SBA Office Site IT Infrastructure

Pre-Contract Specifications and Requirements

NOTE: Items in RED are mandatory requirements no deviations or substitutes are acceptable

Version 1.1 Date: July 2018

U.S. SMALL BUSINESS ADMINISTRATION

U.S. SMALL BUSINESS ADMINISTRATION

Table of Contents

Section Number Page Number

1 Purpose

2 WAN Facilities

3 Cooling and Power Requirements

4 Enquiries

5 Abbreviations & Definitions

1.0 PURPOSE

The purpose of this document is to provide physical plant telecommunications utilities and equipment requirements for any proposed SBA office space. These requirements are specific to SBA and include telecommunications access and pathways, the LAN room/closet, and all electrical and cooling requirements. These requirements are applicable to all new and/or remodeled offices provided to the SBA. All SBA office infrastructure must comply and be built according to these standards going forward. Any exception must be approved in writing by a representative from the OCIO. These requirements ensure that every SBA office site is configured to a common set of infrastructure standards across the enterprise which provides the platform for consistent and reliable IT services.

2.0 WAN Facility in SBA Building (mandatory)

In the main telecommunications room (demarc) of each building in which an SBA office is located, there must be Local Exchange Carrier (LEC) equipment and capacity already in place to provide the SBA office at a minimum: two (2) each high- speed telecommunications circuits. SBA uses optical carrier, DS3 and/or Ethernet circuits.

2.1 WAN Facility to SBA Suite (mandatory)

Each SBA office suite must have in place prior to occupancy conduit with excess capacity to extend the SBA telecommunications circuit(s) from the buildings main telecommunications room (demarc) to each respective SBA suite LAN room/closet (extended demarc. Conduit shall be a minimum of 2 inches

3.0 LAN ROOM SPECIFICATIONS

Equipment room spaces in SBA offices require adequate access in a well ventilated (floor & ceiling) area to house and secure all Local Area Network (LAN) equipment. These guidelines are based on TIA- 569

- B Standards for Building Spaces.

a) Floor space requirements: The room shall be large enough to allow no less than three feet (36 inches) for accessibility around all sides of the LAN equipment. For smaller networks requiring less than 16U of total rack space, a wall mounted LAN rack may be used. If installation of a LAN rack outside of a secured room is required, approval must be given first by the Office of the Chief Information Officer.

b) HVAC requirements: Adequate temperature and humidity control of the SBA network equipment in the LAN room will be provided 24 hours a day. No additional fire suppression is required for Regional/District/Branch offices (only in critical SBA data center systems)

c) One IT equipment rack (19”), minimum of 42 RUs bolted to the floor with horizontal and vertical cable management.

(Above picture is for demonstration purposes only)

d) Equipment Installation requirements: All operating computer equipment, distribution networks and backbone cables in the LAN room shall be installed using cable trays and 19” IT equipment racks with access from both front and back.

The sample drawing above shows a representative layout of the LAN room. It is important to check the depth of equipment which is to be installed before selecting racks to ensure a proper fit while still allowing 36” access around all sides of the equipment rack.

4.0 Cooling and Power Requirements

Cooling Requirements and Power Consumption Rates

DESCRIPTION POWER

CONSUMPTION

(Watts)

BTU /

Hr.

Temp

(operating)

Humidity

Router (Cisco 900) 310 1058 61–75 °F 40–55% with a maximum dew point of 61°F

Switch (Cisco 850) 75 256 61–75 °F 0–55% with a maximum ew point of 61°F

Power Requirements

SPACE

Power Requirement

Description

LAN Room 1 Dedicated Quad Outlets (30 amp) for UPS Battery Unit

LAN Equipment

1 Dedicated Quad Outlet (20amp)

A/C Unit (if not direct wired)

1 Dedicated Quad Outlet (15 amp) per network printer

Multi-function printer

5.0 Grounding systems (per ANSI/TIA-607-B and TIA-942)

a) All LAN room equipment must be grounded in compliance with state and local codes.

b) LAN room equipment grounds must be independent of all other building grounds (such as lightning protection systems).

c) All metal objects must be bonded to ground including cabinets, racks, LAN room UPS’s, LAN room A/C, cable pathway, and any raised floor systems.

d) Ground resistance should be < 5 Ohms.

6.0 Enquires

Direct all questions concerning this notice to SBA, OCIO - IT Operations staff.

6.1 Abbreviations and Definitions

IEEE Institute of Electrical and Electronics Engineers Information Technology IT Information Technology LAN Local Area Network OCIO Office of the Chief Information Officer PBX Private Branch Exchange UTP Unshielded Twisted Pair SBA Small Business Administration SCORE A nonprofit association for helping small businesses TIA-942 TIA-942 is a standard developed by the Telecommunications Industry Association

(TIA) to define guidelines for planning and building data centers, particularly with regard to cabling systems and network design. The standard deals with both copper and fiber optic media.

TIA-569 TIA-569 is a Commercial Building Standard for Telecommunications Pathways and Spaces that specifies specific pathway and space design & construction practices in support of telecommunications media & equipment within buildings.

http://searchnetworking.techtarget.com/definition/fiber-optic

SBA Office Site
IT Infrastructure
Pre-Contract
Specifications and Requirements
1.0 PURPOSE
2.1 WAN Facility to SBA Suite (mandatory)
3.0 LAN ROOM SPECIFICATIONS
4.0 Cooling and Power Requirements
6.0 Enquires
6.1 Abbreviations and Definitions