ESBD_368991_1724082686931_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf

PDF 56 KB Posted

Attached to
HUSH HOUSE POWER RESTORATION BLDG 1395
Solicitation number
TMD24-ANG-WJ-24142008
Issued by
Harris County, Texas

About this file

This document is an attachment to a state and local contract opportunity related to coordination and meetings for the Ellington Field (EF) project in Houston, Texas. The attachment outlines requirements for contractor coordination, preconstruction meetings, progress meetings, and pre-installation meetings. Key details include scheduling and administration of meetings, required attendance, and meeting agenda items such as reviewing work progress, identifying problems, and maintaining quality and schedule. The attachment also covers examination and preparation requirements for the contractor prior to commencing work.

The document does not provide details on the product or service being procured, quantities, response dates, award information, or contract term. It focuses solely on the administrative and coordination requirements for the contractor throughout the project.

View the file

Other files

File Type Posted
ESBD_368991_1724082976624_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_368991_1724082890585_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_368991_1724082931291_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082710316_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082606067_TMD24-ANG-WJ-24142008 HUSH HOUSE POWER RESTORATION BLDG 1395.pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082921642_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_368991_1724082954334_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
ESBD_368991_1724082965372_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082720968_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_368991_1724082686931_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082911427_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082867681_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_368991_1724082763544_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082988276_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_368991_1724082901306_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_368991_1724082626168_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_368991_1724082829837_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_368991_1724082792520_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_368991_1724082698512_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_368991_1724082778254_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_368991_1724082942443_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_368991_1725886672960_Addendum 1 - TMD24-ANG-WJ-24142008.pdf PDF
ESBD_368991_1724082650762_ATTACHMENT G.3 Pricing Schedule.pdf PDF
ESBD_368991_1724082747289_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_368991_1724082996919_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_368991_1724082857255_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_368991_1724082731553_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_368991_1724082674402_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_368991_1724082804482_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_368991_1724082841358_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_368991_1724082636922_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_368991_1724082818767_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_368991_1724082663749_ATTACHMENT G.4 TMD Standard Terms and Conditions.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.B - ELLINGTON AFB (EF) COORDINATION AND

MEETINGS

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Coordination

b. Preconstruction meeting

c. Progress meetings

d. Pre-installation meetings

e. Examination

f. Preparation

2. COORDINATION

A. Coordinate scheduling, submittals, and Work of the various sections of the Project

Manual to assure efficient and orderly sequence of installation of interdependent construction elements, [with provisions for accommodating items installed later].

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with line of building.

Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas [except as otherwise indicated], conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and cleanup of Work of separate sections in preparation for

Substantial Completion.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

3. PRE-CONSTRUCTION MEETING

A. The Project Manager will schedule a meeting after Notice of Award.

B. Agenda:

a. Distribution of Contract Documents

b. Submission of list of Subcontractors, list of Products, schedule of values, and proposed construction schedule.

c. Designation of personnel representing the parties in Contract

d. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures

e. Scheduling

f. Safety plan submittal

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

4. PROGRESS MEETINGS

A. The Contractor will in Coordination with the Project Manager:

a. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals, every 2-weeks is preferred.

b. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

c. Review coordination with related work

d. Provide written documentation of the meeting minutes for review and acceptance by all present within 3 working days of each meeting.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, the

Project Manager as appropriate to agenda topics for each meeting.

C. Agenda:

a. Review minutes of previous meetings

b. Review of Work progress

c. Field observations, problems, and decisions

d. Identification of problems which impede planned progress.

e. Review of submittals schedule with emphasis on Critical Path Items and status of submittals

f. Review of off-site fabrication and delivery schedules

g. Maintenance of progress schedule

h. Corrective measures to regain projected schedules.

i. Planned progress during succeeding work period.

j. Coordination of projected progress

k. Maintenance of quality and work standards

l. Effect of proposed changes on progress schedule and coordination

m. Other business relating to Work.

5. PRE-INSTALLATION MEETING

A. When required in individual specification sections, convene a pre-installation meeting at work site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the

C. specific section.

D. Notify the Project Manager four days in advance of meeting date.

E. Contractor will prepare agenda and preside at meeting:

a. Review conditions of installation, preparation, and installation procedures

b. Provide written documentation of the minutes of the meeting within 3 working days of each meeting.

PART 2 – EXECUTION

1. EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural attachment of new Work being applied or attached.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct location.

2. PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply any manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.