ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf

PDF 107 KB Posted

Attached to
HUSH HOUSE POWER RESTORATION BLDG 1395
Solicitation number
TMD24-ANG-WJ-24142008
Issued by
Harris County, Texas

About this file

This document is an attachment to a state and local contract opportunity related to quality control requirements for the Ellington AFB (EF) project in Houston, Texas. It outlines the quality assurance and control requirements for the installation of products, including monitoring quality control over suppliers, manufacturers, products, services, site conditions, and workmanship. The document specifies tolerances, references to industry standards, and the use of an independent inspecting and testing laboratory. It also requires manufacturers' field services and reports to be provided to the Project Manager.

The related state and local contract opportunity is for the HUSH HOUSE POWER RESTORATION BLDG 1395 project, which is seeking a contractor to remove and replace wire from existing conduit and install new 15 kilovolt (kV) wire for a transformer located at the 147th Attack Wing facility in Houston, Texas. The project is located in Harris County, Texas.

View the file

Other files

File Type Posted
ESBD_368991_1724082976624_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_368991_1724082890585_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_368991_1724082931291_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082710316_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082606067_TMD24-ANG-WJ-24142008 HUSH HOUSE POWER RESTORATION BLDG 1395.pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082921642_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_368991_1724082954334_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
ESBD_368991_1724082965372_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082720968_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_368991_1724082686931_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082911427_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082867681_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_368991_1724082763544_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082988276_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_368991_1724082901306_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_368991_1724082626168_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
ESBD_368991_1724082976624_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.G - ELLINGTON AFB (EF) QUALITY CONTROL

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Quality assurance – control of installation.

b. Tolerances.

c. References.

d. Mockup.

e. Inspecting and testing laboratory services.

f. Manufacturers’ field services and reports.

2. RELATED SECTIONS

A. Attachment G.T - Ellington AFB (EF) Post Award Submittals: Submission of manufacturers’ instructions and certificates.

B. Attachment G.M - Ellington AFB (EF) Material Equipment.

C. Attachment G.O - Ellington AFB (EF) Starting Of Systems.

3. QUALITY ASSURANCE – CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step-in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from the Project Manager before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform work by persons qualified to produce workmanship of specified quality.

F. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

4. TOLERANCES

A. Monitor tolerance control of installed Products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from the Project Manager before proceeding.

C. Adjust Products to appropriate dimensions; position before securing Products in place.

5. REFERENCES

A. For Products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date of Contract

Documents, except where a specific date is established by code.

C. Obtain copies of standards where required by product specification sections.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

D. The contractual relationship, duties, and responsibilities of the parties in Contract nor those of the Architect or the Project Manager shall not be altered from the Contract

Documents by mention or inference otherwise in any reference document.

6. INSPECTING AND TESTING LABORATORY SERVICES

A. Contractor shall employ and pay for specified services of an independent firm to perform inspecting and testing. The independent lab shall be approved by the Project

Manager prior to use and should be submitted in sufficient time to eliminate delay.

B. The independent firm will perform inspections, tests, and other services specified in individual specification sections and as required by the Project Manager. Test reports are required to be submitted within 3 working days of each test performed.

C. Inspecting, testing, and source quality control may occur on or off the project site.

Perform off-site inspecting or testing as required by the Project Manager.

D. Reports will be submitted by the independent firm to the Project Manager and the

Contractor, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.

F. Notify the Project Manager and independent firm in writing 24 hours prior to expected time for operations requiring services.

G. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

H. Testing or inspecting does not relieve Contractor to perform Work to contract requirements.

I. Retesting required because of non-conformance to specified requirements shall be performed by the same independent firm on instructions by the Project Manager.

Payment for all testing services (including re-testing) will be the responsibility of the

Contractor.

7. MANUFACTURERS’ FIELD SERVICES AND REPORTS

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to the Project Manager 30 days in advance of required observations. Observer subject to approval of the Project Manager.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

D. Submit report in duplicate within 30 days of observation to Architect for information if applicable.