ESBD_368991_1724082867681_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf

PDF 132 KB Posted

Attached to
HUSH HOUSE POWER RESTORATION BLDG 1395
Solicitation number
TMD24-ANG-WJ-24142008
Issued by
Harris County, Texas

About this file

This document is an attachment related to a state and local contract opportunity in Texas for Ellington Field (EF) Manufacturers' Services. The attachment outlines the requirements for manufacturer's services, including submittals, qualifications, fulfillment of specified minimum services, training schedule, training plan, and training of EF personnel. Key details include the need for a manufacturer's representative who is factory-trained and experienced, required training and documentation, and coordination with EF personnel for startup and post-startup training.

The related state and local contract opportunity is for the HUSH HOUSE POWER RESTORATION BLDG 1395 project, where TMD is seeking a contractor to remove and replace wire from existing conduit and install new 15 kilovolt (kV) wire for a transformer located at the 147th Attack Wing in Houston, Texas within Harris County. No additional details are provided regarding pricing, set asides, incumbents, funding, or other salient information.

View the file

Other files

File Type Posted
ESBD_368991_1724082976624_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_368991_1724082890585_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_368991_1724082931291_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082710316_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082606067_TMD24-ANG-WJ-24142008 HUSH HOUSE POWER RESTORATION BLDG 1395.pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082921642_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_368991_1724082954334_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
ESBD_368991_1724082965372_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082720968_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_368991_1724082686931_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082911427_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082867681_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_368991_1724082763544_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082988276_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_368991_1724082901306_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_368991_1724082626168_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.N - ELLINGTON AFB (EF) MANUFACTURERS’

SERVICES

PART 1 – GENERAL

1. DEFINITIONS

Person-Day: One person for eight (8) hours within regular Contractor working hours.

2. SUBMITTALS

A. Training Schedule: Submit not less than twenty-one (21) days prior to start of equipment installation and revise as necessary for acceptance.

B. Preliminary Training Plan: Submit within sixty (60) days after Notice to Proceed for approval by the Project Manager.

C. Final Training Plan: Submit after training coordination meeting.

D. Training Materials:

a. Submit written outlines of proposed training sessions not less than twenty-one

(21) days prior to scheduled training to be approved by the Project Manager.

b. Furnish complete training materials, to include operation and maintenance data as required in this section to be retained by each trainee.

E. Quality Control Submittals: When specified in the individual Specifications, submit:

a. Qualifications of Manufacturer’s Representative performing specified services.

b. Manufacturer’s Certificate of Proper Installation: On form appended to this section.

3. QUALIFICATION OF MANUFACTURER’S REPRESENTATIVE

A. Authorized representative of the manufacturer shall be factory trained and experienced in the technical applications, installation, operation, and maintenance of respective equipment, subsystem, or system. Additional qualifications may be specified elsewhere.

B. Manufacturer’s Representative subject to acceptance by the Project Manager. No substitute representatives will be allowed unless prior written approval by the Project

Manager has been given.

4. FULFILLMENT OF SPECIFIED MINIMUM SERVICES

A. Where manufacturers’ services are specified, furnish manufacturer’s qualified representative. Where time is necessary in excess of that stated in the Specifications for manufacturers’ services, additional time required to perform the specified services shall be considered incidental work.

B. Schedule manufacturer’s services to avoid conflicting with other onsite testing or other manufacturer’s onsite services.

a. Determine that all conditions necessary to allow successful testing have been met before scheduling services.

C. Only those days of service approved by the Project Manager will be credited to fulfill the specified minimum services.

D. If specified, manufacturer’s onsite services shall include as a minimum:

a. Assistance during product (system, subsystem, or component) installation to

ELLINGTON FIELD, HOUSTON, TX 21 May 2024 include observation, guidance, instruction of Contractor’s assembly, erection, installation or application procedures.

b. Inspection, checking, and adjustment as required for product (system, subsystem, or component) to function as warranted by manufacturer and necessary to furnish written approval of installation.

c. Revisiting the site as required to correct problems and until installation and operation are acceptable to the Project Manager.

d. Resolution of assembly or installation problems attributable to, or associated with, respective manufacturer’s products and systems.

e. Assistance during functional and performance testing and startup demonstration, and until product acceptance by the Project Manager.

f. Training of EF personnel in the operation and maintenance of respective product as required.

g. Completion of Manufacturer’s Certificate of Proper Installation (form enclosed at end of this section) with applicable certificates for proper installation and initial, interim, and final test or service.

h. Additional requirements as may be specified elsewhere.

5. TRAINING SCHEDULE

A. List specified equipment and systems with respective manufacturers that require training services of manufacturers’ representatives and show:

a. Estimated dates for installation completion.

b. Estimated training dates to allow for multiple sessions when several shifts are involved.

B. Adjust training schedule to ensure training of appropriate personnel as deemed necessary by the Project Manager, and to allow full participation by manufacturers’ representatives. Adjust schedule for interruptions in operability of equipment.

6. TRAINING PLAN

A. Preliminary Training Plan: If specified, and within sixty (60) days after Notice to

Proceed, submit for each proposed course to be approved by the Project Manager:

a. Title and objectives.

b. Training schedule.

c. Prerequisite training and experience of attendees.

d. Recommended types of attendees (e.g., managers, engineers, operators, maintenance).

e. Course description and outline of course content.

f. Duration.

g. Location (e.g., training center or site).

h. Format (e.g., lecture, self-study, demonstration, hands-on).

i. Instruction materials and equipment requirements.

j. Final Training Plan: Submit the following after training coordination meeting, if specified.

k. Updated versions of course descriptions from preliminary training plan.

l. Personnel who will attend each course.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

m. Schedule of training courses including dates, durations, and locations of each class.

n. Detailed course schedule for each day showing time allocated to each topic.

o. Resumes of instructors providing the training.

7. TRAINING BASE PERSONNEL

A. Furnish trained, articulate personnel to coordinate and expedite training, to be present during training coordination meetings with EF Personnel, and familiar with operation and maintenance manual information specified in Division 1 Section, “Operation and

Maintenance Data”.

B. Furnish manufacturers’ representatives for detailed classroom and hands-on training to EF personnel on operation and maintenance of specified product (system, subsystem, component) and as may be required in applicable Specifications.

a. Manufacturer’s Representative: Familiar with facility operation and maintenance requirements as well as with specified equipment.

C. Prestart up Training:

a. Coordinate training sessions with EF operating personnel and manufacturers’ representatives, and with submission of operation and maintenance manuals in accordance with Division 1 Section “Operation and Maintenance Data”.

b. Complete at least fourteen (14) days prior to actual startup.

D. Post-Startup Training: If required in Specifications, furnish and coordinate training of

EF operating personnel by respective manufacturer’s representatives.

8. SUPPLEMENTS

A. The supplements listed below, following “END OF SECTION,” are part of this

Specification.

a. Forms: Manufacturer’s Certificate of Proper Installation.