Exhibit 2 Deliverable Schedule.pdf

PDF 170 KB Posted

Attached to
Structural Health Monitoring (SHM) Current Practice and Web Manual
Solicitation number
693JJ320R000023
Issued by

About this file

This document outlines deliverables and submission requirements for a federal contract to develop a Structural Health Monitoring Web Manual. Key deliverables include draft and final reports on current SHM practices, an ROI tool, workshop plans and reports, draft and final components of the SHM Web Manual, a draft and final technical brief, and a webinar. Deliverables must meet Section 508 accessibility standards and are to be submitted electronically in Word or software format to the Contracting Officer's Representative according to the schedule, which spans from one to thirty months from the effective contract date. The related federal contract opportunity is a solicitation issued by the Department of Transportation Federal Highway Administration seeking proposals for the contract, with a response due date of July 23, 0900 EDT, to investigate current SHM practices and policies and develop the comprehensive SHM Web Manual.

View the file

Other files

File Type Posted
QandA_SHM_07.14.2020.pdf PDF
693JJ320R000023_0001.pdf PDF
QandA_SHM_07.10.2020.pdf PDF
Exhibit 1_Peformance Requirements Summary.pdf PDF
693JJ320R000023_SHM.pdf PDF
Attachment 1 QASP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 2

DELIVERABLES SCHEDULE

This technical exhibit lists any reports or documentation that is required as a deliverable to include the frequency, # of copies, medium/format and who/where it is to be submitted. A deliverable is anything that can be physically delivered but may include non-physical things such as meeting minutes.

Deliverables

508 Complaint Frequency # of Copies Medium/Format Submit to

Summary of Kickoff Meeting (3.5.1)

No Once within 1 month from effective date of the contract

1 Word file COR

Task 1 Draft Synthesis Report (1.3.1)

Yes Once within 6 months from effective date of the contract

Word file

COR

Task 2 Draft Report (1.3.2)

Yes Once within 12 months from effective date of

Word

ROI Tool (1.3.2)

Yes Once within 12 months from effective date of

Software Code

Task 3 Draft Report (1.3.3)

Yes Once within 14 months weeks from effective date of the contract

Task 4 Draft Report (1.3.4)

Yes Once within 16 months from effective date of

SHM Draft Two-day Workshop Plan (1.3.5)

Yes Once within 16 months from effective date of the contract

1 Word COR

SHM Final Two-day Workshop Plan (1.3.5)

Yes Once, 15 days prior to scheduled SHM Two-day Workshop

SHM Two-day Workshop (1.3.5)

Yes Once within 17 months from effective date of

Workshop

Draft SHM Workshop Report (1.3.5)

Yes Once within months from effective date of

Word COR

Draft Component List for User Input and System Output Module of the SHM Web Manual (1.3.6 Task 6a)

Yes Once within 19 months from effective date of

Draft SHM Web Manual Document for each Component (1.3.6 Task 6b)

Yes Once within 24 months from effective date of

Final component list for user input and system output module of the SHM Web Manual (Task 6a)

Yes Once within 26 months from effective date of

Final SHM Web Manual Document for each Component (1.3.6 Task 6b)

Yes Once within 2 weeks final comments on Draft SHM Web Manual Document

Draft Final Report (1.3.7)

Yes Once within 28 months from effective date of

Draft TechBrief (1.3.7)

Yes Once within 28 months from effective date of the contract

1 Word COR

Final Report (1.3.7)

Yes Once within 30 months from effective date of

Final Technical Brief

Yes Once within 30 months from effective date of

A Webinar

Yes Once within 30 months from effective date of

1 PPT COR