ESBD_368991_1724082965372_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf

PDF 122 KB Posted

Attached to
HUSH HOUSE POWER RESTORATION BLDG 1395
Solicitation number
TMD24-ANG-WJ-24142008
Issued by
Harris County, Texas

About this file

This document is a Standard Operating Procedure (SOP) for Ellington Field (EF) in Houston, Texas, regarding the inadvertent discovery of unmarked burials. The SOP outlines the responsibilities and actions to be taken by various stakeholders, including installation leadership, training site managers, civil engineers, security police, public affairs, and legal representatives, when such discoveries occur. The triggering events include ground disturbance activities like construction, maintenance, off-road traffic, and outdoor recreation. The key steps outlined in the SOP include ceasing ground-disturbing activities, securing the discovery location, notifying the Environmental Manager, protecting the remains and artifacts, and initiating appropriate consultations if the remains are determined to be related to the Native American Graves Protection and Repatriation Act (NAGPRA).

The related state and local contract opportunity is for the Hush House Power Restoration Building 1395 project, located at the 147th Attack Wing in Houston, Texas. The Texas Military Department (TMD) is seeking a contractor to remove and replace wire from existing conduit and install new 15 kilovolt (kV) wire for a transformer at this location in Harris County, Texas.

View the file

Other files

File Type Posted
ESBD_368991_1724082976624_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_368991_1724082890585_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_368991_1724082931291_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082710316_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082606067_TMD24-ANG-WJ-24142008 HUSH HOUSE POWER RESTORATION BLDG 1395.pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082921642_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_368991_1724082954334_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082720968_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_368991_1724082686931_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082911427_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082867681_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_368991_1724082763544_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082988276_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_368991_1724082901306_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_368991_1724082626168_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
ESBD_368991_1724082976624_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.V - ELLINGTON AFB (EF), HOUSTON, TEXAS

STANDARD OPERATING PROCEDURE (SOP) FOR INADVERTENT

DISCOVERY OF UNMARKED BURIALS

20 Apr 22

Contact: Mr. Mark Garcia, Ellington Field Environmental Manager (CEV) 281-929-2013, mark.garcia.16@us.af.mil

Statutory References:

1. Native American Graves Protection and Repatriation Act

2. Archaeological Resources Protection Act

3. National Historic Preservation Act and its implementing regulations

Regulations:

1. 42 CFR 10

2. 32 CFR 229

3. 36 CFR Part 800

Applies to:

1. Installation leadership

2. Training Site Manager

3. Base Civil Engineer

4. Real Property Office

5. Security Police

6. Public Affairs Office

7. Judge Advocates Office

8. Maintenance, utilities, and grounds crews and foremen

9. Unit commanders and unit/activity personnel

10. Tenants and contractors

Typical Situations: Ground disturbance from construction involving digging, bulldozing, clearing, or grubbing, maintenance or repair activities, off-road traffic, field units on exercise, outdoor recreation, observation of eroded areas.

Typical Triggering Event: Discovery of unmarked burial(s), including Native American burials or cemeteries from which headstones were relocated but not the physical remains.

Policy: In the event that an unanticipated discovery of cultural artifacts occurs, activity in the immediate vicinity should cease until an assessment of the materials can be made.

The unit commander/supervisor should be notified immediately so the CEV can be contacted.

Procedures: This section describes specific actions to be taken for discovery of unmarked burials. The flow chart (figure 5-3) is intended to be used by unit/activity level personnel, unit commanders, and similar personnel as a decision-making guide when inadvertent discoveries of burials are made as described under the applicability section of this SOP.

mailto:mark.garcia.16@us.af.mil https://www.nps.gov/subjects/nagpra/index.htm https://www.fs.usda.gov/lei/archeological-resources-protection.php#:~:text=It%20governs%20the%20excavation%20of,archaeological%20collections%20from%20those%20sites.

https://www.achp.gov/sites/default/files/2018-06/nhpa.pdf https://www.ecfr.gov/current/title-42/chapter-I/subchapter-A/part-10 https://www.ecfr.gov/current/title-32/subtitle-A/chapter-I/subchapter-M/part-229 https://www.wbdg.org/ffc/fed/code-federal-regulations/36-cfr-part-800#:~:text=Section%20106%20of%20the%20National,to%20comment%20on%20such%20undertakings.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

Scenario I: inadvertent discovery of burials.

A. Unit commander, environmental liaison, PA, Unit/activity personnel

a. Goals: understand the procedure when burials are inadvertently discovered so that the remains can be adequately protected.

B. Tasks:

a. Cease ground-disturbing activity when possible, human remains or burials are observed or encountered.

b. Unit personnel will report any observations or discoveries of human remains or burials immediately to the unit commander or facility manager and they will in turn notify the CEV immediately. They will await instructions from

CEV.

c. Secure the discovery location(s). Examine the location of the discovery to ensure that it has been properly secured. Take appropriate measures to further secure location if needed.

d. Coordinate with CEV on where and when activities can resume and give direction to the construction superintendent.

C. Environmental Manager

a. Goals: ensure that when each discovery occurs procedures are followed that will protect and properly treat any remains that are discovered.

D. Tasks:

a. ensure the site location and materials are properly protected.

b. Provide unit commander with necessary information so burials can be protected/avoided, etc.

c. ensure that all remains, and artifacts are accounted for and properly labeled and packaged if removed from the ground.

d. notify the installation commander.

e. notify the medical examiner.

f. determine if the remains and objects are NAGPRA related and initiate appropriate consultation if necessary.