Exhibit 1 Specifications.pdf
PDF 435 KB Posted
- Solicitation number
- S-73000-00012958
- Issued by
- Douglas County, Canyonville City, Oregon
About this file
This is a specifications document for the Canyonville Maintenance Station ESB Building 03 Remodel project located at 260 SE Elliott Ave in Canyonville, Oregon, managed by the Oregon Department of Transportation (ODOT). The project involves remodeling a 1983-era maintenance building, including window replacements, door removal, drywall installation, taping and texturing, priming and painting, flooring covering and base cove replacement, plumbing fixture replacements and other related items. The Transportation Maintenance Manager (TMM) Randy Camp is listed as the project contact. The document outlines detailed specifications across multiple divisions including general requirements, wood/plastics/composites, openings, finishes, and plumbing fixtures.
The specifications provide comprehensive technical requirements for materials and installation, including requirements for vinyl windows with specific thermal performance ratings, resinous flooring systems, gypsum board installation, painting standards, and commercial plumbing fixtures. Key operational parameters include construction operating hours limited to 7:00 AM to 5:00 PM Monday through Friday, requirements for contractor coordination with the TMM, and specifications for submittals and quality control. The document details product requirements across all aspects of the remodel, from rough carpentry to final finishes, with emphasis on compatibility between materials and systems.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1~16.docx | DOCX document | |
| Exhibit 2 - Scope of Work.pdf | ||
| 00012958 Preliminary Results.xlsx | XLSX spreadsheet | |
| Exhibit 3_Base Floor Plan~1.pdf | ||
| 00012958 Attachments.docx | DOCX document | |
| OregonBuys Registration Guide~14.pdf | ||
| Addendum 2 Resinous Flooring Specification Sheet.pdf | ||
| 00012958 ESB_RFCQ.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Canyonville Maintenance Station ESB Building 03 Remodel
260 SE Elliott Ave Canyonville, Oregon 97417
F4100603
Project Contact:
Randy Camp Transportation Maintenance Manager
541-957-3666
February 13, 2025
Table of Contents: 02/12/2028
Division
Section Title
Pages
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 01
GENERAL REQUIREMENTS
011000
SUMMARY
012500
SUBSTITUTION PROCEDURES
013100
PROJECT MANAGEMENT AND COORDINATION
013300
SUBMITTAL PROCEDURES
014000
QUALITY REQUIREMENTS
015000
TEMPORARY FACILITIES AND CONTROLS
016000
PRODUCT REQUIREMENTS
017300
EXECUTION
017419
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700
CLOSEOUT PROCEDURES
017839
PROJECT RECORD DOCUMENTS
DIVISION 06
WOOD, PLASTICS, AND COMPOSITES
061000
ROUGH CARPENTRY
062023
INTERIOR FINISH CARPENTRY
079200
JOINT SEALANTS
DIVISION 08
OPENINGS
085313
VINYL WINDOWS
DIVISION 09
FINISHES
092900
GYPSUM BOARD
096513
RESILIENT BASE AND ACCESSORIES
096723 RESINOUS FLOORING 3
09770 RESILIENT REINFORCED WALL PANELS 4
099124
INTERIOR PAINTING (MPI STANDARDS)
224200 COMMERCIAL PLUMBING FIXTURES 1
END OF TABLE OF CONTENTS
ESB Remodel Building 03 Project
SECTION 011000 -
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Time of commencement and completion.
4. Contractor's use of site and premises.
5. Excessive noise.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 PROJECT INFORMATION
A. Project Identification: Canyonville Maintenance Station. ESB Remodel Building 03.
1. Project Location: 260 South Elliott Street, Canyonville, Oregon
B. Owner: Oregon Department of Transportation, 3339 Old Highway 99, Roseburg, Oregon.
1. Owner's Representative: Randy Camp. Randy.Camp@odot.oregon.gov, phone
541.957.3666, Transportation Maintenance Manager (TMM).
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. The project consists of selective building remodel of a 1983 era Maintenance Building including window replacements, door removal, drywall, tap and texture, prime and paint, flooring covering and base cove replacement, plumbing fixture replacements and other mischievous items as indicated in the Contract Documents.
1.4 TIME OF COMMENCEMENT AND COMPLETION
A. Notice to proceed: A written notice to proceed will be provided by the Owner to the Contractor as indicated in the invitation to bid. The Contractor shall begin the work upon receipt of the notice to proceed. Notwithstanding any other provision of the contract the Owner shall not be obligated to accept or to pay for any work furnished by the Contractor prior to delivery of notice to proceed, whether or not the Owner has knowledge of the furnishing of work.
SECTION 011000 -
1.5 CONTRACTOR'S COPIES OF CONTRACT DOCUMENTS
A. Contractor shall be supplied electronically, with one PDF set of 11 x 17 drawings and specifications. At least one complete set of contract documents, including drawings and specifications shall be kept at the site of construction in good condition, and at all times available to the Transportation Maintenance Manager
1.6 PERMITS AND FEES
A. All required permits, and payment of all fees, inspection charges and other similar costs shall be the responsibility of the contractor.
1.7 RESERVE
1.8 CONTRACTOR'S USE OF SITE AND PREMISES
A. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated by the Transportation Maintenance Manager (TMM).
B. Construction Operating Hours: Operating hours shall be limited to 7:00 AM to 5:00 PM Monday through Friday. Deviations from noted hours shall be with approval by TMM.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction upgrades and repairs. Damage caused by construction operations will be the responsibility of the General Contractor.
1.9 EXCESSIVE NOISE
A. All equipment shall have muffling devices in good working order at all times. Equipment not so equipped will be removed from site.
B. Cooperate with Owner in locating high noise producing equipment in areas least offensive and/or provide sound enclosure or shielding to dampen sound.
1.10 COORDINATION WITH OCCUPANTS
A. Owner will remove all items from the 3 rooms listed on the drawings prior to the start of the project.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SECTION 012500 -
SUBSTITUTION
PROCEDURES
SECTION 012500 - SUBSTITUTION PROCEDURES
1.1 Substitution Requests.
A. Substitution requests shall be made only by the General Contractor
B. Substitution Requests shall be submitted to the Procurement and Contract Specialist (PCS).
C. Substitution requests shall be allowed only during bidding process.
D. Substitution requests shall be submitted to the PCS a minimum of seven days prior to bid closing date.
E. PCS will request additional information or acceptance or rejection within two days.
F. Documentation:
1. Justification.
2. Coordination information.
3. Detailed comparison.
4. Product Data.
5. Samples.
6. Certificates and qualification data.
7. List of similar installations.
8. Material test reports.
9. Research reports.
10. Detailed comparison of Contractor's construction schedule.
11. Cost information.
12. Contractor's certification.
1.2 SUBSTITUTIONS
A. Substitutions for Convenience: Not allowed.
END OF SECTION 012500
ESB Building 03 Remodel
SECTION 013100 - PROJECT
MANAGEMENT AND
COORDINATION
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Description
2. General coordination procedures.
3. Coordination drawings.
4. Requests for Information (RFI's).
5. Project meetings.
1.2 DESCRIPTION
A. The Contractor shall coordinate with the TMM during the duration of the project.
1. The Contractor will be responsible for keeping the TMM informed of all activity throughout the project identified in this Contract.
1.3 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
SECTION 013100 - PROJECT
7. Project closeout activities.
8. Startup and adjustment of systems.
1.4 QUALITY ASSURANCE
A. Throughout the progress of the work, the General Contractor shall provide all necessary personnel thoroughly familiar with the Specifications and Drawings, completely trained and experienced in the necessary skills, who shall be present at the site and direct all work performed.
B. Covering Up: No General Contractor or Subcontractor shall cover up work or conceal work until it has been inspected and/or approved.
1.5 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop
Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1.6 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. TMM will return without response those RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Owner name.
2. Owner's Project number.
3. Project Name
4. Name of Construction Project Manager.
5. ODOT Project number.
6. Date.
7. Name of Contractor.
8. RFI number, numbered sequentially.
9. RFI subject.
10. Specification Section number and title and related paragraphs, as appropriate.
11. Drawing number and detail references, as appropriate.
12. Field dimensions and conditions, as appropriate.
SECTION 013100 - PROJECT
13. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract
Time or the Contract Sum, Contractor shall state schedule and cost impact in the RFI.
14. Contractor's signature.
15. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. RFI Forms: Electronic format containing information as noted above. Software-generated form with substantially the same content as indicated above, acceptable to the TMM.
D. RFI's will be reviewed to determine action required, and response. Allow five days for response to each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of review actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. TMM's action may include a request for additional information, in which case time for response will date from time of receipt.
3. TMM's action on RFIs that may result in a change to the Contract Time or the Contract
Sum may be eligible for Contractor to submit Change Proposal in accordance with General
Provisions.
a. If Contractor believes the RFI response warrants change in the Contract Time or the
Contract Sum, notify TMM in writing within three days of receipt of the RFI response.
E. PDF Document Preparation: Where PDFs are required to be submitted, prepare as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.7 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
B. Preconstruction Meeting: A preconstruction meeting, before starting construction, at a time convenient to Owner and TMM, but no later than five business days following NTP.
SECTION 013100 - PROJECT
1. Attendees: Authorized representative TMM; Contractor and its superintendent; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Designation of key personnel and their duties.
d. Lines of communications.
e. Procedures for processing field decisions and Change Orders.
f. Procedures for RFIs.
g. Procedures for processing Applications for Payment.
h. Submittal procedures.
i. Preparation of Record Documents.
j. Use of the premises and existing building.
k. Work restrictions.
l. Working hours.
m. Owner's occupancy requirements.
n. Responsibility for temporary facilities and controls.
o. Construction waste management and recycling.
p. Parking availability.
q. Office, work, and storage areas.
r. Equipment deliveries and priorities.
s. First aid.
t. Contractor Safety Plan.
u. Security.
v. Progress cleaning.
3. Minutes: Contractor shall record and distribute meeting minutes.
C. Progress Meetings: Conduct progress meetings at weekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representative TMM and the General Contractor.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do
so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Sequence of operations.
2) Site use.
3) Progress cleaning.
4) Quality and work standards.
5) Status of correction of deficient items.
6) Field observations.
7) Status of RFIs.
SECTION 013100 - PROJECT
8) Status of Proposal Requests.
9) Pending changes.
10) Status of Change Orders.
11) Documentation of information for payment requests.
4. Minutes: Contractor shall record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
1.8 TERMS
A. "APPROVED" as used herein means "approved by the ODOT Transportation Maintenance
Manager” (TMM).
B. 'FOR APPROVAL" means "for the Transportation Maintenance Managers (TMM) approval."
C. "SELECTED" means "selected by the Transportation Maintenance Manager (TMM)."
D. "PROVIDE" means "furnish and install."
E. Where words "or approved" ae used, Transportation Maintenance Manager (TMM) is sole judge of quality and suitability of proposed alternate or substitution.
F. TRANSPORTATION MAINTENANCE MANAGER (TMM)" refers to the individual selected by ODOT to manage the project.
G. "Project Coordination" refers to the on-site individual (if) selected by ODOT TMM to be the local liaison the contractor.
H. "INSTALL" means "furnish and install."
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
SECTION 013300 -
SECTION 013300 - SUBMITTAL PROCEDURES
1.1 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that requires responsive action. Action submittals are those submittals indicated in individual Specification Sections as
"action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require responsive action. Submittals may be rejected for not complying with requirements.
Informational submittals are those submittals indicated in individual Specification Sections as
"informational submittals."
1.3 SCHEDULE
A. The contractor shall provide the following schedules and submit them not later than 5 days after notice to proceed or as noted in the Bid Documents.
1. Contractors construction schedule.
2. Contractors list of subcontractors.
3. The Contractors schedule of submittals shall be based upon the Contractor's construction schedule so that the work can progress in accordance with the approve construction schedule..
4. Contractor's schedule of values.
1.4 SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by TMM and additional time for handling and reviewing submittals required by those corrections.
1.5 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Contractor.
4. Names of subcontractor, manufacturer, and supplier.
5. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier, and alphanumeric suffix for resubmittals.
6. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
7. Drawing number and detail references, as appropriate.
8. Indication of full or partial submittal.
9. Signature of transmitter.
B. Options: Identify options requiring selection by TMM.
C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by TMM on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
D. Submittals shall be electronic.
1.6 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Email: Prepare submittals as PDF package and transmit to TMM by sending via email.
Include PDF transmittal form. Include information in email subject line as requested by
TMM.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification
Section as separate packages under separate transmittals.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.
Time for review shall commence on receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 7 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contractor when a submittal being processed must be delayed for coordination.
2. Resubmittal Review: Allow 7 days for review of each resubmittal.
D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's action stamp.
1.7 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Mark each copy of each submittal to show which products and options are applicable.
2. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
B. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Permanently attach label on unexposed side of Samples that includes the following:
a. Project name and submittal number.
b. Generic description of Sample.
c. Product name and name of manufacturer.
d. Sample source.
e. Number and title of applicable Specification Section.
f. Specification paragraph number and generic name of each item.
3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.
4. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
1.8 CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.
Note corrections and field dimensions. Mark with approval stamp before submitting to TMM.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with contractors’ approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract
Documents.
1. TMM will not review submittals received from Contractor that do not have Contractor's review and approval.
1.9 ODOT REVIEW
A. Action Submittals: TMM will review each submittal, indicate corrections or revisions required.
1. PDF Submittals: TMM will indicate, via markup on each submittal, the appropriate action as follows:
a. Submittals will be returned marked Approved, Approved as Noted, Revise and
Resubmit. Incomplete submittals will be marked Rejected and not reviewed.
B. Informational Submittals: TMM will review each submittal and will not return it or will return it if it does not comply with requirements. TMM will forward each submittal to appropriate party.
C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from TMM.
D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
E. Submittals received from sources other than Contractor will be returned without review.
F. Submittals not required by the Contract Documents will be returned by TMM without action.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013300
SECTION 014000 - QUALITY
REQUIREMENTS
SECTION 014000 - QUALITY REQUIREMENTS
1.1 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.
1.2 DEFINITIONS
A. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations.
1. Use of trade-specific terminology in referring to a Work result does not require that certain construction activities specified apply exclusively to specific trade(s).
1.3 CONFLICTING REQUIREMENTS
A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements is specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, inform the TMM regarding the conflict and obtain clarification prior to proceeding with the Work. Refer conflicting requirements that are different, but apparently equal, to TMM for clarification before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified is the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to the TMM for a decision before proceeding.
1.4 INFORMATIONAL SUBMITTALS
A. Permits, Licenses, and Certificates: For Owner's record, submit copies to TMM of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
SECTION 014000 - QUALITY
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
END OF SECTION 014000
Shady Maintenance Station
ESB Building03 Remodel
SECTION 015000 -
TEMPORARY FACILITIES
AND CONTROLS
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
1.1 USE CHARGES
A. Water Service: Available from existing system without charge.
B. Electric Power Service: Available from existing system without charge.
1.2 INFORMATIONAL SUBMITTALS
A. Moisture-protection plan.
1.3 TEMPORARY FACILITIES
A. Provide sanitary facilities for all workers and inspectors.
1.4 EQUIPMENT
A. Fire extinguishers.
1.5 INSTALLATION, GENERAL
A. Isolation of work areas in occupied facilities.
1.6 TEMPORARY UTILITY INSTALLATION
A. Sanitary Facilities: Use of Owners sanitary facilities not permitted.
B. Electric Power Service: Connect to existing service.
C. Lighting: Provide temporary lighting as required.
D. Water: Connect to Owners potable water.
1.7 SUPPORT FACILITIES INSTALLATION
A. Parking: Use designated areas by the Owner/TMM’s existing parking areas.
END OF SECTION 015000
SECTION 016000 - PRODUCT
SECTION 016000 - PRODUCT REQUIREMENTS
1.1 SUMMARY
A. Section includes administrative and procedural requirements for selection of products for use in
Project; product delivery, storage, and handling; manufacturers' standard warranties on products;
special warranties; and comparable products.
1.2 DEFINITIONS
A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment,"
"system," and terms of similar intent.
1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.
2. New Products: Items that have not previously been incorporated into another project or facility. Salvaged items or items reused from other projects are not considered new products. Items that are manufactured or fabricated to include recycled content materials are considered new products, unless indicated otherwise.
3. Comparable Product: Product by named manufacturer that is demonstrated and approved through the comparable product submittal process described in Part 2 "Comparable
Products" Article, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.
B. Subject to Compliance with Requirements: Where the phrase "Subject to compliance with requirements" introduces a product selection procedure in an individual Specification Section, provide products qualified under the specified product procedure. In the event that a named product or product by a named manufacturer does not meet the other requirements of the specifications, select another named product or product from another named manufacturer that does meet the requirements of the specifications; submit a comparable product request or substitution request, if applicable.
C. Comparable Product Request Submittal: An action submittal requesting consideration of a comparable product, including the following information:
1. Identification of basis-of-design product or fabrication or installation method to be replaced, including Specification Section number and title and Drawing numbers and titles.
D. Substitution: Refer to Section 012500 "Substitution Procedures" for definition and limitations on substitutions.
1.3 QUALITY ASSURANCE
A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options.
1.4 QUALITY AND QUANTITY
A. Work shall be executed in conformity with the Owner/TMM accepted standard of practice of the trade so as to contribute to maximum efficiency of operation, accessibility and appearance, minimum cost of maintenance and construction of future alterations and additions. It shall be executed that the completed work will conform and adjust itself to any existing installation.
B. When materials are specified to conform to ASTM, Federal, or other reference specifications, the materials delivered to the site shall bear the manufacturer's printed labels stating that the materials meet the requirements of such referenced specification.
1.5 MANUFACTURER'S INSTRUCTIONS
A. Perform work in accord with manufacturer's instructions.
B. Do not omit preparatory or installation procedures required by the manufacturer.
C. Handle, install, connect, clean, condition and adjust products in strict accord with such instructions and in conformance with specified requirements.
D. Should job conditions or specified requirements conflict with manufacturer's instructions consult with TMM.
E. Do not proceed with work without clear instruction.
1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products, using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.
1.7 PRODUCT WARRANTIES
A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract
Documents.
1. Manufacturer's Warranty: Written standard warranty form furnished by individual manufacturer for a particular product and issued in the name of the Owner or endorsed by manufacturer to Owner.
2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner and issued in the name of the Owner or endorsed by manufacturer to Owner.
B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution.
1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.
2. Specified Form: When specified forms are included in the Project Manual, prepare a written document, using indicated form properly executed.
3. See other Sections for specific content requirements and particular requirements for submitting special warranties.
PART 2 - PRODUCTS
2.1 PRODUCT SELECTION PROCEDURES
A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation.
1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.
2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.
3. Owner reserves the right to limit selection to products with warranties meeting requirements of the Contract Documents.
4. Where products are accompanied by the term "as selected," TMM will make selection.
5. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.
B. Product Selection Procedures:
1. Sole Product: Where Specifications name a single manufacturer and product, provide the named product that complies with requirements. Comparable products or substitutions for
Contractor's convenience will not be considered.
C. Visual Selection Specification: Where Specifications include the phrase "as selected by TMM from manufacturer's full range" or a similar phrase, select a product that complies with requirements. TMM will select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.
2.2 COMPARABLE PRODUCTS
A. Conditions for Consideration of Comparable Products: TMM will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, TMM may return requests without action, except to record noncompliance with the following requirements:
1. Evidence that proposed product does not require revisions to the Contract Documents, is consistent with the Contract Documents, will produce the indicated results, and is compatible with other portions of the Work.
2. Detailed comparison of significant qualities of proposed product with those of the named basis-of-design product. Significant product qualities include attributes, such as type, function, in-service performance and physical properties, weight, dimension, durability, visual characteristics, and other specific features and requirements.
3. Evidence that proposed product provides specified warranty.
4. List of similar installations for completed projects, with project names and addresses and names and addresses of architects and owners, if requested.
5. Samples, if requested.
B. Action on Comparable Products Submittal: If necessary, TMM will request additional information or documentation for evaluation, as specified in Section 013300 "Submittal
Procedures."
1. Form of Approval of Submittal: As specified in Section 013300 "Submittal Procedures."
2. Use product specified if TMM does not issue a decision on use of a comparable product request within time allocated.
C. Submittal Requirements, Two-Step Process: Approval by the TMM of Contractor's request for use of comparable product is not intended to satisfy other submittal requirements. Comply with specified submittal requirements.
D. Submittal Requirements, Single-Step Process: When acceptable to TMM, incorporate specified submittal requirements of individual Specification Section in combined submittal for comparable products. Approval by the TMM of Contractor's request for use of comparable product and of individual submittal requirements will also satisfy other submittal requirements.
END OF SECTION 016000
SECTION 017300 -
SECTION 017300 - EXECUTION
1.1 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the
Work, including, but not limited to, the following:
1. Installation of the Work.
2. Cutting and patching.
3. Progress cleaning.
4. Protection of installed construction.
5. Correction of the Work.
B. Related Requirements:
1. Section 011000 "Summary" for limits on use of the Project site.
1.2 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work.
B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.
1.3 INFORMATIONAL SUBMITTALS
A. Certificates: Submit certificate signed by contractor, certifying that location and elevation of improvements comply with requirements.
1.4 QUALITY ASSURANCE
A. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.
1. Structural Elements: When cutting and patching structural elements, or when encountering the need for cutting and patching of elements whose structural function is not known, notify
TMM of locations and details of cutting and await directions from TMM before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.
2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety.
3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety.
4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in TMM's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.
B. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of specified products and equipment.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Comply with requirements specified in other Sections.
B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.
1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to TMM for the visual and functional performance of in-place materials. Use materials that are not considered hazardous.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examination and Acceptance of Conditions: Before proceeding with each component of the
Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.
1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.
2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.
3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.
B. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Measurements: Take measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication.
Coordinate fabrication schedule with construction progress to avoid delaying the Work.
B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to TMM in accordance with requirements in Section 013100 "Project Management and Coordination."
3.3 INSTALLATION
A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Install products at the time and under conditions that will ensure satisfactory results as judged by
TMM. Maintain conditions required for product performance until Substantial Completion.
D. Conduct construction operations, so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy of type expected for
Project.
E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on-site and placement in permanent locations.
F. Tools and Equipment: Select tools or equipment that minimize production of excessive noise levels.
G. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions with manufacturer.
1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by TMM.
2. Allow for building movement, including thermal expansion and contraction.
3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to
Project site in time for installation.
H. Joints: Make joints of uniform width. Where joint locations in exposed Work are not indicated, arrange joints for the best visual effect, as judged by TMM. Fit exposed connections together to form hairline joints.
3.4 CUTTING AND PATCHING
A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.
1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.
C. Temporary Support: Provide temporary support of Work to be cut.
D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.
E. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations. Do not over cut corners.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.
3. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.
4. Proceed with patching after construction operations requiring cutting are complete.
F. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as practicable, as judged by TMM. Provide materials and comply with installation requirements specified in other Sections, where applicable.
1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.
2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
a. Where patching occurs in a painted surface, prepare substrate and apply primer and intermediate paint coats appropriate for substrate over the patch, and apply final paint coat over entire unbroken surface containing the patch, corner to corner of wall and edge to edge of ceiling. Provide additional coats until patch blends with adjacent surfaces.
G. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.
3.5 PROGRESS CLEANING
A. Clean Project site and work areas daily, including common areas. Enforce requirements strictly.
Dispose of materials lawfully.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where Work is in progress to the level of cleanliness necessary for proper execution of the Work.
1. Remove liquid spills promptly.
2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.
D. Exposed Surfaces: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.
E. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways.
F. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
G. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
3.6 CORRECTION OF THE WORK
A. Repair or remove and replace damaged, defective, or nonconforming Work. Restore damaged substrates and finishes.
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
B. Repair Work previously completed and subsequently damaged during construction period. Repair to like-new condition.
C. Restore permanent facilities used during construction to their specified condition.
D. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.
E. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.
F. Remove and replace chipped, scratched, and broken glass or reflective surfaces.
END OF SECTION 017300
SECTION 017419 -
CONSTRUCTION WASTE
DISPOSAL
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Disposing of demolition and waste.
1.2 DEFINITIONS
A. Construction Waste: Building, structure, and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building, structure, materials resulting from demolition operations.
1.3 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged or recycled, remove waste materials from
Project site and legally dispose of them in a landfill.
1. Do not allow waste materials that are to be disposed of accumulate on-site.
END OF SECTION 017419
SECTION 017700 -
SECTION 017700 - CLOSEOUT PROCEDURES
1.1 SUMMARY
A. Section includes administrative and procedural requirements for Contract closeout, including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
B. Related Requirements:
1. Section 017823 "Operation and Maintenance Data" for additional operation and maintenance manual requirements.
2. Section 017839 "Project Record Documents" for submitting Record Drawings, Record
Specifications, and Record Product Data.
3. Section 017900 "Demonstration and Training" for requirements to train the Owner's maintenance personnel to adjust, operate, and maintain products, equipment, and systems.
1.2 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.
1.3 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's "punch list"), indicating the value of each item on the list and reasons why the Work is incomplete.
B. Submittals…