This is a Scope of Work document issued by the Texas Military Department, Construction and Facilities Management Office, for the State of Texas pertaining to chiller replacement services at the Dyess Army Reserve Center (AFRC) located at 819 3rd Street, Abilene, Texas. The project involves the removal and disposal of a failed air-cooled chiller system that became non-operational due to catastrophic mechanical failure from a winter storm, along with the installation of a temporary chiller to maintain facility operations during equipment lead time and installation of a new air-cooled chiller system. The scope of work includes replacement of damaged chilled water piping and insulation, electrical and controls reconnections, system startup, commissioning, and related work necessary to restore the HVAC system to full operational capability at the 69,855-square-foot facility constructed in 2011. The proposed construction will meet current codes and standards while incorporating material and equipment improvements to reduce future damage risk and ensure mission readiness.
The construction cost for this project shall not exceed $1,235,900. The project is designated as AFRC-08140-AON Chiller Replacement with Project Number 48260004 and is located on federally-owned land leased by the Texas Army National Guard. The facility consists of administrative spaces, classrooms, latrines, auditorium, storage, and food preparation areas and is not classified as a historic structure. The existing chiller system experienced leaking condenser coils, refrigerant contamination, and a failed heat exchanger that rendered it beyond economical repair.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF TEXAS
TEXAS MILITARY DEPARTMENT
CONSTRUCTION AND FACILITIES MANAGEMENT OFFICE
NGTX-F 25-Mar-26 Page 1 of 7 Dyess � AFRC - AON Chiller Replacement
APPENDIX A
SCOPE OF WORK
0.0 PROJECT DATA
Project Title: Dyess AFRC-08140-AON Chiller Replacement
Project Address: 819 3rd Street Abilene, TX 79607
Project Number: 48260004
Contract Number: TBD
1.0 SITE DESCRIPTION
1.1 Property Description
The Dyess AFRC is situated on a 25.34-acre tract of land located in Taylor County, Abilene, Texas. The property is Federal land and leased by TXARNG.
1.2 Facility Description
The approximately 69,855-square-foot AFRC was constructed in 2011. The facility consists of men�s and women�s latrines, an auditorium, administrative spaces, classrooms, supply storage, and food preparation areas. The building is not considered a historic structure.
2.0 PROJECT DESCRIPTION
2.1 Project Goals
This project replaces the failed air-cooled chiller system (approximately 1 -ton) and associated chilled water piping at the Dyess Army Reserve Center (AFRC), which was rendered non-operational due to catastrophic mechanical failure caused by Winter
Attachment G.8 Page 1 of 7
NGTX-F 25-Mar-26 Page 2 of 7 Dyess � AFRC - AON Chiller Replacement
SCOPE OF WORK
Storm Fern. The existing system has leaking condenser coils, refrigerant contamination, and a failed heat exchanger, and is beyond economical repair.
2.2 SCOPE
Work includes removal and disposal of the existing chiller, installation of a temporary chiller system to maintain facility operations during equipment lead time, and installation of a new air-cooled chiller. The project also includes replacement of damaged chilled water piping and insulation, along with required electrical and controls reconnections, system startup, commissioning and similar types of work to ensure full operational capability.
The proposed construction will be comparable to the original system, with improvements to materials and equipment to meet current codes and standards and reduce the risk of future damage.
This project restores the facility�s HVAC system to full operational capability and ensures continued mission readiness.
3.0 CONSTRUCTION COST
The construction cost for this project shall not exceed $1,235,900
~END OF SOW~
Attach: Dyess AFRC Location Map
Attachment G.8 Page 2 of 7
NGTX-F 25-Mar-26 Page 3 of 7
SCOPE OF WORK
Location Map
TXARNG � Dyess AFRC 08140
Attachment G.8 Page 3 of 7
SCOPE OF WORK
NGTX-F 25-Mar-26 Page 4 of 7 Dyess � AFRC - AON Chiller Replacement
TXARNG � Dyess AFRC 08140
Dyess AFRC
Attachment G.8 Page 4 of 7
NGTX-F 25-Mar-26 Page 5 of 7
SCOPE OF WORK
Dyess AFRC Chiller Tag
Attachment G.8 Page 5 of 7
NGTX-F 25-Mar-26 Page 6 of 7 Dyess � AFRC - AON Chiller Replacement
Dyess AFRC Exterior of Chiller
Attachment G.8 Page 6 of 7
NGTX-F 25-Mar-26 Page 7 of 7 Dyess � AFRC - AON Chiller Replacement
Dyess AFRC Chiller Damaged Coils
Attachment G.8 Page 7 of 7