ESBD_368299_1724861905455_MCD_CP577221_24JOC3700_ Addendum_1.pdf
PDF 625 KB Posted
- Solicitation number
- 24JOC3700
- Issued by
- Jeff Davis County, Texas
About this file
This document is an Addendum to the Solicitation Documents for an Indefinite Delivery/Indefinite Quantity (IDIQ) General Construction Services contract for the University of Texas at Austin's McDonald Observatory (MCD) project, identified as RFP 24JOC3700 and Project # CP577221. The Addendum provides clarifications and responses to questions related to the number of key personnel required, the need for a cover letter, and the number of subcontractors that can be listed. There are no changes to the general specifications or requirements.
The IDIQ contract is for a master agreement to provide Job Order Contract (JOC) services for general construction projects of all types at all locations and buildings at the MCD. The contract will cover a variety of general construction services, including renovation, concrete work, site work, mechanical and electrical system upgrades, fire protection, life safety, and utility infrastructure systems. The University is seeking qualified JOC providers, with an emphasis on qualifications rather than a specific number of personnel.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE UNIVERSITY OF TEXAS AT AUSTIN
Planning, Design & Construction
1301 E. Dean Keeton Street, FC1 • Austin, Texas 78722 • H9610 • 512-471-3042 https://pmcservices.utexas.edu/
CAM/MCD CP577221 08272024 ADD1-1
August 27, 2024
ADDENDUM:
To: All Interested Proposers
From: Trina Bickford, Assistant Director, Contracts
Re: ADDENDUM NO. 1 to the Solicitation Documents for
Indefinite Delivery/Indefinite Quantity (IDIQ) General Construction Services CAM/McDonald Observatory
RFP 24JOC3700 Project # CP577221
This Addendum is a part of the Documents for the above-named project and shall become an integral part of the originally issued Solicitation Documents dated 7/16/2024. Wherein the items of Addenda differ from the original Specifications, this Addendum shall take precedence. All other terms and conditions not specifically affected by this Addendum will remain unchanged. Revise the Specifications referenced below as described. This Addendum contains sheets ADD1-1 through ADD1-2.
Proposer shall acknowledge receipt of all Addenda by notation in response.
I. GENERAL
None
II. SPECIFICATIONS
None
III. CLARIFICATIONS
QUESTIONS/ANSWERS: The following questions received against the referenced solicitation - corresponding responses are included. Questions may have been edited and/or combined for clarity.
Question 1: Does the University have requirements for having a minimum number of people in key positions, such as safety officer, assistant project manager, quality control manager, etc.? If so, is there a minimum or maximum number of people required on the proposed team?
Response 1: The University does not require a set number of personnel. Proposers must consider the potential projects and workload, and base their proposal on assignment of an appropriate number of qualified staff members
ADDENDUM NO.1
RFP: 24JOC3700
McDonald Observatory JOC IDIQ
CAM/MCD CP577221 08272024 ADD1-2
necessary to accomplish the work while fulfilling general safety and quality control requirements listed in the RFP. Work levels will fluctuate and the awarded Proposer must be responsive to changes, making adjustments to staffing levels as needed. The University’s priority is to have a qualified JOC provider, meaning qualifications rather than quantity of personnel are key.
Question 2: Is a cover letter required as a part of submission no. 2?
Response 2: A cover letter is not a mandatory requirement but proposers may include one if desired to summarize their response in submission no. 2.
Question 3: (Reference Section 8.2.1.3) Is there a minimum or maximum number of subcontractors that may be listed in response to this section requesting a list of typically used major subcontractors?
Response 3: There is no minimum or maximum – the University would like to evaluate the subcontractors that will typically be used on projects at McDonald Observatory.
END OF ADDENDUM NO. 1