ESBD_383072_1733498859708_RFQ 2024-085 Addendum 3.pdf
PDF 1 MB Posted
- Solicitation number
- RFQ2024-085
- Issued by
- Loving County, Wichita Falls City, Texas
About this file
This is Addendum #3 for RFQ 2024-085 issued by the City of Waco Purchasing Services for the Waco MPO Place Based Safety and Demonstration Projects. The addendum provides responses to questions regarding the implementation of six demonstration projects focused on safety improvements, with submissions due December 12, 2024, at 2:00 PM CT and a bid opening at 2:01 PM CT via Zoom Video and Dial-in at 1415 N. 4th St. Waco, Texas. The clarifications address coordination between the MPO and city permitting processes, collaboration with TxDOT, project timelines, and implementation requirements. The MPO confirms that while they don't have direct authority over municipal permitting, they will actively support the permitting process and work closely with TxDOT through their Safety Action Task Force.
The addendum clarifies that the project budget must include materials for all demonstration projects, though some in-kind material contributions are anticipated from cities and TxDOT. Professional Engineer (PE) sealed drawings will not be required as these are not classified as construction projects. The MPO maintains its goal of implementing all six demonstration projects as outlined in the RFQ, though they remain open to reassessment based on community input or other factors. The MPO does not anticipate significant delays related to permitting and approvals, as they will be responsible for coordinating any NEPA process with TxDOT.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchasing Services PO Box 2570 Waco, Texas 76702-2570
T: (254) 750 8062 F: (254) 750 8063 waco-texas.com
Date:
RFQ No:
Bid Opening Location: 1415 N. 4th St. Waco, Texas (Via Zoom Video & Dial-in)
Addendum No: 3 The above-mentioned bid invitation has been changed in the following manner. Sign and return addendum to the Purchasing Office by the closing time and date with your RFB/P/Q response. Returning this page signed by your authorized agent will serve to acknowledge this change. All other requirements of the invitation remain unchanged. If you have any questions, please call or stop by the Purchasing Office at the above address.
Commodity:
Contact:
December 5, 2024 2024-085 Waco MPO Place Based Safety and Demonstration Projects Paul Campos pcampos@wacotx.gov
Firm: ____________________________________________________________________________________
Address___________________________________________________________________________________
Signature of Person Authorized to Sign Bid:______________________________________________________________________
Signor's Name and Title (print or type):_____________________________________________________________________________
Date:____________________Telephone:___________________________Fax:_________________________
THE FOLLOWING IS BEING ISSUED AS ADDENDUM NO. 3
PLEASE REVIEW THE FOLLOWING PAGES
• Final Response to Open Questions.
Closing Time: December 12, 2:00 P.M. CT Opening Time: December 12, 2:01 P.M. CT
RFQ 2024-085 Addendum 3, Page 1
RFQ 2024-085 Addendum 3, Page 2
Addendum 3 to RFQ 2024-085: Waco MPO Place-Based Safety and Demonstration Projects
The following clarifications are provided in response to questions received regarding
RFQ 2024-085:
1. City/MPO Coordination for Efficient Permitting and Approval
• While the MPO does not have authority over municipal permitting, it will actively support applications for any required permitting and approvals to the greatest extent possible.
2. Coordination with TxDOT on Projects Impacting Their Jurisdiction
• The MPO collaborates closely with TxDOT, including through its Safety Action Task Force, which will confirm concurrence on proposed projects (see Task 6 of the RFQ).
• As demonstration projects are not classified as construction by TxDOT, coordination is anticipated to be positive and straightforward. The MPO will provide support for any necessary TxDOT permitting applications. The MPO will be responsible for coordinating with TxDOT for any NEPA process.
3. Project Timeline and Feasibility
• The project installation timeline is driven by the need to complete project installations, data collection, and the final report prior to grant closeout. The MPO does not anticipate significant delays related to permitting and approvals.
4. Budget for Materials
• The project budget must include materials for all demonstration projects. However, the MPO anticipates some in-kind material contributions from respective cities and TxDOT to support the effort.
5. Requirement for Signed/Sealed Drawings
• Signed/sealed drawings by a PE licensed in Texas will not be required for all demonstration projects, as these projects are not considered construction projects.
6. Flexibility in Number of Demonstration Projects
• The MPO’s goal is to implement six demonstration projects as outlined in the RFQ. A reduction in the number of projects is not anticipated nor desired. However, the MPO is open to reassessment if necessary due to community input or other factors. Submissions should assume projects at all six locations.
This addendum is issued to ensure all respondents have the same understanding of the expectations outlined in the RFQ.
| RFB 2024-007 Addendum 1 Bid Sheet.pdf |
| BID_PROPOSAL |
| 02-2022_MillOverlay_Plans_ADD1.pdf |
| C003 |
| C005-C012 SPPs |
| C000 SHEET INDEX-C005 SPECIAL PROJECT PROVISIONS (1 OF 8) |
| C000 SHEET INDEX-C006 SPECIAL PROJECT PROVISIONS (2 OF 8) |
| C000 SHEET INDEX-C007 SPECIAL PROJECT PROVISIONS (3 OF 8) |
| C000 SHEET INDEX-C008 SPECIAL PROJECT PROVISIONS (4 OF 8) |
| C000 SHEET INDEX-C009 SPECIAL PROJECT PROVISIONS (5 OF 8) |
| C000 SHEET INDEX-C010 SPECIAL PROJECT PROVISIONS (6 OF 8) |
| C000 SHEET INDEX-C011 SPECIAL PROJECT PROVISIONS (7 OF 8) |
| C000 SHEET INDEX-C012 SPECIAL PROJECT PROVISIONS (8 OF 8) |
| C403 |
| C403 CHIMNEY HILL TIMBERLEAF FIELDSTONE CHIMNEY RIDGE WILLOWBEND |
| Blank Page |
| Blank Page |
File details come from the government source that posted it. Updated .