About this file
This document is an Addendum #2 to a Request for Proposals (RFP) issued by Lamar University for the Vincent-Beck Stadium LED System Upgrades project, RFP #734-09192024-KM. The project involves upgrading the LED video display at the stadium. A voluntary pre-submittal conference will be held on September 27, 2024 at 10:00 AM. Proposals are due by October 11, 2024 at 2:00 PM local time. The RFP clarifies that the pre-bid meeting was made voluntary due to Hurricane Helene, and confirms that existing foundations can remain with primary steel poles being cut to grade, and that new foundations can be offset from existing foundations.
The contract opportunity is located in Texas, specifically in Johnson County. Pricing terms, set-asides, incumbent information, funding requirements and sources, and other salient details are not provided in this Addendum.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
FOR
VINCENT-BECK STADIUM
LED SYSTEM UPGRADES
RFP #734-09192024-KM
ADDENDUM 2
Submittal Due Date:
Friday, October 11, 2024
2:00 P.M. local time
A voluntary Pre-Submittal Conference will be held on
Friday, September 27, 2024 at 10:00 AM
Lamar University, Wayne A Reaud Building, Room 120
985 Jim Gilligan Way
Beaumont, TX 77705
REQUESTOR: Uber Displays
Project: Lamar - Vincent-Beck Stadium LED System Upgrades Spec / Drawing Reference Discipline: LED Bidder Question Owner/AJP Response
Please confrim exisitng foudnations can remain with primary steel poles being cut to grade.
Confirmed
Please confirm new foundations can be offset from existing foundations
Confirmed. Intent is to have video face as close to origiinal location bu shifting catwalks forward on columns if your structure design can allow.
Please confrim prebid meeting was mandatory for all prime bidders per section 1.12 of RFP.
Due to Hurricane Helene, the decision was made for the pre-bid meeting to be voluntary instead of canceling and rescheduleing the meeting.
REQUEST FOR INFORMATION FORM
| Addendum #2 734-09192024-KM Vincent-Beck Stadium LED System Upgrade |
| RFI Submittal Form - Uber Displays AJP |