB - ODOT Government Camp MS Misc. Facility Repairs 2