ESBD_File_338829_Revised Attachment B (Public Works Requirements) (10-19-23).xlsx
XLSX spreadsheet 62 KB Posted
- Attached to
- Citywide Repair of Sidewalks and Streets
- Solicitation number
- IFB23-384
- Issued by
- Fort Bend County, Mildred Town, Texas
About this file
This document is a revised attachment to an Invitation for Bids (IFB) for a multi-year contract issued by the City of Missouri City, Texas to provide citywide repair of sidewalks and streets on an "as needed basis". The contract consists of four primary components: sidewalks, street panel replacement, asphalt patching/overlay, and pavement lifting/leveling. Each component has estimated quantities for items such as wheelchair ramps, concrete work, asphalt patching, and pavement lifting across three contract years. Bids are due with the revised attachments by the specified due date. The contract will be awarded for an initial one-year term with two one-year renewal options.
The bid pricing is provided on a unit cost basis for the various line items. Bidders must submit pricing for all four components and all three contract years. The total bid price will be calculated automatically based on the unit prices entered. There are no specific set-asides mentioned, and the current incumbent(s) are not identified. Funding for the contract will come from the City's budget, though specific amounts are not provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Year 1 (Sidewalks) Revised Attachment B-1-1 Year 1 Price Sheet
| (Public Works Estimated Requirements) | |||||
| SIDEWALKS | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| 1 | LS | Mobilization | $ - 0 | ||
| 2 | 100 | Each | Temporary Traffic Control | $ - 0 | $ - 0 |
| 4 | 4 | Each | Standard ADA Wheelchair Ramp (New) | $ - 0 | $ - 0 |
| 5 | 18 | Each | Standard ADA Wheelchair Ramp (remove and replace) | $ - 0 | $ - 0 |
| 6 | 230 | Each | Bricks, Truncated, for wheelchair ramps | $ - 0 | $ - 0 |
| 7 | 500 | SF | 6" Thick Sidewalk (New) | $ - 0 | $ - 0 |
| 8 | 500 | SF | 4" Thick Sidewalk (New) | $ - 0 | $ - 0 |
| 9 | 2,200 | SF | 6" Thick Sidewalk (Remove and Replace) | $ - 0 | $ - 0 |
| 10 | 100,000 | SF | 4" Thick Sidewalk (Remove and Replace) | $ - 0 | $ - 0 |
| 11 | 565 | LF | 6" Concrete Curb Repair | $ - 0 | $ - 0 |
| 12 | 100 | Each | Concrete Grinding Locations | $ - 0 | $ - 0 |
| 13 | 1,000 | Each | Tree Root Removal | $ - 0 | $ - 0 |
| 14 | 1,000 | LF | Install 12" Tree Root Barrier | $ - 0 | $ - 0 |
| Sidewalk Incidentals | |||||
| 15 | 30 | Each | Manhole Adjustments | $ - 0 | $ - 0 |
| 16 | 30,000 | SF | Sod Block | $ - 0 | $ - 0 |
| 17 | 60 | Each | Sprinkler Replace & Installation (Includes all materials) | $ - 0 | $ - 0 |
| 18 | 20 | Each | Replace Irrigation Sprinkler Head | $ - 0 | $ - 0 |
| 19 | 1,000 | LF | Irrigation line Replace & Installation (includes all materials) (all pipe sizes) | $ - 0 | $ - 0 |
| YEAR 1 (SIDEWALK) TOTAL BID PRICE: | 0.00 |
Note: This Price Sheet must submitted with Revised Attachments B-1-1, B-1-2, B-1-3, B-1-4, B-2-1, B-2-2, B-2-3, B-2-4, B-3-1, B-3-2, B-3-3, and B-3-4.
Year 1 (Street Panel Replace) Revised Attachment B-1-2 Year 1 Price Sheet
| (Public Works Estimated Requirements) | |||||
| STREET PANEL REPLACEMENT | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| Street Panel Replacement | |||||
| 20 | LS | Mobilization | $ - 0 | $ - 0 | |
| 21 | 1 | Each | Traffic Contol | $ - 0 | $ - 0 |
| 22 | 5,000 | LF | 2" Saw Cut | $ - 0 | $ - 0 |
| 23 | 3,200 | LF | Full Depth Saw Cut | $ - 0 | $ - 0 |
| 24 | 35 | LF | Spalled Joint Repair | $ - 0 | $ - 0 |
| 25 | 10,000 | LF | 6" Concrete Curb Repair | $ - 0 | $ - 0 |
| 26 | 15,000 | SF | 7" Concrete Pavement Rem. & Repl. w/appurtenances - 7" Concrete Pavement Removal and Replacement with appurtenances | $ - 0 | $ - 0 |
| 27 | 150,000 | SF | High Early 7" Concrete Repl.-High Early 7" Concrete Pavement Removal and Replacement with appurtenances, min 7 sack cement/CY | $ - 0 | $ - 0 |
| 28 | 5 | Each | Standard ADA Wheelchair Ramp Installation (New) | $ - 0 | $ - 0 |
| 28A | 20 | Each | Standard ADA Wheelchair Ramp (Remove and Replace) | $ - 0 | $ - 0 |
| 29 | 800 | Each | Truncated Bricks | $ - 0 | $ - 0 |
| 30 | 15,500 | SF | 6" Driveway Repair | $ - 0 | $ - 0 |
| 31 | 625 | LF | 6" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 32 | 1,250 | LF | 6" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 33 | 250 | LF | 8" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 34 | 500 | LF | 8" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 35 | 250 | LF | 12" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 36 | 625 | LF | 12" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 37 | 500 | LF | 24" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 38 | 750 | LF | 24" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 39 | 3 | Each | Only (White Thermoplastic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 40 | 3 | Each | Arrow (single, White Thermplastic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 41 | 3 | Each | Arrow (Combo, White Thermoplactic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 42 | 125 | Each | Raised Pavement Markings | $ - 0 | $ - 0 |
| Street Panel Incidentals | |||||
| 47 | 2 | Each | Manhole Adjustments | $ - 0 | $ - 0 |
| 48 | 20 | Each | Inlet Adjustments | $ - 0 | $ - 0 |
| 49 | 1 | SF | 6" Driveway New | $ - 0 | $ - 0 |
| 50 | 1 | Each | Tree Root Removal (Unit Price shall not be less than $ 200) | $ - 0 | $ - 0 |
| 51 | 1,000 | LF | 12" Tree Root Barrier | $ - 0 | $ - 0 |
| 52 | 11,000 | SF | Sod Block Placement | $ - 0 | $ - 0 |
| 53 | 1 | Each | Remove and replace mailbox | $ - 0 | $ - 0 |
| 54 | 1 | Each | Repair mailbox | $ - 0 | $ - 0 |
| YEAR 1 (STREET PANEL) TOTAL BID PRICE: | 0.00 | ||||
| Note: This Price Sheet must submitted with Revised Attachments |
Year 1 (Asphalt) Revised Attachment B-1-3 Year 1 Price Sheet
| (Public Works Estimated Requirements) | |||||
| ASPHALT | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| Asphalt Patching / Overlay | |||||
| 56 | LS | Mobilization | $ - 0 | $ - 0 | |
| 57 | 1 | Each | Traffic Contol | $ - 0 | $ - 0 |
| 58 | 10,000 | SF | 12" Asphalt Patching | $ - 0 | $ - 0 |
| 59 | 30,000 | SF | 2" Depth Asphalt Miling | $ - 0 | $ - 0 |
| 60 | 85,000 | SF | 2" Asphalt Overlay | $ - 0 | $ - 0 |
| YEAR 1 (ASPHALT) TOTAL BID PRICE: | $ - 0 |
Note: This Price Sheet must submitted with Revised Attachments
Year 1 (Pavement Lifting) Revised Attachment B-1-4 Year 1 Price Sheet
| (Public Works Estimated Requirements) | ||||||
| PAVEMENT LIFTING | ||||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | ||||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price | |
| Concrete Pavement Lifting / Leveling | ||||||
| 61 | 225,000 | SF | Lifting and Stabilizing Concrete Panels using Cementitious Slurry Material (pavment lift from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 62 | 300 | SF | Lifting and Stabilizing Concrete Panels using Cementitious Slurry Material (pavment lift from 6.01" and up) | $ - 0 | $ - 0 | |
| 63 | 2,500 | LB | Lifting and Stabilizing Concrete Panels using polyurethane concrete lifting foam (pavment lift from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 64 | 5,000 | LB | Lifting and Stabilizing Concrete Panels using polyurethane concrete lifting foam (pavment lift from 6.01" and up) | $ - 0 | $ - 0 | |
| 65 | 15 | Each | Lifting and Stabilizing Concrete Traffic Signal Pad (lifting from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 66 | 15 | Each | Lifting and Stabilizing Concrete Traffic Signal Pad (lifting from 6.01" and up) | $ - 0 | $ - 0 | |
| 67 | N/A | N/A | Bonding per Section 10 of IFB 23-384, | |||
| based on Attachments B-1-1, B-1-2, B-1-3, B-1-4. | $ - 0 | $ - 0 | ||||
| YEAR 1 (PAVEMENT LIFTING) TOTAL BID PRICE: | $ - 0 |
Note: This Price Sheet must submitted with Revised Attachments
Year 2 (Sidewalks) Revised Attachment B-2-1 Year 2 Price Sheet
| (Public Works Estimated Requirements) | |||||
| SIDEWALKS | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| 1 | 1 | LS | Mobilization | $ - 0 | $ - 0 |
| 2 | 100 | Each | Temporary Traffic Control | $ - 0 | $ - 0 |
| 4 | 4 | Each | Standard ADA Wheelchair Ramp (New) | $ - 0 | $ - 0 |
| 5 | 18 | Each | Standard ADA Wheelchair Ramp (remove and replace) | $ - 0 | $ - 0 |
| 6 | 230 | Each | Bricks, Truncated, for wheelchair ramps | $ - 0 | $ - 0 |
| 7 | 500 | SF | 6" Thick Sidewalk (New) | $ - 0 | $ - 0 |
| 8 | 500 | SF | 4" Thick Sidewalk (New) | $ - 0 | $ - 0 |
| 9 | 2,200 | SF | 6" Thick Sidewalk (Remove and Replace) | $ - 0 | $ - 0 |
| 10 | 100,000 | SF | 4" Thick Sidewalk (Remove and Replace) | $ - 0 | $ - 0 |
| 11 | 565 | LF | 6" Concrete Curb Repair | $ - 0 | $ - 0 |
| 12 | 100 | Each | Concrete Grinding Locations | $ - 0 | $ - 0 |
| 13 | 1,000 | Each | Tree Root Removal | $ - 0 | $ - 0 |
| 14 | 1,000 | LF | Install 12" Tree Root Barrier | $ - 0 | $ - 0 |
| Sidewalk Incidentals | |||||
| 15 | 30 | Each | Manhole Adjustments | $ - 0 | $ - 0 |
| 16 | 30,000 | SF | Sod Block | $ - 0 | $ - 0 |
| 17 | 60 | Each | Sprinkler Replace & Installation (Includes all materials) | $ - 0 | $ - 0 |
| 18 | 20 | Each | Replace Irrigation Sprinkler Head | $ - 0 | $ - 0 |
| 19 | 1,000 | LF | Irrigation line Replace & Installation (includes all materials) (all pipe sizes) | $ - 0 | $ - 0 |
| YEAR 2 (SIDEWALKS) TOTAL BID PRICE: | 0.00 |
purchasing
Year 2 (Street Panel Replace) Revised Attachment B-2-2 Year 2 Price Sheet
| (Public Works Estimated Requirements) | |||||
| STREET PANEL REPLACEMENT | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| Street Panel Replacement | |||||
| 20 | 1 | LS | Mobilization | $ - 0 | $ - 0 |
| 21 | 1 | Each | Traffic Contol | $ - 0 | $ - 0 |
| 22 | 5,000 | LF | 2" Saw Cut | $ - 0 | $ - 0 |
| 23 | 3,200 | LF | Full Depth Saw Cut | $ - 0 | $ - 0 |
| 24 | 35 | LF | Spalled Joint Repair | $ - 0 | $ - 0 |
| 25 | 10,000 | LF | 6" Concrete Curb Repair | $ - 0 | $ - 0 |
| 26 | 15,000 | SF | 7" Concrete Pavement Rem. & Repl. w/appurtenances - 7" Concrete Pavement Removal and Replacement with appurtenances | $ - 0 | $ - 0 |
| 27 | 150,000 | SF | High Early 7" Concrete Repl.-High Early 7" Concrete Pavement Removal and Replacement with appurtenances, min 7 sack cement/CY | $ - 0 | $ - 0 |
| 28 | 5 | Each | Standard Wheelchair Ramp Installation (New) | $ - 0 | $ - 0 |
| 28A | 20 | Each | Standard ADA Wheelchair Ramp (Remove and Replace) | $ - 0 | $ - 0 |
| 29 | 800 | Each | Truncated Bricks | $ - 0 | $ - 0 |
| 30 | 15,500 | SF | 6" Driveway Repair | $ - 0 | $ - 0 |
| 31 | 625 | LF | 6" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 32 | 1,250 | LF | 6" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 33 | 250 | LF | 8" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 34 | 500 | LF | 8" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 35 | 250 | LF | 12" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 36 | 625 | LF | 12" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 37 | 500 | LF | 24" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 38 | 750 | LF | 24" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 39 | 3 | Each | Only (White Thermoplastic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 40 | 3 | Each | Arrow (single, White Thermplastic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 41 | 3 | Each | Arrow (Combo, White Thermoplactic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 42 | 125 | Each | Raised Pavement Markings | $ - 0 | $ - 0 |
| Street Panel Incidentals | |||||
| 47 | 2 | Each | Manhole Adjustments | $ - 0 | $ - 0 |
| 48 | 20 | Each | Inlet Adjustments | $ - 0 | $ - 0 |
| 49 | 1 | SF | 6" Driveway New | $ - 0 | $ - 0 |
| 50 | 1 | Each | Tree Root Removal (Unit Price shall not be less than $ 200) | $ - 0 | $ - 0 |
| 51 | 1,000 | LF | 12" Tree Root Barrier | $ - 0 | $ - 0 |
| 52 | 11,000 | SF | Sod Block Placement | $ - 0 | $ - 0 |
| 53 | 1 | Each | Remove and replace mailbox | $ - 0 | $ - 0 |
| 54 | 1 | Each | Repair mailbox | $ - 0 | $ - 0 |
| YEAR 2 (STREET PANEL REPLACEMENT) TOTAL BID PRICE: | 0.00 | ||||
| Note: This Price Sheet must submitted with Revised Attachments |
Year 2 (Asphalt) Revised Attachment B-2-3 Year 2 Price Sheet
| (Public Works Estimated Requirements) | |||||
| ASPHALT | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| Asphalt Patching / Overlay | |||||
| 56 | 1 | LS | Mobilization | $ - 0 | $ - 0 |
| 57 | 1 | Each | Traffic Contol | $ - 0 | $ - 0 |
| 58 | 10,000 | SF | 12" Asphalt Patching | $ - 0 | $ - 0 |
| 59 | 30,000 | SF | 2" Depth Asphalt Miling | $ - 0 | $ - 0 |
| 60 | 85,000 | SF | 2" Asphalt Overlay | $ - 0 | $ - 0 |
| YEAR 2 (ASPHALT) TOTAL BID PRICE: | $ - 0 |
Note: This Price Sheet must submitted with Revised Attachments
Year 2 (Pavement Lifting) Revised Attachment B-2-4 Year 2 Price Sheet
| (Public Works Estimated Requirements) | ||||||
| PAVEMENT LIFTING | ||||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | ||||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price | |
| Concrete Pavement Lifting / Leveling | ||||||
| 61 | 225,000 | SF | Lifting and Stabilizing Concrete Panels using Cementitious Slurry Material (pavment lift from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 62 | 300 | SF | Lifting and Stabilizing Concrete Panels using Cementitious Slurry Material (pavment lift from 6.01" and up) | $ - 0 | $ - 0 | |
| 63 | 2,500 | LB | Lifting and Stabilizing Concrete Panels using polyurethane concrete lifting foam (pavment lift from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 64 | 5,000 | LB | Lifting and Stabilizing Concrete Panels using polyurethane concrete lifting foam (pavment lift from 6.01" and up) | $ - 0 | $ - 0 | |
| 65 | 15 | Each | Lifting and Stabilizing Concrete Traffic Signal Pad (lifting from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 66 | 15 | Each | Lifting and Stabilizing Concrete Traffic Signal Pad (lifting from 6.01" and up) | $ - 0 | $ - 0 | |
| 67 | N/A | N/A | Bonding per Section 10 of IFB 23-384, | |||
| based on Attachments B-2-1, B-2-2, B-2-3, B-2-4. | $ - 0 | $ - 0 | ||||
| YEAR 2 (PAVEMENT LIFTING) TOTAL BID PRICE: | $ - 0 |
Note: This Price Sheet must submitted with Revised Attachments
Year 3 (Sidewalks) Revised Attachment B-3-1 Year 3 Price Sheet
| (Public Works Estimated Requirements) | |||||
| SIDEWALKS | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| 1 | 1 | LS | Mobilization | $ - 0 | $ - 0 |
| 2 | 100 | Each | Temporary Traffic Control | $ - 0 | $ - 0 |
| 4 | 4 | Each | Standard ADA Wheelchair Ramp (New) | $ - 0 | $ - 0 |
| 5 | 18 | Each | Standard ADA Wheelchair Ramp (remove and replace) | $ - 0 | $ - 0 |
| 6 | 230 | Each | Bricks, Truncated, for wheelchair ramps | $ - 0 | $ - 0 |
| 7 | 500 | SF | 6" Thick Sidewalk (New) | $ - 0 | $ - 0 |
| 8 | 500 | SF | 4" Thick Sidewalk (New) | $ - 0 | $ - 0 |
| 9 | 2,200 | SF | 6" Thick Sidewalk (Remove and Replace) | $ - 0 | $ - 0 |
| 10 | 100,000 | SF | 4" Thick Sidewalk (Remove and Replace) | $ - 0 | $ - 0 |
| 11 | 565 | LF | 6" Concrete Curb Repair | $ - 0 | $ - 0 |
| 12 | 100 | Each | Concrete Grinding Locations | $ - 0 | $ - 0 |
| 13 | 1,000 | Each | Tree Root Removal | $ - 0 | $ - 0 |
| 14 | 1,000 | LF | Install 12" Tree Root Barrier | $ - 0 | $ - 0 |
| Sidewalk Incidentals | |||||
| 15 | 30 | Each | Manhole Adjustments | $ - 0 | $ - 0 |
| 16 | 30,000 | SF | Sod Block | $ - 0 | $ - 0 |
| 17 | 60 | Each | Sprinkler Replace & Installation (Includes all materials) | $ - 0 | $ - 0 |
| 18 | 20 | Each | Replace Irrigation Sprinkler Head | $ - 0 | $ - 0 |
| 19 | 1,000 | LF | Irrigation line Replace & Installation (includes all materials) (all pipe sizes) | $ - 0 | $ - 0 |
| YEAR 3 (SIDEWALKS) TOTAL BID PRICE: | 0.00 |
Note: This Price Sheet must submitted with Revised Attachments
Year 3 (Street Panel Replace) Revised Attachment B-3-2 Year 3 Price Sheet
| (Public Works Estimated Requirements) | |||||
| STREET PANEL REPLACEMENT | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| Street Panel Replacement | |||||
| 20 | 1 | LS | Mobilization | $ - 0 | $ - 0 |
| 21 | 1 | Each | Traffic Contol | $ - 0 | $ - 0 |
| 22 | 5,000 | LF | 2" Saw Cut | $ - 0 | $ - 0 |
| 23 | 3,200 | LF | Full Depth Saw Cut | $ - 0 | $ - 0 |
| 24 | 35 | LF | Spalled Joint Repair | $ - 0 | $ - 0 |
| 25 | 10,000 | LF | 6" Concrete Curb Repair | $ - 0 | $ - 0 |
| 26 | 15,000 | SF | 7" Concrete Pavement Rem. & Repl. w/appurtenances - 7" Concrete Pavement Removal and Replacement with appurtenances | $ - 0 | $ - 0 |
| 27 | 150,000 | SF | High Early 7" Concrete Repl.-High Early 7" Concrete Pavement Removal and Replacement with appurtenances, min 7 sack cement/CY | $ - 0 | $ - 0 |
| 28 | 5 | Each | Standard Wheelchair Ramp Installation (New) | $ - 0 | $ - 0 |
| 28A | 20 | Each | Standard ADA Wheelchair Ramp (Remove and Replace) | $ - 0 | $ - 0 |
| 29 | 800 | Each | Truncated Bricks | $ - 0 | $ - 0 |
| 30 | 15,500 | SF | 6" Driveway Repair | $ - 0 | $ - 0 |
| 31 | 625 | LF | 6" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 32 | 1,250 | LF | 6" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 33 | 250 | LF | 8" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 34 | 500 | LF | 8" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 35 | 250 | LF | 12" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 36 | 625 | LF | 12" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 37 | 500 | LF | 24" Yellow Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 38 | 750 | LF | 24" White Thermoplastic marking (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 39 | 3 | Each | Only (White Thermoplastic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 40 | 3 | Each | Arrow (single, White Thermplastic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 41 | 3 | Each | Arrow (Combo, White Thermoplactic) (Hot applied including glass beads) | $ - 0 | $ - 0 |
| 42 | 125 | Each | Raised Pavement Markings | $ - 0 | $ - 0 |
| Street Panel Incidentals | |||||
| 47 | 2 | Each | Manhole Adjustments | $ - 0 | $ - 0 |
| 48 | 20 | Each | Inlet Adjustments | $ - 0 | $ - 0 |
| 49 | 1 | SF | 6" Driveway New | $ - 0 | $ - 0 |
| 50 | 1 | Each | Tree Root Removal (Unit Price shall not be less than $ 200) | $ - 0 | $ - 0 |
| 51 | 1,000 | LF | 12" Tree Root Barrier | $ - 0 | $ - 0 |
| 52 | 11,000 | SF | Sod Block Placement | $ - 0 | $ - 0 |
| 53 | 1 | Each | Remove and replace mailbox | $ - 0 | $ - 0 |
| 54 | 1 | Each | Repair mailbox | $ - 0 | $ - 0 |
| YEAR 3 (STREET PANEL REPLACEMENT) TOTAL BID PRICE: | 0.00 |
Note: This Price Sheet must submitted with Revised Attachments
Year 3 (Asphalt) Revised Attachment B-3-3 Year 3 Price Sheet
| (Public Works Estimated Requirements) | |||||
| ASPHALT | |||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | |||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price |
| Asphalt Patching / Overlay | |||||
| 56 | 1 | LS | Mobilization | $ - 0 | $ - 0 |
| 57 | 1 | Each | Traffic Contol | $ - 0 | $ - 0 |
| 58 | 10,000 | SF | 12" Asphalt Patching | $ - 0 | $ - 0 |
| 59 | 30,000 | SF | 2" Depth Asphalt Miling | $ - 0 | $ - 0 |
| 60 | 85,000 | SF | 2" Asphalt Overlay | $ - 0 | $ - 0 |
| YEAR 3 (ASPHAT) TOTAL BID PRICE: | $ - 0 |
Note: This Price Sheet must submitted with Revised Attachments
Year 3 (Pavement Lifting) Revised Attachment B-3-4 Year 3 Price Sheet
| (Public Works Estimated Requirements) | ||||||
| PAVEMENT LIFTING | ||||||
| Note: This sheet is formatted so that you can only enter unit pricing in the highlighted column. | ||||||
| Item No. | Est. Qty | Unit | Description | Unit Price | Extension Price | |
| Concrete Pavement Lifting / Leveling | ||||||
| 61 | 225,000 | SF | Lifting and Stabilizing Concrete Panels using Cementitious Slurry Material (pavment lift from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 62 | 300 | SF | Lifting and Stabilizing Concrete Panels using Cementitious Slurry Material (pavment lift from 6.01" and up) | $ - 0 | $ - 0 | |
| 63 | 2,500 | LB | Lifting and Stabilizing Concrete Panels using polyurethane concrete lifting foam (pavment lift from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 64 | 5,000 | LB | Lifting and Stabilizing Concrete Panels using polyurethane concrete lifting foam (pavment lift from 6.01" and up) | $ - 0 | $ - 0 | |
| 65 | 15 | Each | Lifting and Stabilizing Concrete Traffic Signal Pad (lifting from 0.01" up to 6.00") | $ - 0 | $ - 0 | |
| 66 | 15 | Each | Lifting and Stabilizing Concrete Traffic Signal Pad (lifting from 6.01" and up) | $ - 0 | $ - 0 | |
| 67 | N/A | N/A | Bonding per Section 10 of IFB 23-384, | |||
| based on Attachments B-3-1, B-3-2, B-3-3, B-3-4. | $ - 0 | $ - 0 | ||||
| YEAR 3 (PAVEMENT LIFTING) TOTAL BID PRICE: | $ - 0 |
Note: This Price Sheet must submitted with Revised Attachments
Three Year Total Bid Price Revised Attachment B-3-5 Total Bid Price Sheet
| (Public Works Estimated Requirements) | |||
| Note: This sheet is formatted so that it will automatically calculate the prices from years 1 through 3. | |||
| Year 1 | Year 2 | Year 3 | Total Bid Price |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Typed Name of Firm:
Name of Authorized Individual:
Manual Signature of Authorized Individual:
Note: This Price Sheet must submitted with Revised Attachments
File details come from the government source that posted it. Updated .