This document is an Addendum No. 2 for Request for Bid (RFB) 2024-055 issued by the City of Waco, Texas for the Water Transmission / American Plaza to Exchange Parkway – Phase II project. The project involves the construction of approximately 6,800 linear feet of 30-inch C-900 PVC DR 18 PVC water line, a 745 linear foot bore and encase construction utilizing 42-inch steel pipe for TxDOT and Union Pacific Railroad crossings, and associated work. The bid opening date has been extended to August 21, 2024 at 2:00 PM CT. The addendum provides clarification on construction requirements, contractor questions and answers, and additional drawing details.
The project is a unit price bid, and the contractor will be responsible for removing all spoils from the project site. Dewatering of the trench will be required, and a dewatering plan must be submitted for approval. Compensation for dewatering activities is included in the Groundwater Occurrence bid item.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchasing Services Post Office Box 2570
Waco, Texas 76702-2570 Phone: 254-750-8098
Fax: 254-750-8063 melaniew@wacotx.gov
CITY OF WACO www.waco-texas.com
Date: 07/22/2024
RFB No: 2024-055 Commodity: Water Transmission – American Plaza to Exchange Parkway – Phase II Purchasing Agent: Melanie Wade
Closing Time: 2:00 P.M. CT, Wednesday, August 21, 2024 Opening Time: 2:01 P.M. CT, Wednesday, August 21, 2024
RFB Opening Location: Via Zoom and Dial In
Addendum No: 2 The date has been extended for question submissions to August 13, 2024 @ 5:00 PM CT.
The date has been changed for bid submissions to August 21, 2024 @ 2:00 PM CT.
See attached for clarifications, questions answered and drawings.
The above-mentioned RFB invitation has been changed in the following manner. Sign and return addendum to the Purchasing Office by the closing time and date with your RFP response. Returning this page signed by your authorized agent will serve to acknowledge this change. All other requirements of the invitation remain unchanged. If you have any questions, please call or stop by the Purchasing Office at the above address.
Firm:
Address
Signature of Person Authorized to Sign Bid:
Signor's Name and Title (print or type):
E-mail Address:
Date: Telephone: Fax:
mailto:melaniew@wacotx.gov http://www.waco-texas.com/
BID NUMBER:
DATE:
TIME: CENTRAL
QUICK LINK:
MEETING ID:
DIAL IN NUMBER:
PASS CODE:
ADDITONAL
INFORMATION:
BID NUMBER:
DATE:
TIME: CENTRAL
QUICK LINK:
MEETING ID:
DIAL IN NUMBER:
PASS CODE:
ADDITONAL
INFORMATION:
PRE BID/ PROPOSAL
BID/ PROPOSAL OPENING
ZOOM ACCESS INSTRUCTIONS & ADDITIONAL INFORMATION
Rev. 1
RFB 2024-055 Page 3 https://wacotx.zoomgov.com/j/1604675079?
https://wacotx.zoomgov.com/j/1609620532?
July 2024 Project RFB 2024-055 Addendum No. 2 00 91 13 - 1
ADDENDUM 2
Project Name: Water Transmission/American Plaza to Exchange Parkway, Phase II Project No.: RFB 2024-055 Owner: City of Waco Engineer: CP&Y, Inc. dba STV Infrastructure
This addendum forms a part of the Contract Documents and modifies the original Project Manual dated June 2024 and Addendum 1. Bidder shall acknowledge receipt of this addendum in the space provided below and in the space provided on the Bid Form. Failure to do so may subject Bidder to disqualification.
BID OPENING:
Bid will be received on August 21st at 2:00 PM.
CLARIFICATION:
Underground piped utilities shall not be constructed, or the pipe laid in the presence of water of any depth or accumulation. All water shall be removed from the excavation prior to the placement of pipe embedment placement to ensure a dry firm granular bed on which to place the embedment. The trench excavation shall be maintained in an unwatered condition until all embedment and a minimum of the first course of backfill installed, compacted and tested. The presence of water, of any nature in the trench, will dictate use of the appropriate embedment detail in accordance with the City of Waco details.
The Contractor is responsible for developing and submitting a dewatering plan for review and approval by the City. Removal of water may be accomplished by bailing, pumping, or by a well-point installation as conditions warrant. The Construction Inspector will review and confirm the conditions that dictate use of the dewatering measures.
If the excavation cannot be dewatered to the point where pipe bedding is free of mud, a concrete seal of 2,000 PSI concrete with a minimum thickness of 3 inches shall be placed in the bottom of the excavation.
Bid item 69, Groundwater Occurrence, will provide compensation for the Contractor for any of the required items of work associated with required dewatering of the trench, including any of the necessary items above as well as wrapping of the embedment. The bid item will be paid at the plan quantity of the pipe installation in linear feet.
CONTRACTOR QUESTIONS:
No. Question Answer
Do the valves 16", 30" and 42" need to have any kind of gearing, spur or beveled? There are no specs given.
See Addendum 1, Question 3
Project RFB 2024-055 Addendum No. 2 00 91 13 - 2
No. Question Answer
2 Is there a place to stockpile on site?
There is limited room to stockpile Valves and other appurtenances at the Owen Elevated Tower site. The Contractor is responsible for locating and acquiring additional storage and stockpile locations.
What material will be required for the vent piping on the air release assemblies since galvanized & PVC piping are allowed and compression fittings are not made for 4" copper per note #2 on detail W-22 & W-23.
See revised details for the 4” ARV construction, Sheet C455 & C456 (attached)
Will a detail be provided for the in-street & off-street 4" combination air & vacuum assembly? The details provided on sheet C411 & C412 are for a 2" assembly.
Updated details of the ARV for in street and off street conditions are provided, See Sheet C455 & C456 (attached)
Can the city confirm double valve isolation will be performed to install the 42" x 30" DIP tee at station 0+08.70?
And will solid sleeves be required on the south side of the tee and the north side of the 42" valve?
To install the 42”x30” Tee on the existing 42” water line, the 42” line will be isolated by closure of the valves as shown on Exhibit A (attached). Any necessary dewatering of the line during the connection process will be at the Contractor’s expense and is included in the applicable bid item. The connection will need to occur at off peak hours. Solid sleeves may be required to connect to the existing 42” line.
Is the mentioned project a lump sum or a unit price bid?
The project is a unit price bid
Do we have to haul off spoils or is there a nearby place to stockpile utility spoils?
All spoils will need to be removed from the project site. It is the Contractor’s means and Methods as to how this occurs.
What type of base should we use if needed?
The requirements for surface replacement and construction methods are located in the plan set.
DRAWINGS:
Add: Construction drawings C455 and C456 are included with this addendum
Please acknowledge receipt of this Addendum No. 2 by signing below and submitting with the Bid.
Acknowledged:
By:
Title:
--~E OF 7"'\\ -~-~P. -=.J- ~ ,, ,. -;, .. •· ·•;•':'f,s, .
,,... ·. 'I , :~., ~ DAVID L. MAREK I
r··~················ .. ···········S ,,~··. 83327 /9:f • o·. ,s>~. Q ··~, 1,-<-i•· .. 9,sre.~~ .. ·~.;' ,,.s-s,o····· .. •~~G - ,,, /VAL~ - '·'t.._,..., ... -
Project RFB 2024-055 Addendum No. 2 00 9113 - 3
NOTES:
1. FRAME AND COVER SHALL BE 30 IN. X 36 IN. 1/4 IN. HINGED CHECKER PLATE.
2. WATER: NO SWEATED JOINTS, GALVANIZED OR PVC PIPE WILL BE ACCEPTED. USE DUCTILE IRON PIPE WITH FLANGED FITTINGS.
3. PIPE VENT OPENING SHALL BE 12 IN. ABOVE TOP OF CONCRETE VAULT
4. CONCRETE VAULT SHALL BE CONCRETE PRODUCTS, INC. MODEL "M.V.-8-H.L." OR PRE-APPROVED EQUAL.
5. AIR RELEASE VALVES SHALL BE PLACED IN AREAS NOT SUBJECT TO SUBMERGENCE AND OUTSIDE OF TRAFFIC AREAS.
6. THE PLACEMENT OF VAULT SHALL BE ON CITY RIGHT-OF-WAY OR WITHIN APPROPRIATE EASEMENTS AND SHALL BE LOCATED IN SUCH A WAY AS TO CAUSE THE LEAST AMOUNT OF SITE
DISTURBANCE TO RESIDENTS AND TO NOT CREATE A SIGHT OBSTRUCTION FOR TRAFFIC.
7. AIR VENT DISCHARGE SHALL BE LOCATED AND PROTECTED TO ACCOMMODATE SITE CONDITIONS. BOLLARDS OR ENCLOSURE DESIGN SHALL BE SUBMITTED TO CITY OF WACO FOR
APPROVAL. VAULT SHALL BE LOCATED AS CLOSE AS POSSIBLE TO PROPERTY LINES.
8. MINIMIZE ANGLES IN VENT PIPE/TUBING, HORIZONTAL LENGTHS TO BE SLOPED DOWN (NOMINAL 2%) TOWARDS ARV.
16 MESH
SCREEN
NON-CORROSIVE
TERMINATION
VENT CAP
COVER 9 IN. 6 IN. ABOVE GROUND
ENCLOSURE PER PLANS (SITE SPECIFIC TO THE PROJECT)
ELBOW MUST POINT STRAIGHT DOWN
IN
4" DISCHARGE LINE,
DUCTILE IRON PIPE
WATER
30 IN.
IN
48 IN.
PLAN VIEW
4" AIR RELEASE VALVE: CLA-VAL
SERIES 33A COMBINATION AIR
RELEASE AND VACUUM BREAKER
VALVE, PRESSURE CLASS 150 LB
THREADED X FLANGE
12 IN. MIN
ALL SIDES
4" RESILIENT SEAT GATE
VALVE W/ HAND WHEEL
SCALE : NTS
4" AIR RELEASE VALVE AND MANHOLE VAULT (OFF STREET)
8" X 4" FLANGED DIP REDUCER
MANF KNOCK OUT OR SMOOTH CORE
IN MANHOLE WALL FOR PIPE WITH 1
IN. CLEARANCE
30" X 8" MJ X FLANGED DIP TEE
FILL BOTTOM OF MANHOLE WITH
AGGREGATE MEETING ASTM 57
SPECIFICATIONS FROM BOTTOM OF
FLANGE TO 6 IN. BELOW WATER LINE
C455
4" A
IR
R
EL
EA
SE
V
AL
VE
A N
D M
AN
H
O
LE
V
AU
LT
(O
FF
S
TR
EE
T)
DLM
CDG
RDO
WIFI2200448
N O
R
EV
IS
IO
N
BY
D
AT
E
VE
R
IF
Y
SC
AL
E
BA
R L
EN
G
TH
E
Q U
AL
S
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IN
G
. V
ER
IF
Y
LE
N
G
TH
O N
T H
IS
S
H
EE
T
AN
D A
D
JU
ST
S
C
AL
E
AC
C O
R D
IN
G
LY
DESIGN:
DRAWN:
REVIEW:
CP&Y:
SHEET
PR
IN
TE
D
B Y:
S cu llS
D
AT
E:
/2 2/
:2
2:
A M
FI
LE
P
AT
H : I
:\P ro je ct s\ C
W
AC
-3 in W
L O w en
-S ch ro ed er -M al l t o M al l\0
8_ Pl an s_
D ra w in gs \2
0_ Sh ee ts
\3
W L\
C W
AC
5- C
0-
D
ET
AI
LS
.d w g, C
CLIENT:
W
AT
ER
T
R
AN
SM
IS
SI
O
N / A
M
ER
IC
AN
P
LA
ZA
T
O
EX
C H
AN
G
E
PA
R
KW
AY
PH
AS
E
II
1"
06/11/2024
R
TE
XA
S R
EG
IS
TE
R
ED
E
N G
IN
EE
R
IN
G F
IR
M
TB
PE
F -1
07/22/2024
AutoCAD SHX Text
DAVID L. MAREK
AutoCAD SHX Text #83327
AutoCAD SHX Text A
AutoCAD SHX Text X
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text E
AutoCAD SHX Text O
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text A
AutoCAD SHX Text F
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text G
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text G
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text R
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text L
NOTES:
1. FRAME AND COVER SHALL BE 30 IN. X 36 IN. 1/4 IN. HINGED CHECKER PLATE.
2. WATER: NO SWEATED JOINTS, GALVANIZED OR PVC PIPE WILL BE ACCEPTED. USE DUCTILE IRON PIPE WITH FLANGED FITTINGS.
3. PIPE VENT OPENING SHALL BE 12 IN. ABOVE TOP OF CONCRETE VAULT
4. CONCRETE VAULT SHALL BE CONCRETE PRODUCTS, INC. MODEL "M.V.-8-H.L." OR PRE-APPROVED EQUAL.
5. AIR RELEASE VALVES SHALL BE PLACED IN AREAS NOT SUBJECT TO SUBMERGENCE AND OUTSIDE OF TRAFFIC AREAS.
6. THE PLACEMENT OF VAULT SHALL BE ON CITY RIGHT-OF-WAY OR WITHIN APPROPRIATE EASEMENTS AND SHALL BE LOCATED IN SUCH A WAY AS TO CAUSE THE LEAST AMOUNT OF SITE
DISTURBANCE TO RESIDENTS AND TO NOT CREATE A SIGHT OBSTRUCTION FOR TRAFFIC.
7. IF WATER MAIN IS IN STREET, VAULT SHALL BE SET 2 FT. BEHIND CURB, UNLESS OTHERWISE SHOWN IN PLANS.
8. AIR VENT DISCHARGE SHALL BE LOCATED AND PROTECTED TO ACCOMMODATE SITE CONDITIONS. BOLLARDS OR ENCLOSURE DESIGN SHALL BE SUBMITTED TO CITY OF WACO FOR
APPROVAL. VAULT SHALL BE LOCATED AS CLOSE AS POSSIBLE TO PROPERTY LINES.
9. MINIMIZE ANGLES IN VENT PIPE/TUBING, HORIZONTAL LENGTHS TO BE SLOPED DOWN (NOMINAL 2%) TOWARDS ARV.
10. MINIMIZE HORIZONTAL DISTANCE BETWEEN MAIN AND ARV.
11. SEAL ALL MANHOLE PENETRATIONS WITH LINK-SEAL PER MANUFACTURES RECOMMENDATIONS.
12. 2 IN. X 2 IN. GALVANIZED SUPPORT ANCHORED TO WALL ON BOTH SIDES.
16 MESH SCREEN
NON-CORROSIVE
TERMINATION VENT CAP
4" VALVE CLA-VAL SERIES 33A
COMBINATION AIR RELEASE AND
VACUUM BREAKER VALVE, PRESSURE
CLASS 150 LB THREADED X FLANGE.
IN
SCALE : NTS
4" AIR RELEASE VALVE AND MANHOLE VAULT (IN STREET)
ELBOW MUST POINT
STRAIGHT DOWN
2 FT. NOMINAL
COVER 9 IN.
2 FT. NOMINAL
6 IN. ABOVE NATURAL GROUND
4" RESILIENT SEAT GATE VALVE
2 - 4" 45° MJ DIP BENDS
8" X 4" MJ X MJ DIP REDUCER
30" X 8" MJ X MJ DIP TEE
4" DISCHARGE LINE,
DUCTILE IRON PIPE
12 IN. MIN
ALL SIDES
IN
. M
IN
BO
TT
O M
FILL BOTTOM OF MANHOLE
WITH AGGREGATE
MEETING ASTM 57
SPECIFICATIONS FROM
BOTTOM OF 45° BENDS
4" FLANGED 45° DIP BEND
4" MJ X FLANGED 45° DIP
BEND
12 9
1% MIN
4" DIP, ENCAPSULATED
IN POLYWRAP
WATER
30 IN.
IN
48 IN.
" M
IN
PLAN VIEW
ENCLOSURE PER PLANS (SITE
SPECIFIC TO THE PROJECT)
C456
4" A
IR
R
EL
EA
SE
V
AL
VE
A N
D M
AN
H
O
LE
V
AU
LT
(IN
S
TR
EE
T)
DLM
CDG
RDO
WIFI2200448
N O
R
EV
IS
IO
N
BY
D
AT
E
VE
R
IF
Y
SC
AL
E
BA
R L
EN
G
TH
E
Q U
AL
S
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IN
G
. V
ER
IF
Y
LE
N
G
TH
O N
T H
IS
S
H
EE
T
AN
D A
D
JU
ST
S
C
AL
E
AC
C O
R D
IN
G
LY
DESIGN:
DRAWN:
REVIEW:
CP&Y:
SHEET
PR
IN
TE
D
B Y:
S cu llS
D
AT
E:
/2 2/
:2
2:
A M
FI
LE
P
AT
H : I
:\P ro je ct s\ C
W
AC
-3 in W
L O w en
-S ch ro ed er -M al l t o M al l\0
8_ Pl an s_
D ra w in gs \2
0_ Sh ee ts
\3
W L\
C W
AC
5- C
0-
D
ET
AI
LS
.d w g, C
CLIENT:
W
AT
ER
T
R
AN
SM
IS
SI
O
N / A
M
ER
IC
AN
P
LA
ZA
T
O
EX
C H
AN
G
E
PA
R
KW
AY
PH
AS
E
II
1"
06/11/2024
R
TE
XA
S R
EG
IS
TE
R
ED
E
N G
IN
EE
R
IN
G F
IR
M
TB
PE
F -1
07/22/2024
AutoCAD SHX Text
DAVID L. MAREK
AutoCAD SHX Text #83327
AutoCAD SHX Text A
AutoCAD SHX Text X
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text E
AutoCAD SHX Text O
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text A
AutoCAD SHX Text F
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text G
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text G
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text R
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text L
| BID NUMBER: RFB 2024-055 |
| MM/DD/YY: |
| TIME CENTRAL: |
| QUICK LINK: |
| MEETING ID: |
| DIAL IN NUMBER: |
| PASS CODE: |
| FREE COMMENT TEXT: |
| BID NUMBER_2: RFB 2024-055 |
| MM/DD/YY2: 08/21/24 |
| TIME CENTRAL: 2:00 P.M. (CT) |
| QUICK LINK_2: https://wacotx.zoomgov.com/j/1609620532? |
| MEETING ID_2: 160 962 0532 |
| DIAL IN NUMBER_2: 1 551 285 1373 |
| PASS CODE_2: 444962 |
| FREE COMMENT TEXT_2: Via Zoom Video and Dial In |
File details come from the government source that posted it. Updated .