This PowerPoint presentation from the University of Houston details a mandatory pre-proposal meeting for RFP730-25000, covering the Houston Science Center New Fire Alarm Panel, Pump Replacement and Fire Sprinkler System project. The meeting is scheduled for January 15, 2025, at 2:00 PM CT, and covers introductions, RFP overview, project overview, and HUB requirements. The project scope includes all labor, equipment, materials, and supplies necessary to replace the existing fire alarm panel and fire pump with a new fire sprinkler system, according to specifications prepared by HUITT-ZOLLARS. Proposals must be submitted to Eric Shen at the University of Houston Purchasing Department, with late submissions not being accepted.

The presentation emphasizes the mandatory HUB Subcontracting Plan (HSP) requirement with a 21.1% HUB participation goal. All communication must be directed through the buyer, Eric Shen, with no contact permitted with other UH employees regarding the project. The HSP must be submitted in a separate sealed envelope with a USB drive, and the UH HUB Department offers a courtesy review with a 10-day turnaround time. A bonding letter is required, and contractors must demonstrate good faith efforts to meet the HUB subcontracting goals.

View the file

Other files

File Type Posted
ESBD_389280_1736444072147_EXHIBIT A - Drawings and Specifications.txt TXT text file
ESBD_389280_1737039995230_Addendum 2 - RFP730-25000 Houston Science Center New Fire Alarm Panel.pdf PDF
ESBD_389280_1737039518525_RFP730-25000 Sign-in Sheet.pdf PDF
ESBD_389280_1737040204317_HSP HUB Paperwork Instructions Video.docx DOCX document
ESBD_389280_1736787899023_Addendum 1 - Corrected Scope - RFP730-25000 NEW FIRE ALARM PANEL.docx DOCX document
ESBD_389280_1736460046792_EXHIBITS B THRU G.zip ZIP file
ESBD_389280_1736444010417_RFP730-25000 Houston Science Center New Fire Alarm Panel - FINAL2.pdf PDF
ESBD_389280_1737040083374_Purchasing-Pre-Proposal Meeting - Fire Alarm Panel & Pump.pptx PPTX presentation
ESBD_389280_1738706418961_Addendum 3 - RFP730-25000 Houston Science Center New Fire Alarm Panel.docx DOCX document
ESBD_389280_1737040204317_HSP HUB Paperwork Instructions Video.docx DOCX document
ESBD_389280_1737040083374_Purchasing-Pre-Proposal Meeting - Fire Alarm Panel & Pump.pptx PPTX presentation
ESBD_389280_1736444010417_RFP730-25000 Houston Science Center New Fire Alarm Panel - FINAL2.pdf PDF
ESBD_389280_1737039518525_RFP730-25000 Sign-in Sheet.pdf PDF
ESBD_389280_1736444072147_EXHIBIT A - Drawings and Specifications.txt TXT text file
ESBD_389280_1736787899023_Addendum 1 - Corrected Scope - RFP730-25000 NEW FIRE ALARM PANEL.docx DOCX document
ESBD_389280_1736460046792_EXHIBITS B THRU G.zip ZIP file
ESBD_389280_1737039995230_Addendum 2 - RFP730-25000 Houston Science Center New Fire Alarm Panel.pdf PDF
ESBD_389280_1737040204317_HSP HUB Paperwork Instructions Video.docx DOCX document
ESBD_389280_1736444010417_RFP730-25000 Houston Science Center New Fire Alarm Panel - FINAL2.pdf PDF
ESBD_389280_1736460046792_EXHIBITS B THRU G.zip ZIP file
ESBD_389280_1737039518525_RFP730-25000 Sign-in Sheet.pdf PDF
ESBD_389280_1737039995230_Addendum 2 - RFP730-25000 Houston Science Center New Fire Alarm Panel.pdf PDF
ESBD_389280_1736787899023_Addendum 1 - Corrected Scope - RFP730-25000 NEW FIRE ALARM PANEL.docx DOCX document
ESBD_389280_1736444072147_EXHIBIT A - Drawings and Specifications.txt TXT text file
ESBD_389280_1736460046792_EXHIBITS B THRU G.zip ZIP file
ESBD_389280_1736444010417_RFP730-25000 Houston Science Center New Fire Alarm Panel - FINAL2.pdf PDF
ESBD_389280_1736444072147_EXHIBIT A - Drawings and Specifications.txt TXT text file
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP730-25000

Houston Science Center New Fire Alarm Panel, Pump Replacement and Fire Sprinkler System

Mandatory Proposal Meeting

1/15/2025 @ 2:00 PM CT

Agenda Introductions RFP Overview—Eric Shen, Buyer 3 Project Overview—Frank Andrews, Huitt-Zollars HUB Overview Questions

RFP Overview

1.4 Schedule:

2.6 Submission of Proposals:

Proposals are due on or before the Submittal Deadline identified in Section 1.4. Proposals received after the Submittal Deadline will not be accepted or considered. Proposals must be delivered to the address below.

Eric Shen University of Houston Purchasing Department 5000 Gulf Freeway Building 1, Room 214 Houston, TX 77204-5015 purfpc@central.uh.edu

Communication Restriction:

Point of Contact is Eric Shen, purchasingFPC@uh.edu

All communication must go through the Buyer Eric Shen. Do not contact any other UH employees about this project.

RFP Overview

3.5 Bonding Letter - Required

Exhibit B - HUB Subcontracting Plan (“HSP”) and TIP Sheet is included and part of the Exhibits Package (Exhibit B).

HUB SUBCONTRACTING PLAN

Based on an analysis performed by the University’s Purchasing Department, subcontracting was determined to be probable for this contract. Therefore, a HSP will be required to be submitted with the Proposal.

The HUB Subcontracting Goal for this project is 21.1%

UH HUB Department offers a courtesy review. Contact HUB Operations Department at hubdocs@uh.edu.

10 day turn around time

Frequently Asked Questions and Answers Is a HSP Required?

Yes. UH Purchasing Department has determined that subcontracting is probable for this contract.

How do we submit the HSP?

Respondents must return the HSP plan in a separate envelope, in a USB, and it must be sealed with the reference number.

What is the HUB Goal for this project?

The HUB Subcontracting Goal for this RFP is 21.1%.

Do we HAVE TO Subcontract?

Successful respondents will be required to make a good faith effort to award subcontracts in at least the specified percentage of the value of the awarded contract to historically underutilized businesses (HUBs).

HSP Paperwork Instructions Video https://uofh-my.sharepoint.com/:v:/g/personal/dcampbe4_cougarnet_uh_edu/EUZ9BOply1lMqz-q4R2WuzwBzaxntlmcDDxVH57HqUsKRw?e=lHRQ6J

Project Overview Project Description. All labor, equipment, materials, and supplies necessary and reasonably inferable to replace existing fire alarm panel and fire pump with new fire sprinkler system in accordance with the drawings and specifications prepared by HUITT-ZOLLARS, a copy of which is attached hereto and incorporated herein as EXHIBIT A.

Questions?